Sneddon Daily Project Log

Add: Site report | Memo

Tim Beaulieu entered the following on 06:09:30 Nov/20/2009:
Weather Conditions:Sunny and clear through out the day high in the lower 70's
Date
:
November 19, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Jeff Collins, Danny Tracy, Ed E
Subcontractors on site: CCS-4, MMC-2, JTS-1, Vaught-1, AGA-1, ACC-6, Big Horn-12, SCE&G-2, Joey-2, Screening-1, Direct TV-3
Visitors: The owners were on site today to review progress
Equipment Used: The back hoe was returned to the shop yesterday. The fork lift, roller, and bob cat were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior floor finish was underway and completed. The entire house is being cleaned. Finish grade work was being completed around all decks. Fuax finishing was being completed in the master bedroom. All appliances were being run though out. The main gas meter was installed and gas lanterns fired, all other related gas appliances are now running with the exception of the outdoor kitchen and garage water heater. Water has been running and ice is being made. Garage doors were adjusted a final cleaning of the tracks is still needed. HVAC unit installation was completed the units have been tested and found to be functional. Interior paint touch ups were being completed through out. Screen porch hardware was being installed through out. Cobble stone installation is progressing well we are currently approaching the 50 percent mark. Electrical trim out was being completed through out. Service yard fencing was being laid out and post installed. We will had two additional gates to the design to service the generator. Direct TV was on site and installed the dish on the main house chimney. They have 100 percent signal and 4 wires are stubbed out in the attic. Straw was being spread around the main house and garage for dirt control.


Tim Beaulieu entered the following on 20:41:03 Nov/18/2009:
Weather Conditions:Sunny and clear, High in the low 70's
Date
:
November 18, 2009
Employees Working on site: Tim Beaulieu, Ed E, Greg Barber, Jeff Collins, Danny Tracy,
Subcontractors on site: CCS-5, HHS-2, SCE&G-2, Cuda-3, ACC-5, Big Horn-13, Palmetto Gas-2, DSG Screening-1, Clover Glass-2, MMC-2, Clealand-1, Culligan Water-2, Prestige Stone-1, Distinctive Marble and Granite-1,
Visitors: The home owners were on site to view progress.
Equipment Used: The Big Horn bobcat was used for 5 hours for grade and driveway work. The roller was used for two hours on the driveway. The forklift was used for 2 hours to stage material.
Urgent Items and Equipment Needed
:
No forseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior painting was being completed in the main house foyer. Security trim out was being completed through out. The cobble stone circle installation was underway and is 25 percent completed. HVAC units were started and tested. The units have been shut off will painting and floor finishing is on going. Electrical trim out is on going. Two mirrors in the master bedroom suite were installed. The built in mirror in the second floor guest bath was completed. Exterior paint touch ups were underway and progressing well. Site clean up and final grading is on going. The fence post were being cut down and prepared for fencing. Appliances were being run through out the day. The laundry room built in ironing board installation was completed. An ironing boards door is being fabricated at MMC. The water softener and RO system was installed and tested. SCE&G did not install the gas meter today. They will be on site in the AM to complete the installation. The screen porch screening was started today. All screen porch doors were hung. The daybed was positioned and mounting points laid out. 2 Steel fireplace box plates were picked up in Oldfield and delivered to the site and installed in the fireplaces. Gas log installation is scheduled for Monday. Cabinet hardware was being installed in the kitchen. The main house foyer was painted. The foyer floor protection was removed and the floor cleaned. YRP was contacted they will not set service yard equipment till Monday and they will schedule their final inspection for Dec 7-8.


Tim Beaulieu entered the following on 18:51:32 Nov/17/2009:
Memo:
Sneddon Daily Site Report 
November 11-17 2009 
The following report is entered due to networking 
difficulties experience during 11-17th of November.  

Interior painting is on going and the majority of the work 
is expected to be completed by Thursday. Perm Service 
inspection was passed and SCEG was on site to install main 
feeders and meter. Gas line finishing work was underway and 
is expected to be completed on Thursday. Water supply and 
sewer lines are installed through out. Water is being run 
through all fixtures. All appliances have been installed 
and testing is underway. HVAC units were being installed, 
unit installation is nearing completion and testing is 
expected to begin on Wednesday. All handrails have been 
installed faux finishing is remaining on the interior rail. 
The exterior gas light fixtures were installed we are still 
waiting on the light post to provide the last fixture. The 
rush delivery of cobble stone arrived. Paul Miller of the 
Palmetto Bluff Design Review Board as approved the driveway 
change and service yard changes. The generator was set on 
the service yard pad. The swinging day bed location was 
approved by the Sneddons. Gas meter installation has been 
scheduled for Wednesday. 


Tim Beaulieu entered the following on 06:29:35 Nov/12/2009:
Weather Conditions:Rains through out the afternoon, high in the mid 70's
Date
:
November 10, 2009
Employees Working on site: Tim Beaulieu, Ed E, Greg Barber, Rolando Nunez, Danny Tracy, Jeff Collins, Dan Burke
Subcontractors on site: Russell Love-2, ACC-2, AGA-1, Vaught-1, JTS-1, CCS-2,YRP-1, MMC-2
Visitors: The Sneddon were on site to view faux finishing.
Equipment Used: The back hoe, bob cat, forklift were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Service yard work was being completed on the garage. The water heaters were being installed. The main house was being cleaned out. The side retaining wall was being completed. The pool service yard pipe work was being completed. Faux finishing was being completed in the master bedroom. Interior painting was being completed in the garage. The mechanical room built in was being installed. Cobble stones were being installed at the driveway apron.


Tim Beaulieu entered the following on 06:22:19 Nov/12/2009:
Weather Conditions:Sunny and clear high in the mid 70's
Date
:
November 09, 2009
Employees Working on site: Tim Beaulieu< Duane Constantino, Ed E, Greg Barber, Rolando Nunez, Danny Tracy, Dan Burke, Jeff Collins
Subcontractors on site: CCS-1, MMC-1, Hunter Plubming-2, Doline-2, ACC-3,
Visitors: Pual Miller from PBDRB was on site to discuss fencing, and service yards. The Sneddons were on site to view progress.
Equipment Used: The manlift was returned back to 12 Marshland, The mini track was returned. The back hoe was on site but not used. The bobcat was on site and used for 5 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes at this time.
Work Completed or Work in Progress notes: Interior painting was completed in the garages. plumbing trim out is underway and progress well. Electrical trim out is ongoing. The service yard fence post were being installed. The rear deck was being sanded and finished. Interior hardware was on site and nearing completion. The interior of the main house was being cleaned out.


Tim Beaulieu entered the following on 06:05:56 Nov/09/2009:
Weather Conditions:Sunny and Clear High in the upper 70's
Date
:
November 04-06, 2009
Employees Working on site: Tim Beaulieu, Ed E, Greg Barber, Rolando Nunez, Danny Tracy, Jeff Collins, Dan Burke
Subcontractors on site: JTS-1, Vaught-1,
Visitors: The Sneddons were on site to veiw progress and discuss scheduling
Equipment Used: The man lift and back hoe were on site but not used. The bobcat and track hoe and used for 3 hours. The fork lift was on site and used for 1 hour.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Lower vine fence to three feet Remove brick bordered walkway
Work Completed or Work in Progress notes: Cobble stone were being installed on the driveway apron and border. Interior painting was being completed in the foyer and garage. Faux finishing was being completed in the great room. Electrical trim out is underway. The retaining wall is completed. We have call and been to the review on numerous occasions but have to received word back. Plubming trim out is on going and nearing completion. Grade and drainage work was underway and is nearing completion.


Tim Beaulieu entered the following on 06:11:06 Nov/05/2009:
Weather Conditions:Sunny and clear through out the day high in the upper 70's
Date
:
November 03, 2009
Employees Working on site: Tim Beaulieu, Rolando Nunez, Greg Barber, Jeff Collins, Danny Tracy, Dan Burke, Ed E
Subcontractors on site: ACC-2, AGA-1, Vaught-1, JTS-1, CCS-2, Big Horn-10, Cuda Company-3, YRP-1, PGPNA-1
Visitors: The home woners were on site to review progress.
Equipment Used: The man lift, and three temp HVAC units were on site bt not used. The mini track hoe was on site and used for 3 hours. The bobcat was onsite and used for 4 hours. The back hoe was on site but not used. 3 bunks of scaffolding was used the entire day for faux finishing.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Change walk at rear pool deck and lower the majority of the vine fence to three feet while the section in front of the master bedroom will be at two feet. I will review with the PBDRB in the AM.
Work Completed or Work in Progress notes: The cobble stone installation is underway and roughly 1/3 completed. The second coat of epoxy was applied to the garage floors. Faux finishing was being completed in the master bathroom. The service yard on the main house was formed up. Gas line rough in work was completed at the main house service yard. The pool equipment service yard was reviewed and lay out completed. Electrical trim out was underway. The retaining wall on the side of the pool was completed. Drainage and grade work was being completed on the exterior shower side of the property.


Tim Beaulieu entered the following on 06:10:57 Nov/05/2009:
Weather Conditions:Sunny with a high in the mid 60's
Date
:
November 2, 2009
Employees Working on site: Tim Beaulieu, Rolando Nunez, Greg Barber, Jeff Collins, Danny Tracy, Dan Burke, Ed E
Subcontractors on site: ACC-2, AGA-1, Vaught-1, JTS-1, CCS-2, Big Horn-10, Cuda Company-3
Visitors: The home owners were on site to review progress.
Equipment Used: The man lift, and three temp HVAC units were on site bt not used. The mini track hoe was on site and used for 3 hours. The bobcat was onsite and used for 4 hours. The back hoe was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Retaining wall piling was being installed. The interior hardware was completed through out the main house with the exception of all cabinet hardware which will not arrive till the 19NOV09. Cobble stone installation was started on the driveway border. The 1st coat of epoxy was applied to the garage floors. Exterior paint punch work was being completed. Sheet rock touch ups were being completed through out the first floor of the main house.


Tim Beaulieu entered the following on 06:10:48 Nov/05/2009:
Weather Conditions:Sunny and Clear high in the mid 70's
Date
:
October 30, 2009
Employees Working on site: Tim Beaulieu, Rolando Nunez, Greg Barber, Jeff Collins, Danny Tracy, Dan Burke, Ed E
Subcontractors on site: ACC-2, AGA-1, Vaught-1, JTS-1, CCS-2, AGC-3, Big Horn-5
Visitors: The home owners were on site to review progress.
Equipment Used: The man lift, and three temp HVAC units were on site bt not used. The mini track hoe was on site and used for 2 hours. The bobcat was onsite and used for 3 hours. The back hoe was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The home owners would like to add a sink to the double car garage, all rough in work was completed earlier in the project. Epoxy color was selected for the garage floors (SW6944)
Work Completed or Work in Progress notes: Interior paint prep was completed in the foyer. The garages were cleaned out and prepared for epoxy coating. Drainage and grade work was being complete on the rear of the property. The pools retaining wall construction was underway. The retaining wall and piling installation is on going. Sheet rock touch ups were being completed in the main house. Interior hardware installation was being completed on the second floor of the main house. MEP trim out is underway and progressing well.


Tim Beaulieu entered the following on 06:10:39 Nov/05/2009:
Weather Conditions:Sunny and Clear, High in the mid 70's
Date
:
October 29, 2009
Employees Working on site: Tim Beaulieu, Rolando Nunez, Greg Barber, Jeff Collins, Danny Tracy, Dan Burke
Subcontractors on site: ACC-2, AGA-1, Vaught-1, JTS-1, CCS-2, AGC-3, Big Horn-5
Visitors: The owners were on site to review progress.
Equipment Used: The man lift, and three temp HVAC units were on site bt not used. The mini track hoe was on site and used for one hour. The bobcat was onsite and used for 5 hours. The back hoe was on site and used for two hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Drainage and grade work was underway. The retaining wall piling was being installed. Interior door hardware was being completed. Driveway form work was being completed and prepared for concrete. The service yard on the garage was completed. Electrical trim out was underway. Interior painting and sheet rock touch ups were being completed in the foyer.


Tim Beaulieu entered the following on 19:13:06 Oct/29/2009:
Weather Conditions:Light AM rain high in the low 70's
Date
:
October 28, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Rolando Nunez, Danny Tracy, Jeff Collins, Dan Burke
Subcontractors on site: ACC-5, AGA-1, JTS-1, Big Horn-5, Joey D-2, HHS-2
Visitors: The home owners were on site today to review progress.
Equipment Used: The man lift was on site but not used. The bob cat and track hoe were on site and used for five hours. The fork lift was on site and used for 1 hour. Three temp HVAC units were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Drainage and grade work was being completed in the front of the property. The retaining wall posts and pilings were being installed. Faux finishing was being completed in the master bedroom. Staging was erected for faux finishing in the great room. New ½ cdx plywood was purchased as floor protection for wall faux finishing. A platform in the main attic was completed. Shoe molding was being installed on the second floor of the main house. Remaining hardware installation was underway. HHS was completing the security and fire trim out.


Tim Beaulieu entered the following on 18:17:01 Oct/28/2009:
Weather Conditions:Rain showers through out the day, High in the mid 70's
Date
:
October 27, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Rolando Nunez, Danny Tracy, Jeff Collins, Dan Burke
Subcontractors on site: CCS-1, Ronny Knight, ACC-5, AGA-1, JTS-1, Big Horn-5, Joey D-2, Culligan-1
Visitors: The home owners were on site to review progress and discuss the job schedule.
Equipment Used: The man lift was on site but not used. The bob cat and track hoe were on site and used for five hours. The fork lift was on site and used for 1 hour.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior painting was being completed in the foyer and main hall. Door hardware was being completed on the second floor of the main house. The retaining wall was being installed all post have been installed and sheet pile installation is underway. Drainage and grade work was being completed in the front of the property. Landscape lighting conduits were being installed. A platform for the two water storage tanks in the attic was completed. A shower drain will be installed. A mirror was taken from the Oldfield home and profile and finishes will try to be matched for the mirror in the guest bathroom and master bathroom. Faux finishing was underway in the master bedroom and bathroom. Samples of finishes were applied to the bathroom walls are pending the home owners approval. Plugs were being installed in the timber stairs. Water sample were taken of the raw water to determine water softener and RO system.


Tim Beaulieu entered the following on 18:42:28 Oct/27/2009:
Weather Conditions:Overcast through out the day, High in the upper 60's
Date
:
October 26, 2009
Employees Working on site: Tim Beaulieu, Jeff Collins, Dan Burke, Danny Tracy, Rolando Nunez, Ed E
Subcontractors on site: CCS-1, Ronny Knight, AGA-5, Vaught-1, JTS-1, Big Horn-5, Palmetto Ready Mix-1, HHS-3, ACC-5
Visitors: The home owners were on site today to view progress.
Equipment Used: The bobcat was on site and used for 5 hours. Three temp HVAC units were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The driveway forms were poured and completed. Interior painting is underway in the foyer the final paint color was selected and the first coat was being applied. Plumbing fixtures were being installed in the main house. Retaining wall post installation is on going. Grade and drainage work was being completed on the front of the main house. The garage service yard was poured and broom finished. The timber stairs were being completed down to the water. The rear stairs from the pool were being laid out and were discussed with the home owner. David, Greg, and I have agreed that the rear stairs will not work as drawn. We will now have a small retaining was to each side of the stairs. Floor sanding was being completed on the second floor of the main house. Security trim out was being completed in the garage apartment.


Tim Beaulieu entered the following on 18:24:58 Oct/27/2009:
Weather Conditions:Low 70's, Sunny with clouds
Date
:
October 23, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Rolando Nunez, Jeff Collins
Subcontractors on site: AGA-1, JTS Construction-1, ACC-5, Big Horn-6, Cuda Company-2, CCS-1, Joey D-2, Hunter Plumbing-1
Visitors: The home owners were on site to view progress and Foyer paint color.
Equipment Used: The man lift, fork lift, and three temp HVAC units were on site but not used. The back hoe was on site and used for 1 hour. The bobcat was on site and used for three hours. The mini track hoe was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Floor finishing prep work was completed and finsh coats was applied in the garage apartment and 2nd floor of the main house. Driveway form work was underway and is ready for a monday pour. The retaining wall post installation is on going. The stairs to the rear porch were worked on and are roughly 50 percent completed. Faux finishing was being completed in the master bedroom. Drainage work was completed in front of the double car garage. A lighting plan was recieved and reviewed for installation. Plumbing trim out is on going. The master tub will be installed after Jo D has completed finishing in the master bathroom. Recepticals were being installed through out the main house.


Tim Beaulieu entered the following on 18:17:03 Oct/27/2009:
Weather Conditions:High in the mid 60's
Date
:
October 22, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Rolando Nunez, Jeff Collins, Dan Burke, Nathan Klien, Joe C, Nathan Klien
Subcontractors on site: Ronny Knight, Big Horn-6, CCS-2, ACC-5, DGM-2, Hunter Plubming-1
Visitors: The home owners were on site for the weekly site meeting.
Equipment Used: The man lift, fork lift, and three temp HVAC units were on site but not used. The back hoe was on site and used for 1 hour. The bobcat was on site and used for three hours. The mini track hoe was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Foyer paint color sample completed TBD.
Work Completed or Work in Progress notes: Grade work was being completed in the rear of the house. A site meeting was conducted today items discussed were landscape lighting, irrigation, drainage, rear porch handrails, and interior painting. CCS will complete the landscaped lighting job. Buds and Blooms will complete the irrigation system. The rear timber stairs were laid out and installation started. The retaining wall posts were being installed. The driveway form work was completed and poured. Plumbing fixture were being installed through out. Interior painting is underway. The Sneddons are still deciding on the foyer paint color. To sample were completed and viewed. Fuax finishing was being completed in the main house bedroom. Electrical trim out is underway.


Tim Beaulieu entered the following on 06:13:11 Oct/22/2009:
Weather Conditions:Sunny and clear, high in th mid 60's
Date
:
October 21, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Jeff Collins, Rolando Nunez, Danny Tracy
Subcontractors on site: JTS-1, CCS-1, ACC-3, Cuda Company-1, Vaught-1, Russell Love-2, Big Horn-6, Hunter Plubming-1
Visitors: Th home owners were on site today to veiw progress
Equipment Used: The man lift, fork lift, ten bunks of scaffolding, and three temp HVAC units were on site but not used. The back hoe was on site and used for 1 hour. The bob cat was on site and used for 1 hour to complete grade work. The track hoe was onsite and use for 2 hour.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The foyer and main hall pain color is pending. Danny and the owners were on site to review colors and Danny will provide new samples tomorrow.
Work Completed or Work in Progress notes: The timber frame stairs down to the waters edge was started. Gravel was being installed in the rear path ways. One side of the driveway is formed up and ready for concrete. Interior painting was being completed in the garage. Plubming fixtures were being installed in the main house. Grade and drainage work was bein completed on the side and front of the main house. Pocket door hardare was being installed and is completed.


Tim Beaulieu entered the following on 18:22:45 Oct/20/2009:
Weather Conditions:High in the mid 60's, clear
Date
:
October 20, 2009
Employees Working on site: Tim Beaulieu, Rolando Nunez, Jeff Collins, Danny Tracy
Subcontractors on site: JTS-1, CCS-1, Vaught-1, Big Horn-6, Ronny Knight-1, Courtland-1, Cuda-1, ACC-3, 2 Brothers-2
Visitors: The owners were on site today to review progress
Equipment Used: The back hoe was on site and used for 1 hour, the bobcat was on site and used for 5 hours, the forklift was on site and used for 1 hour, the man lift, ten bunks of scaffolding were on site but not used, the track hoe was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Exterior painting on the foundation fencing was being completed. The dryer duct was being modified and installed. Interior paint was underway in the garage. Pocket doors were being installed. Interior trim was being installed at all exterior doors at the floor threshold connection. All remaining stucco work was completed. The pathway and fire pit behind the RPOD line was cut in and fabric installed.


Tim Beaulieu entered the following on 18:57:48 Oct/19/2009:
Weather Conditions:Sunny and Clear high in the lower 60's
Date
:
October 19, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Danny Tracy, Jeff Collins
Subcontractors on site: CCS-1, JTS-1, Vaught-1, ACC-1, Cuda Company-1
Visitors: David was on site to discuss scheduling and project completion
Equipment Used: The fork lift and man lift were on site but not used. The big horn bobcat was on site and used for 4 hours to complete grade work. The back hoe was on site and is currently out of service two lines on the hoe are broken and parts have been ordered. Ten bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior paint preparation work was being completed in the garage and main house. Appliances were being installed in the main house. Grade work was being completed on the left hand side of the main house. Base board installation was being completed in the main house pantry and master closets. Day bed construction is underway at the shop. Lattice panels were completed and are being primed. Exterior painting was being completed on the screen porch. The walkways beyond the RPOD line were being laid out. The granite coble stone and driveway form material was delivered, off loaded, and staged in the front yard. The main house was cleaned and demobilize. The garage was emptied and all remaining material, fixtures, and MEP trim outs were staged in the great room.


Tim Beaulieu entered the following on 19:46:21 Oct/14/2009:
Weather Conditions:Rain through out the day high of 76
Date
:
October 14, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Greb Barber, Jeff Collins
Subcontractors on site: Vaught-1, JTS-1, ACC-6, CCS-1, 2 Brothers-2, Cuda Company-3, Big Horn-1, Doylen-2, Distinctive Granite and Marble-3
Visitors: Mrs Sneddon was on site today with two guest looking for ideas regarding curtains.
Equipment Used: The man lift, fork lift, and ten bunks of scaffolding were on site but not used; the back hoe was on site and used for 2 hours; three temp hvac units were on site but not used; one Murdaugh mini track hoe was on site and used for 3 hours; 1 Big horn bob cat was delievered to the site and used for 5 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior faux finishing base coats were installed in the foyer and main hall. The foyer ceiling was being painted. The kitchen counter tops were being installed, the tops will be completed tomorrow. Exterior door hardware was being installed on the main house doors. Grade and drainage work was being completed on the right hand side of the house. All drainage work was completed in this area but final grading has been delayed till the rain stops and everything dries up. Stucco work around first floor doors was completed. Misc electrical trim out was being completed.


Tim Beaulieu entered the following on 19:08:49 Oct/13/2009:
Weather Conditions:Overcast in the AM high in the low 80's
Date
:
October 13, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Gerson Morales, Jeff Collins
Subcontractors on site: JTS-1, Vaught-1, 2 Brothers-2, ACC-7, Cuda-3, Low Country Land Services-1
Visitors: The home owners were on site to review the shutters faux paint samples
Equipment Used: The back hoe was on site and used for 5 hours. The man lift, fork lift, and three bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house. 1 Rented mini track hoe was on site and used for 3 hours for drainage and grade work.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Hardware was being installed in the garage apartment. Retaining wall take offs were being completed. Exterior paint prep work was being completed on the screen porch. The screen porch installation is underway and nearing completion. The front planter was being cleaned out and prepared for drainage work. Grade elevations were being shot and staked and flaged. The final delivery of road ballast was recieved and staged. faux finishing was being completed on the kitchen cabinets. The front deck was being cleaned.


Tim Beaulieu entered the following on 20:19:01 Oct/12/2009:
Weather Conditions:Overcast through out the day, Heavy PM showers
Date
:
October 12, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Greg Barber, Jeff Collins, Danny Tracy
Subcontractors on site: JTS-1, Low Country Land Services-2, ACC-7, Vaught-1
Visitors: The home owners were on site today to view progress and review floor samples. David stated that he would like to keep the floor clear and not stain it or sand it.
Equipment Used: The man lift was on site but not used. Three temp HVAC units were on site, one unit was used the entire day to condition the garage apartment, two units for the main house were turned off during the day while interior painting was underway. The back hoe was onsite and used for 6 hours to grade the driveway. 1 Mini track hoe was delivered to the site and used for 1 hour. 3 bunks of scaffolding were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The screen porch was being completed. Interior paint prep work was being completed on the main house walls and trim. The driveway road ballast was completed. Silt fencing was being removed on the side of the property. The outdoor shower was being fabricated and is nearing completion.


Tim Beaulieu entered the following on 19:26:40 Oct/11/2009:
Memo:
October 6-9 2009 

BTV staff on site Greg Barber, Jeff Collins, Danny Tracy, 
Gerson Morales

Sub on site Closet Pro-4, ACC-7, AGC-2, JTS-1, Vaught-1, 
CCS-2

Equipment on site and used: The back hoe was on site and 
used for 10 hours to work on the driveway. The fork lift 
was on site but not used. Three temp hvac unit were on site 
and used during the night to condition the house. One unit 
remained on to condition the garage apartment during the 
day. The other two units were shut off do to interior paint 
work. Ten bunks of scaffolding were on site but not used. 
The man lift was on site but not used.

Weather October 5 rain in am. The rest of the week was warm 
and humid

Possible changes. No known changes at this time. 

Work completed:•	Interior painting is on going. All 
interior trim now has first coats completed. Joey has 
finalized the wall colors for faux finishing. The ceilings 
are schedule for paint next followed by the walls
•	Closet shelving was installed in the master walk-
ins and the pantry
•	The outdoor shower is nearing completion.
•	All treated retaining wall material has arrived on 
site. We will move in additional equipment this week and 
begin construction. The silt fence was pushed back and the 
site is prepared.  The cattle fencing were removed in 
preparation of upcoming work. 
•	Driveway excavation was completed. Road ballast is 
scheduled for delivery on Monday.
•	Shutter fabrication was completed on Friday and is 
ready for faux finishing.
•	All appliances were pulled from storage this week 
and staged in the great room
•	All plumbing, electrical, and hardware is on site 
and staged in the garage.
•	Sheet rock touch ups were being completed on the 
first floor walls and ceilings
•	The screen porch installation is nearing completion 
and looks great. 
•	Flooring samples are being completed and will be 
ready Tuesday for approvals. We currently have a few 
options available and will discuss finishing processes once 
the samples are ready for viewing.  
•	All gutters were delivered and installed
•	2 Brother Stucco was called and schedule to 
complete remaining stucco work


Tim Beaulieu entered the following on 21:41:01 Oct/06/2009:
Memo:
September 30-October 5 

The sites driveway grade work was completed. The driveway 
is now prepared for the sub base and is cut in. 

Interior painting is on going. All areas have been primed 
and are ready for 1st coats on the interior trim.

Cuda Company was called and will begin finish painting on 
the exterior on Monday.

2 Brothers Stucco was called and scheduled to complete the 
remaining stucco work.

The exterior screen porch was worked on and is roughly 75 
percent completed.

Electrical trim out is underway. The garage is roughly 60 
percent completed and the main house is 40 percent 
completed. David would like to change the rear porch 
ceiling fans to longer rods the fans will now have an 18 
inch rod.

All counter tops have been installed with the exception of 
the kitchen and the outdoor kitchen. 

The man lift and fork lift were on site and not used. The 
back hoe was on site and used for 20 hours for the driveway 
excavation. Ten bunks of scaffolding were on site but not 
used. 

Gutter installation was started today

5 Flooring samples were completed and prepared for the 
owners approvals

All tile installation was completed, there is a few area 
that grout changes are possible per the owners

Greg Barber, Danny Tracy, Gerson Morales, Tim Beaulieu, 
Jeff Collins were all working on site during this period 

MMC-3, CCS-1, AGC-2,  ACC-7, Stone Works-2 


Tim Beaulieu entered the following on 08:37:08 Sep/30/2009:
Memo:
The following entry was completed due to internet and web 
difficulties experience on September 24-29, 2009 


Sneddon jobsite entry

The following work is underway completed or in the process

All countertops were templated and fabrication is underway. 
Interior trim is completed 
Interior paint is on going the garage apartment is 
completed and the first coat of trim paint was being 
applied in the main house.
The screen porch material was delivered and installation is 
underway
All hardscapes plans were approved my the PBDRB on 
29Sept09. Paul Miller of the review board was on site 
Tuesday to review proposed plans. Paul stated that he 
didn’t have any concerns with the desired construction 
technique. 
The cabinet faux finishing is underway. The cabinetry is 
roughly 75 percent completed at this time. 
All light fixture were delivered on 29 September. All 
fixture have been inventoried and has found that we are 
missing one fixture for the garage lighting.
All plumbing fixture were delivered to the site on 25 
September. All fixtures are on site with the exception of 
the 3 tankless water heaters.
Hardscapes and drainage material was being delivered to the 
site.
4 loads of 57 stone were delivered and staged in the front 
yard. 092909
4 Rolls perf pipe staged 092909
3 rolls highway fabric 092409
The site is being prepared for drainage and hardscapes 
work. An additional silt fence was installed at the 
property line. We have straw bales running the length of 
the property to control potential run off.

The following equipment was on site but not used 1 back 
hoe, 1 man lift, 1 fork lift, and 10 bunks of scaffolding. 
Three temp HVAC units were on site and used the entire 
night to condition the house. The units are being turned 
off during the day during the interior paint process. 

The following days 24-29 were dry with no precipitation 
morning low of 51 with a afternoon high of 80 degrees.


Tim Beaulieu entered the following on 09:33:47 Sep/24/2009:
Weather Conditions:Rain off and on through out the day, High in the low 80's
Date
:
September 23, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Jeff Collins, Gerson Morales
Subcontractors on site: CCS-1, MMC-2, Vaught-1, ACC-7, PGPNA-1
Visitors: David was onsite with guest to veiw progress and construction
Equipment Used: The man lift, Fork lift, back hoe, and ten bunks of scaffolding were on site but not used. Three temp HVAC units were on site and turned off for the day while interior painting is underway.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The screen porch installation is underway. A gas line was installed from the rear deck to the main house service yard. Priming was being completed in the main house 2nd floor guest bedroom, mechanical room, and studio. Interior trim was being completed at the kitchen island. Electrical trim out was being completed in the garage. The job site was being organized and clean. Exterior grade work preperations were being completed. A new silt fence will be installed on the left hand side of the house behind the existing. Straw bales will be place up to the fence to control silt during the hardscapes and rough greading portions of the project.


Tim Beaulieu entered the following on 16:05:43 Sep/23/2009:
Weather Conditions:Sunny and Clear, High in the low 80s
Date
:
September 22, 2009
Employees Working on site: Tim Beaulieu< Gerson Morales, Jeff Collins, Greg Barber, Danny Tracy
Subcontractors on site: PGPNA-1, ACC-7, MMC-2, JTS-1
Visitors: No visitors today
Equipment Used: The man lift, forklift, and ten bunks of scaffolding were on site but not used. The back hoe was on site and used for 2 hours. Three temp HVAC units were on site and used the entire day condition.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior painting was being completed in the garage apartment. Rough grade work was being completed in the driveway. Interior trim was being completed on the kitchen island. The second floor built ins were being installed in the guest bedroom. Exterior trim was being installed on the garage door jams. The screen porch material was delivered.


Gregory Barber entered the following on 07:00:07 Sep/22/2009:
Weather Conditions:mostly sunny, 84*
Date
:
Sept. 21, 2009
Employees Working on site: Greg Barber, Jeff Collins, Danny Tracy, Gerson Morales, Francisco Trajillo
Subcontractors on site: JTS-1, Vaught- 1, ACC- 7, Distinctive- 1, MMC- 3
Visitors: Mrs. Sneddon and friend
Equipment Used: The man lift, back hoe, forklift and ten bunks of scaffolding were on site but not used. Three temp hvac units were on site and used for the entire day to condition the main and carriage house.
Urgent Items and Equipment Needed
:
none
Possible Change Order Items: none
Work Completed or Work in Progress notes: Interior trim was installed. Guest bedroom builtin installation and trim out was done. Shoe molding was installed in areas with tile floors. Interior paint prep and painting were done in the carriage and guest houses. The kitchen countertop was templated.


Tim Beaulieu entered the following on 22:59:48 Sep/17/2009:
Weather Conditions:Sunny and Clear, High in the low 90's
Date
:
September 16, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Jeff Collins, Ed E
Subcontractors on site: AGA-1, Vaught-1, JTS-1, MMC-1
Visitors: David was on site today to review progress
Equipment Used: The man lift, back hoe, and ten bunks of scaffolding were on site but not used. The forklift was on site and used for 1 hour. Three temp hvac units were on site and used for the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior trim was being completed in the main house kitchen and foyer. The second floor guest bedroom built ins were delivered and will be installed in the AM. The rear porch exterior siding at the kitchen was completed. The entire job site was cleaned and prepared for drainage work. Interior priming was being completed in the garage apartment. Base board was being installed in the garage. The service yard pad for the generator was laid out.


Tim Beaulieu entered the following on 20:38:19 Sep/16/2009:
Weather Conditions:Sunny and Clear, high in the low 90's
Date
:
September 15, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Jeff Collins
Subcontractors on site: AGA, Vaught-1, JTS-1, ACC-5, Prestige Stone-1, MMC-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, and ten bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condtion the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior trim was being completed in the foyer and main house kitchen island. The exterior kitchens siding was completed. Paint prep work was being completed in the garage apartment. A walk thru of all tile work was conducted and a punchlist established.


Tim Beaulieu entered the following on 19:58:10 Sep/16/2009:
Weather Conditions:Sunny and Clear, High in the upper 80's
Date
:
September 14, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Jeff Collins, Greg Barber, Dan Burke, Danny Tracy
Subcontractors on site: AGA-1, ACC-3, Prestige Stone-2, MMC-1, JTS-1
Visitors: No visitors today
Equipment Used: The man lift, back hoe, fork lift and 10 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No know changes to report at this time.
Work Completed or Work in Progress notes: Second floor guest bedroom built in were being complete at 12 Marshland. Paint prep work was being completed in the 2nd floor of the main house. The outdoor shower decking was completed. The exterior kitchen cabinets were being installed. Interior trim was being completed in the foyer and main house kitchen. All interior trim work is nearing completion. Tile puch work was being completed in the first floor studio bath. Exterior trim was completed at the front door. The entire site was being clean and organized.


Tim Beaulieu entered the following on 22:00:22 Sep/14/2009:
Weather Conditions:Sunny and clear, High in the upper 80's
Date
:
September 11, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Roland Nunez, Greg Barber, Jeff Collins, Dan Burke, Danny Tracy
Subcontractors on site: MMC-3, CCS-1, AGA-1, JTS-1, Connely-1, ACC-2,
Visitors: No visitors today
Equipment Used: The man lift, back hoe, fork lift were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known change to report at this time.
Work Completed or Work in Progress notes: Interior trim was being completed in the garage entryway, the main house foyer and kitchen. The second floor was being prepared for paint, all nail hole were filled. The exterior showers deck board were installed. The exterior kitchen cabinet installation was started.


Tim Beaulieu entered the following on 21:55:21 Sep/14/2009:
Weather Conditions:Sunny and clear
Date
:
September 10, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Roland Nunez, Greg Barber, Jeff Collins, Dan Burke, Danny Tracy, Duane Constantino, Nathan Klien
Subcontractors on site: MMC-3, CCS-1, AGA-1, JTS-1, Connely-1, ACC-2, HP-1, Webber-1
Visitors: David was on site to view progress
Equipment Used: The man lift, back hoe, fork lift were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: A site meeting was conducted. Items discussed were hardscapes, driveway, and project completion. Interior trim was being completed in the main house foyer and kitchen. The exterior showers form and concrete work and post setting was completed, deck framing is underway. Plumbing rough in was completed in the outdoor shower. The exterior kitchens plumbing was extended so cabinetry could be installed. Sheet rock touch ups were being completed through out the first floor.


Tim Beaulieu entered the following on 20:41:56 Sep/09/2009:
Memo:
Date
September 09, 2009

Weather 
Sunny and clear, High in the mid 80’s 

Bay Ten Employees on site 
Tim Beaulieu, Gerson Morales, Rolando Nunez, Danny Tracy, 
Greg Barber, Dan Burke, Jeff Collins

Subcontractors on site 
Webber-1, CCS-1, Black, Vaught-1, AGA-1, JTS-1, Connley-1, 
MMC-3

Equipment on site
The man lift, fork lift, and back hoe were on site but not 
used. 10 bunks of scaffolding were onsite but not used, 
Three temp HVAC units were on site and used the entire day 
to condition the main house.

Urgent issue or foreseen problems
No foreseen issues or problems to report at this time 

Possible Changes 
Add beam in gallery and sitting room

Work completed or in progress 
Interior trim was being completed in the foyer and kitchen. 
Tile work was being completed in the main house 1st floor 
studio bath. The garage apartments entryway was sealed and 
prepared for tile. The rear porch ceiling above the 
exterior kitchen was being installed. Electrical trim out 
was being completed in the main house. Receptacles were 
being installed in the first floor baseboards through out. 
Sheet rock touch ups were completed in the laundry room. 
Laundry room cabinetry was installed. 

Date
September 08, 2009

Weather 
Sunny and clear, light PM showers 

Bay Ten Employees on site 
Tim Beaulieu, Greg Barber, Gerson Morales, Rolando Nunez, 
Jeff Collins, Dan Burke, Danny Tracy

Subcontractors on site 
Webber-1, CCS-1, Black, Vaught-1, AGA-1, JTS-1, Connley-1, 
MMC-3

Equipment on site
The man lift, fork lift, and back hoe were on site but not 
used. 4 bunks of scaffolding were on site and used the 
entire day to install the rear porches ceiling boards, 
Three temp HVAC units were on site and used the entire day 
to condition the main house.

Urgent issue or foreseen problems
No foreseen issues or problems to report at this time 

Possible Changes 
No known changes to report at this time

Work completed
Interior trim was being completed in the main house foyer, 
kitchen, and first floor hallway. The exterior porch 
ceiling above the outdoor kitchen was completed. Electrical 
trim out was being completed in the main house. Tile was 
being installed in the first floor studio. Material were 
being organized and staged. The front doors exterior trim 
was being completed

 


Tim Beaulieu entered the following on 20:39:05 Sep/09/2009:
Memo:
Date
September 03, 2009

Weather 
Sunny and clear, High in the mid 80’s 

Bay Ten Employees on site 
Tim Beaulieu, Gerson Morales, Rolando Nunez, Danny Tracy, 
Greg Barber, Dan Burke, Jeff Collins

Subcontractors on site 
Webber-1, CCS-1, Black, Vaught-1, AGA-1, JTS-1, Connley-1, 
MMC-3

Equipment on site
The man lift, fork lift, and back hoe were on site but not 
used. 4 bunks of scaffolding were on site and used the 
entire day to install the rear porches ceiling boards, 
Three temp HVAC units were on site and used the entire day 
to condition the main house.

Urgent issue or foreseen problems
No foreseen issues or problems to report at this time 

Possible Changes 
Add beam in gallery and sitting room

Work completed or in progress 
Interior trim was being completed in the foyer and kitchen. 
Tile work was being completed in the main house 1st floor 
studio bath. The garage apartments entryway was sealed and 
prepared for tile. The rear porch ceiling above the 
exterior kitchen was being installed. Electrical trim out 
was being completed in the main house. Receptacles were 
being installed in the first floor baseboards through out. 
Sheet rock touch ups were completed in the laundry room. 
Laundry room cabinetry was installed. 

Date
September 04 2009

Weather 
Sunny and clear, light PM showers 

Bay Ten Employees on site 
Tim Beaulieu, Greg Barber, Gerson Morales, Rolando Nunez, 
Jeff Collins, Dan Burke, Danny Tracy

Subcontractors on site 
Webber-1, CCS-1, Black, Vaught-1, AGA-1, JTS-1, Connley-1, 
MMC-3

Equipment on site
The man lift, fork lift, and back hoe were on site but not 
used. 4 bunks of scaffolding were on site and used the 
entire day to install the rear porches ceiling boards, 
Three temp HVAC units were on site and used the entire day 
to condition the main house.

Urgent issue or foreseen problems
No foreseen issues or problems to report at this time 

Possible Changes 
No known changes to report at this time

Work completed
Interior trim was being completed in the main house foyer, 
kitchen, and first floor hallway. The exterior porch 
ceiling above the outdoor kitchen was completed. Electrical 
trim out was being completed in the main house. Tile was 
being installed in the first floor studio. Material were 
being organized and staged. The front doors exterior trim 
was being completed

Date 
September 07, 2009 	

Weather 
Sunny and clear
Bay Ten Employees on site 
Tim Beaulieu, Greg Barber, Gerson Morales, Danny Tracy

Subcontractors on site 
CCS-1, Vaught-1, AGA-1, JTS-1, MMC-1

Equipment on site
The man lift, fork lift, and back hoe were on site but not 
used. 10 bunks of scaffolding were on site but not used, 
Three temp HVAC units were on site and used the entire day 
to condition the main house.

Urgent issue or foreseen problems
No foreseen issues or problems to report at this time 

Possible Changes 
No known changes to report at this time

Work Completed 
Interior trim was being completed in the foyer and main 
hall. Interior trim was being completed on the wainscoting 
in the first floor hall  . 


Tim Beaulieu entered the following on 20:53:28 Sep/02/2009:
Weather Conditions:Overcast through out the day
Date
:
September 02, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Rolando Nunez, Jeff Collins, Greg Barber, Dan Burke, Danny Tracy, Ed Ernst
Subcontractors on site: AGA-1, CCS-4, JTS-1, Black-1, Connely-1, PGPNA-1, Vaught-1, MMC-2
Visitors: The home owners were on site to review progress
Equipment Used: The back hoe, man lift, and ten bunks of scaffolding were on site but not used. The fork lift was on site and used for 15 minutes to move the gun safe. Three temp HVAC units were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Add additional beam, and pilaster in foyer.
Work Completed or Work in Progress notes: Interior trim was being completed in the main hall, kitchen, and foyer. The garage apartments handrail was completed. Electrical trim out was being completed in the garage apartment. An additional gas line was install in the outdoor kitchen. Ipe deck plug work was underway and nearing completion. The master water closets built in was installed. The exterior grills hood exhaust work was installed. Foundation louvers were being fabricated and installed on the rear porch.


Tim Beaulieu entered the following on 20:43:59 Sep/01/2009:
Memo:
Date
090109

Weather
Overcast through out the day, High in the low 90’s

Bay Ten Employees on site
Tim Beaulieu, Nathan Klein, Greg Barber, Billy Bowers, Dan 
Burke, Danny Tracy, Jeff Collins, Rolando Nunez, Gerson 
Morales, Nicholas Royas

Subcontractors on site
CCS-4, AGA-1, Black Construction-1, Vaught Construction-1, 
JTS Construction-1, Connely-1, Prestige Stone-1, MMC-3, 
Webber-1  

Visitors on site
The home owners were on site to review drainage, 
hardscapes, and driveway

Equipment on site
The back hoe, man lift, and fork lift were on site but not 
used. Three temp HVAC unit were on site and used the entire 
day to condition the main house and garage. Ten bunks of 
scaffolding were on site and used the entire day for 
interior trim

Possible change orders
No known changes to report at this time

Urgent or foreseen issues
No foreseen issues or problems to report at this time

Work in progress 
Electrical trim out was being completed in the garage 
apartment. The garage apartment’s staircase handrail 
installation is underway. Tile installation is nearing 
completion in the garage apartment bathroom. Interior trim 
was being completed in the main house foyer and kitchen. 
Exterior trim was being installed on the garage apartment. 
The exterior hoods duct work was installed. Ipe decking was 
being completed on the rear porch. Hardscapes, drainage, 
and driveway was reviewed and is pending the home owners 
approval. 



Date 
083109

Weather
Rain showers off and on through out the day, High in the 
upper 80’s 

Bay Ten Employees on site
Tim Beaulieu, Gerson Morales, Nicholas Royas, Greg Barber, 
Jeff Collins, Billy Bowers, Rolando Nunez, Dan Burke 

Subcontractors on site
CCS-2, MMC-3, JTS Construction-1, Vaught Construction-1, 
Black-1, Connely-1, Prestige Stone-2, AGA-1

Equipment on site 
The back hoe, man lift, forklift were on site but not used. 
Three temp HVAC units were on site and used the entire day 
to condition the main house. Ten bunks of scaffolding were 
on site and used the entire day to install interior trim in 
the main house foyer.

Possible Change orders 
No known changes to report at this time

Urgent or foreseen issues
No foreseen issues at this time

Work in Progress 
Interior trim was being completed in the main house 
kitchen. Closet shelving was installed in the 2nd floor 
guest bedroom and 2nd floor studio. Tile installation was 
underway in the garage apartment single car side. Handrail 
pickets were being mortised for dowels to be installed in 
the garage staircase. Ipe decking was completed on the 
porches. Ipe plug installation is underway on the ipe 
border. A paint schedule was completed and is pending the 
owners approval. A threshold was installed in the foyer at 
the tile work in the kitchen. The cased opening was 
installed in the sitting room/kitchens rough opening. The 
anteroom door casing and cabinetry was installed. 


Date 
082809

Weather
Sunny in clear in am, Light afternoon showers with a high 
in the low 90’s

Bay Ten Employees on site 
Tim Beaulieu, Greg Barber, Gerson Morales, Nicholas Royas, 
Rolando Nunez, Jeff Collins, Dan Burke, Danny Tracy, Ed 
Ernst 

Subcontractors on site 
AGA-1, CCS-2, JTS Construction-1, Black-1, Vaught 
Construction-1, ACC-1, Connely-1, Prestige Stone, 2 
Brothers Stucco-1

Equipment on site 
The Back hoe, fork lift, man lift were on site but not 
used. 10 bunks of scaffolding were on site but not used. 
Three temp HVAC units were on site and used the entire day 
to condition the main house and garage apartment

Possible change orders 
No known changes to report at this time

Urgent or foreseen issues
No foreseen issues to report at this time

Work in progress
Interior trim was being completed in the Anteroom, garage 
apartment. Door hardware was being mortised on the second 
floor of the main house and was completed. 2 Brothers was 
on site to review remaining work. 2 Brother stated they 
would complete work on Wednesday. Electrical trim out was 
being completed in the 2nd floor of the main house. All 
receptacles and switches were installed.   The kitchen beam 
framing was underway and should be completed on Monday. 
Tile work was being completed in the garage apartment’s 
shower. Ipe Decking was being completed on the front of the 
main house. Closet shelving for the second floor of the 
main house was being fabricated at the shop, and will be 
ready for installation on Monday.

Date
082709

Bay Ten Employees on site 
Tim Beaulieu, Nathan Klien, Greg Barber, Nicholas Royas, 
Gerson Morales, Billy Bowers, Jeff Collins, Dan Burke, 
Rolando Nunez, Danny Tracy 

Subcontractor on site
AGA-1, MMC-1, CCS-2, Black-1, JTS Construction-1, Connely-
1, Vaught Construction-1, Prestige Stone

Visitor on site
David was on site for the weekly site meeting

Equipment on site
The back hoe, fork lift, man lift and ten bunks of 
scaffolding were on site but not used. Three temp HVAC 
units were on site and used the entire day to condition the 
main house. 

Possible change orders
Exterior shutter will be nonfunctioning. The 2nd floor 
guest room built in was reviewed and approved for 
construction. The last tread on the main house stair case 
will be cut so that the radius of the stair will carry 
through. The fluted portion of hand rail will be changed so 
the handrail will terminate into a decorative newel post. 
Russel Love was contact and is aware of the modification

Urgent or foreseen issues 
No foreseen issues to report at this time

Work completed or in progress
The main house radius wall at the stair case was completed. 
The attic access rough opening was modified to fit the 
stairs from Espy Lumber. Door stop was installed in the 
garage apartment. Crown molding was being installed in the 
kitchen. Interior door and window casing was completed in 
the great room of the main house. Ipe decking was being 
installed on the front porch and is 50 percent completed. 
Tile installation was being completed in the 2nd floor 
studio. Closet shelving was being fabricated at the shop. 
Electrical devices were being installed in the second floor 
of the main house. The anteroom cabinet crown molding was 
being completed.


Tim Beaulieu entered the following on 19:48:13 Aug/27/2009:
Weather Conditions:Sunny and clear
Date
:
August 26, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Billy Bowers, Jeff Collins, Greg Barber, Danny Tracy, Dan Burke
Subcontractors on site: AGA-1, Prestige Stone-2, JTS-1, CCS-2, ACC-1, MMC-3, Black-1, Vaught-1, Connely-1, SCE&G-4
Visitors: David was on site today to review progress
Equipment Used: The man lift, fork lift, back hoe, and ten bunks of scaffolding were on site but not used. Three temp HVAC unit were on site and used for the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Mrs Sneddon called and stated that the closet shelving for the master bedroom closets, and pantry were going to be fabricated outside of Bay Ten. She stated that it will take till the 1st week of October to have installed. Base board will be left off in these area till contact is made with the fabricator.
Work Completed or Work in Progress notes: Ipe decking was being installed on the front porch of the main house. Interior trim was being completed in the kitchen, great room, and 2nd floor apartment. The main house interior stair case is nearing completion. MMC has last five treads and are milling to as built conditions. Tile was installation was underway in the second floor studio. Electrical trim out was being completed in the second floor mechanical room. SCE&G started the main gas line installation from the street. They will complete in the AM.


Tim Beaulieu entered the following on 19:21:58 Aug/26/2009:
Weather Conditions:Sunny and Clear in AM, Overcast in PM
Date
:
August 25, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Jeff Collins, Greg Barber,Dan Burke, Rolando Nunez, Nicholas Royas, Danny Tracy, Billy Bowers
Subcontractors on site: CCS-1, Prestige Stone-2, AGA-1, JTS-1, MMC-3, Vaught-1, Conley-1, Black-1
Visitors: David was on site today to review progress.
Equipment Used: The man lift, fork lift, back hoe, and 10 bunks of scaffolding were on site but not used. Three temp HVAC unit were on site and used the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David stated that it was ok to go ahead and fabricate the shelving for the master bedroom and 2nd floor closets in the main house. All shelving will be paint grade and constructed out of 3/4 birch plywood and have poplar nosings. David would like to move the av wire in the 2nd floor guest bedroom.
Work Completed or Work in Progress notes: Interior trim was completed in the master bedroom. Wainscoting backband extensions were milled and installed in the main hall. The exterior grill was delivered from the storage unit. The garage stairs were completed with the exception of the handrail. The main house staircase radius wall is roughly 80 percent completed. Tile was being installed in both second floor main house showers. Electrical panel trim was being completed in the second floor storage room. Door casing was being completed in the great room.


Tim Beaulieu entered the following on 19:15:10 Aug/26/2009:
Weather Conditions:Sunny and clear
Date
:
August 24, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Jeff Collins, Greg Barber,Dan Burke, Rolando Nunez, Nicholas Royas, Danny Tracy, Billy Bowers
Subcontractors on site: CCS-1, Prestige Stone-1, AGA-1, JTS-1, MMC-3, Vaught-1, Conley-1, Black-1
Visitors: No visitors today
Equipment Used: he man lift, fork lift, back hoe, and 10 bunks of scaffolding were on site but not used. Three temp HVAC unit were on site and used the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Move AV wiring in garage apartment
Work Completed or Work in Progress notes: Interior trim was being installed in the master bathroom, anteroom, 2nd floor garage. Ipe decking was being installed on the side porch. Cabintery was installed in the exterior grill area. The main house and garage staircase was being completed.


Tim Beaulieu entered the following on 22:58:07 Aug/24/2009:
Weather Conditions:Sunny and Clear, High in the upper 90's
Date
:
August 21, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Jeff Collins, Greg Barber,Dan Burke, Rolando Nunez, Nicholas Royas, Danny Tracy, Billy Bowers
Subcontractors on site: CCS-1, Prestige Stone-1, AGA-1, JTS-1, MMC-2, Vaught-1, Conley-1, Black-1
Visitors: The Sneddons were on site to review progres
Equipment Used: The man lift, fork lift, back hoe, and 10 bunks of scaffolding were on site but not used. Three temp HVAC unit were on site and used the entire day to condition the main house
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior trim was being completed in the master bedroom, Anteroom, studio bath, garage apartment. The main house, and garage staircase were being fabricated. Ipe was being completed on the side porch. Extenstion jams were being install in the great room.


Tim Beaulieu entered the following on 22:32:10 Aug/24/2009:
Weather Conditions:Sunny and clear
Date
:
August 20, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Jeff Collins, Greg Barber,Dan Burke, Rolando Nunez, Nicholas Royas, Danny Tracy, Billy Bowers, Nathan Klien, Duane Constintino
Subcontractors on site: CCS-1, Prestige Stone-1, AGA-1, JTS-1, MMC-2, Vaught-1, Conley-1, Black-1
Visitors: The Sneddons were onsite for the site meeting
Equipment Used: The man lift, fork lift, back hoe, and 10 bunks of scaffolding were on site but not used. Three temp HVAC unit were on site and used the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problem to report at this time.
Possible Change Order Items: Add built in at 2nd floor guest bedroom
Work Completed or Work in Progress notes: A site meeting was conducted to discuss hardscapes, built ins, and counter tops. Nathan will publish report. Interior trim was installed in the studio, garage apartment, and master bedroom. Tile was being completed in the master shower. Ipe decking was being completed on the side porch.


Tim Beaulieu entered the following on 21:27:09 Aug/20/2009:
Weather Conditions:Sunny and Clear in Am
Date
:
August 19, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Jeff Collins, Greg Barber,Dan Burke, Rolando Nunez, Nicholas Royas, Danny Tracy, Billy Bowers, Ed E
Subcontractors on site: AGA-1, JTS-1, Doline-2, CCS-1, ACC-2, Connely-1, Black-1,
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, and 10 bunks of scaffolding were on site but not used. Three temp HVAC unit were on site and used the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David would like to add some built-in at the second floor guest bedrooms front wall. Move structure cable to bath wall bedroom side.
Work Completed or Work in Progress notes: Ipe decking was being installed on the rear porch. The side porch framing was being prepared for decking installation. Interior trim was being installed in the master bedroom, first floor studio. A walk thru with ACC was completed. Interior painting will begin on the second floor of the main house on Tuesday. Tile work was being completed in the master bathrooms shower. Sheet rock touch ups were being completed in the second floor of the main house and attic.


Tim Beaulieu entered the following on 20:55:40 Aug/19/2009:
Weather Conditions:Hot and Humid, High in the mid 90's
Date
:
August 18, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Greg Barber, Billy Bowers, Jeff Collins, Ed E, Dan Burke
Subcontractors on site: CCS-1, Prestige Stone-1, AGA-1, JTS-1, MMC-2, Vaught-1, Conley-1, Buds and Blooms-1
Visitors: The owners were on site today to view progress
Equipment Used: The back hoe, man lift, fork lift, and ten bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Interior trim was being completed in the garage apartment, master bedroom, and 1st floor studio. The main house stair case trim out is on going. Tile was being installed in the master shower. Rear porch decking was being completed. The main house second floor was being cleaned.


Tim Beaulieu entered the following on 20:15:14 Aug/17/2009:
Weather Conditions:Sunny and Clear, High in the upper 90's
Date
:
August 17, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Gerson Morales, Nicholas Royas, Danny Tracy, Billy Bowers, Dan Burke, Rolando Nunez, Nathan Klien
Subcontractors on site: CCS-1, MMC-3, AGA-1, JTS-1, Conelly-1, Vaught-1, Presitge Stone-2,
Visitors: The Sneddons were on site with two guest to review project. Buds and Blooms were on site to check status of lanscaping and scheduling. Waste Management was on site to empty the dumpster.
Equipment Used: The fork lift was on site and used for 30 minutes to move trailers. The man lift, back hoe, and ten bunks of scaffolding were on site but not used. Three temp HVAC unit were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
Complete laundry room cabinetry, finalize shelving and paint schedule
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Ipe decking installation on the rear porch is on going. Interior window casing and paneling were completed in the 1st floor studio. Crown installation was started. Master bedroom trim work is on going, all base board was completed. Window and door casing installation in the garage apartment was completed today and baseboards were started. The CO schedule, door hardware, and paint selections was reviewed with the owners this afternoon. The door hardware Nathan proposed was approved for purchase. The master shower wall tile installation was started and is 40 percent completed. Interior trim lay outs were being completed in the foyer and kitchen. The second floor interior trim work was completed. Webber has been notified and will complete sheet rock touch up on Wednesday. The second floor was cleaned and demobilized.


Tim Beaulieu entered the following on 19:58:07 Aug/13/2009:
Weather Conditions:Sunny and clear in am, Heavy afternoon thunder storms and showers
Date
:
August 13, 2009
Employees Working on site: Tim Beaulieu, Ed E, Gerson Morales, Greg Barber, Jeff Collins, Rolando Nunez, Billy Bowers, Nicholas Royas, Dan Burke
Subcontractors on site: AGA-1, JTS-1, Vaught-1, CCS-4, Distinctive Granite and Marble-2, MMC-2
Visitors: David and Guest were on site to review project and status
Equipment Used: The forklift was on site and used for 1 hour to move materials, The backhoe was on site and used for 30 minutes to rough grade, The man lift and 10 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No know changes to report at this time.
Work Completed or Work in Progress notes: Interior door and window casing was being installed in the garage apartment and master bedroom. Cabinetry was installed in the main house kitchen. The first floor studio paneling is on going. Interior pilasters were being fabricated at the BTV shop. Florescent light fixtures were being installed in the main house. Second floor trim work is nearing completion. Base board was installed the 2md floor hall, storage room, guest bedroom and studio bath. Ipe decking was being installed on the rear porch. HCAC material and equipment was being demobilized and inventoried.


Tim Beaulieu entered the following on 18:42:28 Aug/12/2009:
Weather Conditions:Sunny and clear in AM, Heavy afternoon rain showers
Date
:
August 12, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Gerson Morales, Nicholas Royas, Jeff Collins, Rolando Nunez, Billy Bowers
Subcontractors on site: AGA-1, JTS-1, Prestige Stone-3, CCS-2, MMC-3
Visitors: No visitors on site today
Equipment Used: The man lift, and back hoe were on site but not used. The fork lift was on site and used for 2 hours to demobilize job site and organize materials. Three temp HVAC units were on site and used the entire day to condition the main house and garage. The artic heater and all scaffolding was return to 12 Marshland. 10 Bunks of scaffolding remained on site but not used.
Urgent Items and Equipment Needed
:
Resolve main house kitchen cabinet counter top selections. Complete closet design. Greg B will go to shop in AM to construct foyer and studio casing.
Possible Change Order Items: Discuss wainscoting detail with owners.
Work Completed or Work in Progress notes: Base board was being completed in the second floor guest bedroom and bathroom. Window and door casing was on going in the master bath, bedroom, and garage apartment. Ipe decking was laid out and decking prepared for installation. Tile was laid out for the master shower walls and pending approval. Electrical trim out was being completed in the garage apartments mechanical closet. Plumbing and electrical conduits were being strapped below the deck framing. The job site was demobilized of all unnecessary material and equipment. Shelving was fabricated for the main house second floor bathrooms built in.


Tim Beaulieu entered the following on 19:43:39 Aug/11/2009:
Weather Conditions:Sunny and clear through out the day, High in the mid 90's
Date
:
August 11, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Ed E, Gerson Morales, Nicholas Royas, Jeff Collins, Danny Tracy, Rolando Nunez
Subcontractors on site: AGA-1, JTS-1, Vaught-1, PGPNA-1, Hunter Plubming-2, Prestige Stone-3, CCS-5, Cuda-3, MMC-2
Visitors: The home owners were on site today with 1 guest.
Equipment Used: The back hoe, man lift, fork lift, and 30 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Possible add 7 exterior receptacles to rear porch. CCS has returned with a proposal. This will be discuss with the owners tomorrow.
Work Completed or Work in Progress notes: All garage interior bay light fixtures were installed. Attic electrical work was completed in the main house attic and garage attic. Exterior painting was being completed on the garage balconies and garage siding. The exterior paint work on the garage is 100 percent completed. The plumbing below the kitchen sink and laundry room sink was adjusted for cabinet installation. The main house porch plywood was removed. All grade work below the deck was completed. Deck blocking was being installed around brick piers. The gas line rough in for the kitchen cook top was completed. Interior window and door casing was being completed in the master bedroom and garage apartment. Tile lay out for the master shower wall is on going. Tile was installed on the master shower floor and both garage apartment shower floors. HVAC duct work was completed in the second floor mechanical closet, main house attic, and 2nd floor guest bedroom window seat. The 2nd floor guest bedrooms bath built in was completed. The first floor studio paneling and casing is on going. The remaining kitchen and shower wall tile was delivered. All tile setting was completed in the kitchen. Bone grout color was approved and will be applied tomorrow. Exterior electrical receptacles were being installed.


Tim Beaulieu entered the following on 20:44:45 Aug/10/2009:
Weather Conditions:Sunny and Clear, High in the upper 80's
Date
:
August 10, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Ed E, Gerson Morales, Danny Tracy, Nicholas Royas, Rolando Nunez
Subcontractors on site: AGA-1, Vaught Con-1, CCS-4, Prestige Stone-4, JTS-1, Cuda-3,
Visitors: The Sneddons were on site to review progress and discuss various trim elements. Cregger was on site to deliver the master baths sinks.
Equipment Used: The back hoe, fork lift, man lift, and 30 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Price out additional cabinet in laundry room. Push main kitchen beam out two inches toward the great room. Decrease main kitchen beam size two inches. Move chandler electrical box to line up with the tenth riser on the staircase and centered between stairs and opposing wall. Add built in at main house, second floor guest bathroom. Move low voltage wire in guest house, single car side to kitchenette wall. Add two additional parking spaces near front porch R. David would like to make the driveway 2 feet wider. Raise wainscoting height as much as possible.
Work Completed or Work in Progress notes: All shower floors were laid out and the home owners have approved for installation. The home owners would like to lay the master shower tile out so all brown tiles are on the top and bottom, this will maximize use of green tiles at eye level. Master bath and kitchen sinks and faucets were delivered and installation layout completed. Extension jams were being installed in the 1st floor studio. Panel work for the studio was being prepared for installation. The second floor guest bedroom window seat was complete with the exception of pulls and hinges. Threshold protection was being completed on the first floor main house exterior doors. Exterior priming was completed on the rear porch columns. Electrical trim out was being completed in the main house attic and garage attic. Interior window trim was being completed in the master bath. Exterior paint was being completed on the covered walkway and main house. The dryer booster fan was installed in the second floor guest bedroom. Plywood was being removed from the main house deck framing. Grade work was being completed below the deck. Exterior window trim was completed on the main house. 2 Brothers was contacted and notified the house is completed and is ready for all remaining stucco work. Base board installation was started on the second floor of the main house. Floor protection was completed in the master bath and water closet. The new plans were received and reviewed on site. Hunter still has a few additional revisions. Nathan will contact Hunter.


Gregory Barber entered the following on 21:38:41 Aug/07/2009:
Weather Conditions:partly sunny, 92*
Date
:
August 07, 2009
Employees Working on site: Greg Barber, Dan Burke, Jeff Collins, Gerson Morales, Rolando Nunez, Nicholas Rojas, Ed Ernst
Subcontractors on site: AGA- 1, JTS-1, CCS; electrical-1, Cuda Painting-1, Prestige Stone-2, CCS; HVAC-3
Visitors: Mr Sneddon came by briefly
Equipment Used: The manlift and arctic heater, backhoe and 30 bunks of scaffolding were on site but not used.
Urgent Items and Equipment Needed
:
None
Possible Change Order Items: None
Work Completed or Work in Progress notes: Interior trim in the Carriage House was done. The Master Bath floor tile was installed and grouted. Door jamb installation and asing was done on the 1st and 2nd floors. Exterior painting continues with the painting of the porch ceilings. Cabinet and threshold protection were done. Fabrication of the Guest Bedroom window seat nears completion. Electrical wiring and lineset connection at the permanent HVAC units was done.


Gregory Barber entered the following on 07:21:52 Aug/07/2009:
Weather Conditions:partly cloudy with a high of 91
Date
:
August 06, 2009
Employees Working on site: Greg Barber, Dan Burke, Jeff Collins, Gerson Morales, Rolando Nunez, Nicholas Rojas, Danny Tracy, Ed Ernst
Subcontractors on site: JTS- 1, AGA-1, Cuda Painting- 3, MMC- 2, CCS electrical- 1, CCS- HVAC- 1, Prestige Stone- 3,
Visitors: No visitors today
Equipment Used: The manlift and arctic heater, and 30 bunks of scaffolding were on site but not used. The backhoe was delivered to the site, but not used.
Urgent Items and Equipment Needed
:
None
Possible Change Order Items: None
Work Completed or Work in Progress notes: Vanities in the Carriage House were installed and protected. Interior trim in the Carriage House is on-going. Exterior painting continues with work concentrating on the porches. Wood flooring was installed in the second floor hall and Master Bedroom. Window seat assembly is on-going. Floor tile was done in the Master Bath. Casing in the Master Bedroom was installed.


Gregory Barber entered the following on 18:22:26 Aug/05/2009:
Weather Conditions:Mostly sunny, 88*
Date
:
August 05, 2006
Employees Working on site: Greg Barber, Jeff Collins, Gerson Morales, Rolando Nunez, Danny Tracy, Ed Ernst
Subcontractors on site: JTS- 1, AGA- 1, CCS: Electrical- 1, Cuda Painting- 3, Prestige Stone- 3, MMC- 3
Visitors: Mr Sneddon
Equipment Used: The manlift and arctic heater, and 30 bunks of scaffolding were on site but not used. The forklift was used for four hours.
Urgent Items and Equipment Needed
:
None
Possible Change Order Items: None
Work Completed or Work in Progress notes: Second floor hallway/ Foyer crown molding installation was completed. Guest Bedroom window seat installation was begun. Master Suite window and door casing installation is ongoing. The Master Bath floor tile was laid out and approved by Mr Sneddon. The blockwork for the Master shower seat was installed (this may need to be higher). Shower walls were waterproofed. The bathroom vanities were delivered. Interior trim was done in the Carriage House. Wiring of the Main House electrical panels is ongoing. The yard was cleaned and organized to make working room for the driveway installation. Unnecessary equipment was removed from the site.


Gregory Barber entered the following on 21:15:04 Aug/04/2009:
Weather Conditions:Partly cloudy, 90*
Date
:
August 04, 2009
Employees Working on site: Greg Barber, Dan Burke, Jeff Collins, Gerson Morales, Rolando Nunez, Danny Tracy, Ed Ernst
Subcontractors on site: JTS- 1, AGA- 1, Cuda PAinting- 3, Prestige Stone- v$, MMC- 2, CCS- HVAC-2, CCS Electrical-1
Visitors: Mr. Sneddon and friends
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but not used
Urgent Items and Equipment Needed
:
No foreseen issues to report
Possible Change Order Items: No changes to report
Work Completed or Work in Progress notes: Flooring protection in the Carriage House was done. Carriage House kitchinette cabinet installation was completed. The waterproofing and mudset was done at the Carriage House showers. Tree protection and silt fencing was relocated for the driveway installation. Exterior painting and paint prep is ongoing. Column bases were permanently attached along the covered walkway and porch. Second floor hall crown molding installatioin continues. The radius balcony nosing was fit and installed. The straight nosing is cut and fit. Casing installation in the Master Suite continues. Shower waterproofing and mudset were done in the Master Bath. Cabinets were installed in the Studio. HVAC boots were installed at the two window seat locations. Kitchen cabinet layout was done. A mockup of the Master Hall chair rail was made and tacked up for approval.


Gregory Barber entered the following on 21:02:22 Aug/04/2009:
Weather Conditions:Partly cloudy, 89*
Date
:
August 03, 2009
Employees Working on site: Greg Barber, Dan Burke, Jeff Collins, Gerson Morales, Rolando Nunez, Danny Tracy, Ed Ernst
Subcontractors on site: JTS-1, AGA- 1, Cuda Painting- 3, Prestige Stone- 3,MMC- 2
Visitors: No visitors today
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used for the entire day to condition the main house and garage apartment
Urgent Items and Equipment Needed
:
No foreseen issues to report
Possible Change Order Items: No changes to report
Work Completed or Work in Progress notes: Crown molding in the second floor hall was done. Balcony floor nosings were laid out. Casing was done in the Master Suite. The Carriage House flooring installation was completed and protection begun. Exterior painting and paint prep is ongoing. The Master Bath mudset for floor tile was done. Kitchinette cabinets in the Carrige House were installed.


Tim Beaulieu entered the following on 20:30:29 Jul/30/2009:
Weather Conditions:Sunny and Clear, Heavy afternoon showers
Date
:
July 30, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Billy Bowers, Greg Barber, Rolando Nunez, Danny Dracy, Dan Burke, Jeff Collins, Ed E
Subcontractors on site: AGA-1, CCS-2, Cuda Company-3, Prestige-3, MMC-2,
Visitors: No visitors today
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used for the entire day to condition the main house and garage apartment
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The driveway was laid out and prepared and the site prepared for heavy equipment work. No cuts was called to flag the front of the property. Interior trim was installed in the second floor hall. Cedar was installed in the second floor mechanical room closet. SYP flooring was installed in the garage apartment. Exterior painting was being completed on the garage. Cabinetry was installed in the main house laundry room. Crown was installed in the master baths water closet. A walk thru was completed with Ed E


Tim Beaulieu entered the following on 19:52:28 Jul/30/2009:
Weather Conditions:Sunny and Clear in AM, Heavy winds and Rain in PM
Date
:
July 29, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Jeff Collins, Billy Bowers, Danny Tracy, Rolando Nunez
Subcontractors on site: MMC-3, CCS-4, ACC-1, Cuda Company-3
Visitors: David was on site to view progress
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used for the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
A meeting was schedules with the Sneddons and MMC at the Oldfield house on 072909 @ 1200
Possible Change Order Items: Cabinets will be constructed by MMC and will meet Oldfield Specs.
Work Completed or Work in Progress notes: HVAC duct work was being completed in the garage apartment. Cedar was being installed in the 2nd floor storage room. Doors and windows were being cased in the 2nd floor guest bedroom and studio. SYP flooring was being completed in the hall and master bedroom. Crown was installed in the pantry and laundry room. Cabinetry was installed in the laundry room. Exterior painting was being completed on the garage and covered walkway. Floor protection was installed in the great room, main hall, pantry and master bedroom. The garage apartment was cleaned out and prepared for flooring.


Tim Beaulieu entered the following on 23:22:25 Jul/29/2009:
Weather Conditions:Sunny and Clear through out the day, High in the upper 80's
Date
:
July 28, 2009
Employees Working on site: Tim Beaulieu, Geran Morales, Nicholas Royas, Billy Bowers, Dan Burke, Jeff Collins, Rolando Nunez, Rolando Nunez
Subcontractors on site: CCS-3, ACC-1, Cuda Company-3
Visitors: The Sneddons were on site this afternoon to view the installed cabinetry.
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but not used
Urgent Items and Equipment Needed
:
David stated the bathroom vanity cabinets seem to low and did not match what was in Oldfield. I have measure the cabinets in Oldfield and have found a four inch descrepancy. MMC was contacted and will be making new cabinets to the Oldfield Specs
Possible Change Order Items: No known changes at this time.
Work Completed or Work in Progress notes: Interior trim was being completed on the second floor in the studio and guest bedroom. SYP flooring was installed in the great room and pantry, laundry room and hall. Exterior painting was being completed on the covered walkway. The ERV in the garage bonus room was completed. HVAC work was being completed in the second floor mechanical closet.


Tim Beaulieu entered the following on 21:23:30 Jul/29/2009:
Weather Conditions:Sunny and Clear in AM, Heavy PM Showers
Date
:
July 27, 2009
Employees Working on site: Tim Beaulieu, Geran Morales, Nicholas Royas, Billy Bowers, Dan Burke, Jeff Collins, Rolando Nunez, Rolando Nunez
Subcontractors on site: CCS-3, ACC-1, Cuda Company-3, Prestige-2
Visitors: No visitors today
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but not used
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Install redguard in kitchen on mud set
Work Completed or Work in Progress notes: Interior trim was being completed on the second floor in the studio and guest bedroom. SYP flooring was installed in the great room and second floor hall. The kitchen redgaurd process was completed. Exterior painting was being completed on the covered walkway. The ERV in the garage bonus room was completed. HVAC work was being completed in the second floor mechanical closet.


Tim Beaulieu entered the following on 08:32:12 Jul/26/2009:
Weather Conditions:Sunny and Clear Through out the day
Date
:
July 23, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Jeff Collins, Danny Tracy, Greg Barber
Subcontractors on site: JTS-1, AGA-1, CCS-4, Prestige-4, Cuda Company-4
Visitors: The home owners were on site today to review progress.
Equipment Used: The man lift, artic heater, 30 bunks of scaffolding were on site but not used. The forklift was onsite and used for 1 hour. Three temp HVAC units were on site and used the entire day to condition the main house
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The covered walkway was being prepared for priming. Tile work was being completed in the 2nd floor main house bathrooms. Crown moulding was being completed in the master bedroom closets. SYP flooring was being installed in the great room, 2nd floor main hall and mechanical room. HVAC units were being installed in the 2nd floor guest bedroom mechanical closet. Mock ups of windows and doors were completed and approved by the Sneddons.


Tim Beaulieu entered the following on 05:41:55 Jul/24/2009:
Weather Conditions:Sunny and Clear upper 80's
Date
:
July 22, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Billy Bowers, Greg Barber, Billy Bowers, Danny Tracy
Subcontractors on site: CCS-3, AGA-1, JTS-1, Prestige Stone-4, Cuda Company-1
Visitors: The Sneddons were on site to review tile mock up and interior trim mock ups.
Equipment Used: The man lift, artic heater, 30 bunks of scaffolding were on site but not used. The forklift was onsite and used for 1 hour. Three temp HVAC units were on site and used the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: The Sneddons would like to change out the first floor studio baths tiles.
Work Completed or Work in Progress notes: Tile was being installed in the garage apartments bathrooms. Extension jams were being completed in the 1st floor study. Window trim was being completed in the second floor studio bath. SYP flooring was install in the great room.


Tim Beaulieu entered the following on 19:07:53 Jul/23/2009:
Weather Conditions:Sunny and Clear, High in the mid 80's
Date
:
July 21, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez,Greg Barber, Jeff Collins, Danny Tracy, Billy Bowers
Subcontractors on site: Prestige Stone-4, CCS-3, AGA-1, JTS-1
Visitors: No visitors today
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but used. Three temp HVAC units were on site and used the entire day to condition the main house and garage.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Current front door and double exterior, trim mock ups have been approved.
Work Completed or Work in Progress notes: SYP flooring was being completed in the foyer and great room. Tile layout was completed for the bath floors with the exception of the 1st floor study bath. HVAC work was being completed in the garage attic and Second floor mechanical closet. Various interior trim mock ups were being completed for approval.


Tim Beaulieu entered the following on 05:56:50 Jul/21/2009:
Weather Conditions:Sunny and Clear, High in the upper 70's
Date
:
July 20, 2009
Employees Working on site: Tim Beaulieu, Duane Constantino, Ed E, Greg Barber, Nicholas Royas, Danny Tracy, Billy Bowers
Subcontractors on site: AGA-1, JTS-1, Prestige Stoneworks-2
Visitors: The home owners were on site to review progress
Equipment Used: the manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but used. Three temp HVAC units were on site and used the entire day to condition the main house and garage.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Crown moulding detail was discussed, further mock ups will be completed for the home owners approval.
Work Completed or Work in Progress notes: Foundation fencing was being completed on the rear of the porch. Exterior trim was being completed on the garage balcony. Extension jams were being completed in the 1st floor studio. All tile and delivered and staged in the main house. Control lines were apply to the first floor and grounds installed to begin flooring. Shower pans were being installed in the garage apartment.


Tim Beaulieu entered the following on 05:51:17 Jul/21/2009:
Weather Conditions:Sunny and Clear, High in the mid 80's
Date
:
July 17, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Jeff Collins, Billy Bowers, Danny Tracy
Subcontractors on site: AGA-1, JTS-1, YRP-1
Visitors: No visitors today
Equipment Used: he manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but used. Three temp HVAC units were on site and used the entire day to condition the main house and garage.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Durock and shower pan were installed in the master bathroom. The shower pan is being water tested. Exterior handrail was installed on the garage balcony facing the main house. Copper flashing caps were installed on the covered walkway.


Tim Beaulieu entered the following on 10:35:08 Jul/20/2009:
Weather Conditions:Sunny and Clear
Date
:
July 16, 2009
Employees Working on site: Tim Beaulieu,Nicholas Royas, Ed E. Greg Barber, Jeff Collins, Danny Tracy, Billy Bowers
Subcontractors on site: CCS-3, AGA-1, JTS-1, Big Horn-1
Visitors: No visitors today
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but used. Three temp HVAC units were on site and used the entire day to condition the main house and garage.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: Crown mock up are were completed above the exterior double doors.
Work Completed or Work in Progress notes: Durock was being completed on the first floor of the main house. Exterior trim was installed on the covered walkway and is completed. Foundation fencing was being installed and is 80 percent completed. The main house master shower pan was glued up and will be installed and water tested on Friday. HVAC units were being installed in the main house attic. Installation is nearing completion. Greg Barber will go to the shop on Friday to fabricate HVAC grils for the garage apartments ceiling.


Tim Beaulieu entered the following on 10:31:16 Jul/20/2009:
Weather Conditions:Sunny and Clear in AM, Overcast and light rain in PM, High of 85 Degrees
Date
:
July 14, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Ed E. Greg Barber, Jeff Collins, Danny Tracy, Billy Bowers
Subcontractors on site: ACC-1, AGA-1, JTS-1, YRP-5
Visitors: No visitors today
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but used. Three temp HVAC units were on site and used the entire day to condition the main house and garage.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The crown moulding is running into the transom window heads. A new detail is needed.
Work Completed or Work in Progress notes: The pool deck was washed and completed. Foundation fencing was installed around the side of the main house. Durock was being completed in the second floor bathrooms. Exterior trim was being installed on the covered walkway. Exterior trim and siding was being primed.


Tim Beaulieu entered the following on 18:39:04 Jul/14/2009:
Weather Conditions:Sunny and Clear in AM, Heavy afternoon showers
Date
:
July 13, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Danny Tracy, Jeff Collins, Greg Barber, Ed E, Billy Bowers
Subcontractors on site: AGA-1, JTS-1, YRP-6
Visitors: No visitors today
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but used. Three temp HVAC units were on site and used the entire day to condition the main house and garage.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Foundation fencing was being completed around the main house porch. Exterior trim was being installed on the covered walkway. Pool deck pavers were being completed. Shower pans were being completed on the second floor of the main house Durock work was completed in the 2nd floor showers.


Tim Beaulieu entered the following on 18:34:23 Jul/14/2009:
Memo:
Addendium

Todd Bowers and Dan Burke were working on site on July 10, 2009


Tim Beaulieu entered the following on 18:33:12 Jul/14/2009:
Weather Conditions:Sunny and Clear
Date
:
July 10, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Jeff Collins, Greg Barber, Danny Tracy, Ed E
Subcontractors on site: CCS-2, JTS-1, AGA-1
Visitors: No visitors today
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but used. Three temp HVAC units were on site and used the entire day to condition the main house and garage.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes at this time.
Work Completed or Work in Progress notes: Exterior trim was installed on the covered walkway. Plywood was being installed on the great room sleeper system. Extension jams were being completed on the garage apartment windows. Foundation fencing was being completed around the main house porch.


Tim Beaulieu entered the following on 05:56:47 Jul/10/2009:
Weather Conditions:Heavy AM showers, clearing in PM
Date
:
July 09, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Nicholas Royas, Ed E, Gerson Morales, Jeff Collins, Rolando Nunez, Danny Tracy, Billy Bowers
Subcontractors on site: JTS-1, AGA-1, YRP-1, CCS-3, Prestige Stone-1
Visitors: No visitors today
Equipment Used: The forklift, manlift, and 30 bunks of scaffolding were on site but not used. Three temp HVAC units were onsite and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Exterior trim was being completed on the covered walkway. The garage apartments ceiling is now completed. Finishing was schedule and the prep work was underway. The sleeper system in the great room was being completed. All 2x4 materials is installed. The floor outlets were moved to David’s specified location. Interior doors were being installed in the garage apartment.


Tim Beaulieu entered the following on 05:49:53 Jul/10/2009:
Weather Conditions:Sunny and clear in am, with PM showers
Date
:
July 8, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Billy Bowers, Greg Barber, Danny Tracy
Subcontractors on site: CCS-2, AGA-1, YRP-5, JTS-1
Visitors: Espy was onsite to deliver 2x4 treated for floor system in great room.
Equipment Used: The manlift, fork lift, and 30 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Move great room floor outlets.
Work Completed or Work in Progress notes: The crown moldings were mocked up in 2 variations, and is pending decision/approval. Exterior trim was being installed on the covered walkway and is roughly 80 percent completed. The rear pool deck construction is underway the pool deck work is 50 percent completed. The garage apartment ceiling is nearing completion. All ceiling boards are completed and trim work is remaining. The sleeper system was started in the great room. Foundation fencing and hardware cloth was being installed around the porches.


Tim Beaulieu entered the following on 06:06:38 Jul/09/2009:
Weather Conditions:Sunny with clouds in AM, PM Shower, high in the upper 80's
Date
:
July, 07 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Jeff Collins, Danny Tracy, Greg Barber
Subcontractors on site: AGA-1, JTS-1, YRP-6, CCS-3
Visitors: The home owners were onsite to view progress. CMF was on site to deliver the crown moulding package and flooring.
Equipment Used: The man lift, fork lift, and 30 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condition the garage and main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: All flooring and crown moulding was unload and staged in the main house. Exterior trim was installed on the covered walkway. Foundation fence hardware cloth was installed on the side of the house below the porch. The pool deck stone work is underway. The garage aparments ceiling was being completed.


Tim Beaulieu entered the following on 17:44:31 Jul/07/2009:
Weather Conditions:Sunny and Clear through out the day, High in the upper 80's
Date
:
July 06, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Jeff Collins, Danny Tracy, Gerson Morales, Rolando Nunez, Nicholas Royas
Subcontractors on site: CCS-1, AGA-1, JTS-1, YRP-4, ACC-2, Big Horn-2
Visitors: No visitors today
Equipment Used: The manlift, forklift, artic heater, and 30 bunks of scaffolding were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage apartment.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The great room ceiling finish was applied and completed. The garage apartments ceiling boards were being installed and is 80 percent completed. Lime stone sill were installed in all stucco window openings. The pool patio rough grade work and border was completed. All drainage work in the pool deck was completed. Exterior trim was being installed on the covered walkway. Hardware cloth was being installed below the main house deck behind the foundation fencing.


Tim Beaulieu entered the following on 05:53:34 Jul/06/2009:
Weather Conditions:Sunny and Clear high in the low 90's
Date
:
July 02, 2009
Employees Working on site: Tim Beaulieu, Jeff Collins, Greg Barber, Gerson Morales, Nicholas Royas, Danny Tracy
Subcontractors on site: AGA-1, JTS-1, YRP-5, CCS-1, ACC-4
Visitors: No visitors today
Equipment Used: The manlift and forklift were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage bonus rooms. 30 Bunks of scaffolding were usded the entire day to prep the great room ceiling.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The great room ceiling was being prepared for finishing work. The garage bonus room ceiling is now 50 percent completed. Exterior foundation fencing and hardware cloth was being installed on porches. Exterior trim was being installed on the cevered walkway. The pool deck work is ongoing.


Tim Beaulieu entered the following on 05:45:29 Jul/06/2009:
Weather Conditions:Sunny and Clear, High in the upper 80's
Date
:
July 1, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Jeff Collins, Danny Tracy
Subcontractors on site: CCS-2, AGA-1 JTS-1
Visitors: The Sneddons were on site to view progress.
Equipment Used: The man lift, fork lift, artic heater were on site but not used. 30 Bunks of scaffolding were on site and used for 1 hour. 3 temp HVAC units were on site and used for the entire day to condition the main house
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No know changes to report at this time.
Work Completed or Work in Progress notes: The ceiling in the garage bonus room was laid out and installation of SYP is underway. The rear pool deck paver work is 15 percent completed. The covered walkway exterior trim work was being completed. The garage was primed and prepared for finish work.


Tim Beaulieu entered the following on 19:57:52 Jun/30/2009:
Weather Conditions:Sunny and Clear, high in the low 90's
Date
:
June 30, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Jeff Collins, Danny Tracy
Subcontractors on site: AGA-1, JTS Construction-1, CCS-1, ACC-4, YRP-4
Visitors: The Sneddons were on site to review the Great room Ceilings wash.
Equipment Used: The manlift and forklift were on site but not used. Three temp HVAC units were on site and used the entire day to condition the main house and garage bonus rooms. 30 Bunks of scaffolding were on site but not used.
Urgent Items and Equipment Needed
:
Interior trim and Flooring is needed asap.
Possible Change Order Items: The Sneddons would like to change the approved Great room wash sample to what they have in Oldfield. 6 SYP boards will have to be sanded in the great room. The approved stain material was already purchased. The color is a custom blend and is not refundable.
Work Completed or Work in Progress notes: The great room wash was started in the balcony dormer. All HVAC grills were installed in the great room ceiling. The pool work was started. The pool deck was laid out and material carried to the rear of the property. Interior priming was being completed in the garage and bonus rooms. The garage door installation was completed, all motors are in place. HVAC duct work was being modified in the 2nd floor mechanical chase. Balcony trim boards and flashing was completed on the street side balcony. Exterior trim was installed on the covered walkway.


Tim Beaulieu entered the following on 19:19:30 Jun/29/2009:
Weather Conditions:Rain through out the AM, Clearing in PM, High in the Low 90's
Date
:
June 19, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Jeff Collins, Steve Stone
Subcontractors on site: AGA-1, JTS Construction-1
Visitors: No visitors today
Equipment Used: The fork lift and man lift were on site but not used. Two temp HVAC units were on site and used the entire day to condition the main house. 30 Bunks of scaffolding were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Balcony handrails were being installed on the street side of the garage. Copper Column flashing was being completed on the covered walkway columns. Ipe Decking was being installed on the garage balconies.


Tim Beaulieu entered the following on 16:11:55 Jun/28/2009:
Weather Conditions:Hot, High in the Mid 90's
Date
:
Tim Beaulieu
Employees Working on site: Tim Beaulieu, Jeff Collins, Steve Stone, Nicholas Royas
Subcontractors on site: AGA=1, JTS Construction-1
Visitors: David was on site to view progress
Equipment Used: The fork lift and man lift were on site but not used. Two temp HVAC units were on site and used the entire day to condition the main house. 30 Bunks of scaffolding were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The balcony on the street side of the garage was being completed. Copper flashing caps for the covered walkway columns were being fabricated. Siding was being completed on the garage. Herb from YRP was contacted and stated construction would begin on Tuesday.


Tim Beaulieu entered the following on 20:50:30 Jun/25/2009:
Weather Conditions:Sunny, High in upper 80's
Date
:
June 24, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Rolando Nunez, Danny Tracy, Jeff Collins, Steve Stone
Subcontractors on site: JTS Construction-1
Visitors: No visitors today
Equipment Used: The man lift was on site and used for 1 hour to install siding on the front of the garage. The fork lift was on site but not used. Two temp HVAC units were on site and used for the entire day to condition the main house. 30 bunks of scaffolding was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Copper flashing caps were being fabricated for the covered walkway columns. Siding was being installed on the front of the garage. Handrail post were being installed on the garage balconies. Drainage was being installed at the pool deck location.


Tim Beaulieu entered the following on 20:54:43 Jun/24/2009:
Weather Conditions:Sunny and Clear, High in the low 90's
Date
:
June 23, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Jeff Collins, Rolando Nunez, Danny Tracy, Steve Stone
Subcontractors on site: CCS-3, JTS-1, AGA-1
Visitors: David was on site to review progress
Equipment Used: The man lift was on site and used for 3 hours to install siding on the front of the garage. The fork lift was on site but not used. Two temp HVAC units were on site and used for the entire day to condition the main house. 30 bunks of scaffolding was on site and used for 6 hours to install the great room ceiling boards.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David would like to change the location of the tv in the garage bonus room above the garage. The wire needs to be located next to the exterior french door.
Work Completed or Work in Progress notes: Siding was being installed on the front of the garage. The great room ceiling board installation was completed. We have 6000 LFT remaining of 1x6 SYP for ceilings. I will discuss with owners regarding which ceilings could be completed. HVAC units were being installed in main house attic. Electrical panels were being dressed out. The electrical for the washer and dryer in the garage was completed. Paul Miller with the PBDRB was contacted regarding shutter colors and design . Paul stated he would review the colors on the mock up and schedule for this Thursdays meeting.


Tim Beaulieu entered the following on 20:46:23 Jun/24/2009:
Memo:
Previous site reports date is incorrect and should read June
22, 2009. 


Tim Beaulieu entered the following on 05:41:59 Jun/23/2009:
Weather Conditions:Hot and humid high in the upper 90's
Date
:
June 21, 2009
Employees Working on site: Tim Beaulieu, Danny Tracy, Nicholas Royas, Rolando Nunez, Jeff Collins, Steve Stone
Subcontractors on site: AGA-1, JTS Construction-1, CCS-3
Visitors: The home owners were on site this week to review progress.
Equipment Used: The man lift was on site and used for 2 hours to install siding on the garage. The forklift was on site but not used. Two temp HVAC units were on site and used the entire day to condition the main house. 30 bunks of scaffolding were onsite and used the entire day to install the great room ceiling
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Siding was being installed on the front of the garage. Plywood underlayment was completed through out. The great room 1x6 SYP was being installed. The ceiling should be completed on Tuesday. Painters will be schedule for Wednesday to complete the pickled finish. Electrical work was being completed in the main house attic.


Tim Beaulieu entered the following on 05:36:54 Jun/23/2009:
Weather Conditions:Sunny and Clear high in the upper 90's
Date
:
June 19, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Jeff Collins, Steve Stone
Subcontractors on site: JTS-1, AGA-1, CCS-3
Visitors: No visitors today
Equipment Used: The man lift, fork lift and artic heater were on site but not used. Two temp HVAC units were on site and used the entire day to condition the main house. 30 Bunks of scaffolding were used the entire day to install the great room ceiling
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Add washer and dryer to the guest house garage was completed.
Work Completed or Work in Progress notes: The great room ceiling corner boards were being installed. Plywood underlayment was being completed on the second floor of the main house and garage. All interior doors were delivered. HVAC units were being installed in the main house attic. Exterior siding was being installed on the front of the garage. Interior pocket doors were completed.


Tim Beaulieu entered the following on 05:54:00 Jun/22/2009:
Weather Conditions:Sunny and clear high in the mid to upper 90's
Date
:
June 18, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Rolando Nunez, Gerson Morales, Jeff Collins, Steve Stone
Subcontractors on site: AGA-1, JTS Construction-1, CCS-3
Visitors: No visitors today
Equipment Used: The man lift was on site but not used. Two temp HVAC unit were onsite and used the entire day to condition the main house. The fork lift was on site and used for 1 hour to move materials. 32 bunks of scaffolding was on site and used the entire day to install the great room ceiling.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The great room ceiling was being completed. HVAC units were being installed in the main house attic. Electrical work was being completed in the main house attic. The 2nd layer of plywood was being completed on the 2nd floor of the main house. Interior doors are being installed. All pocket doors are completed.


Tim Beaulieu entered the following on 19:44:50 Jun/18/2009:
Weather Conditions:Sunny and clear high in the mid 90's
Date
:
June 17, 2009
Employees Working on site: Tim Beaulieu, Danny Tracy, Nicholas Royas, Rolando Nunez, Jeff Collins, Steve Stone
Subcontractors on site: AGA-1, JTS-1, Big Horn-1, CCS-3, MMC-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift and artic heater were on site but not used. Two temp HVAC units were on site and used the entire day to condition the main house. 30 Bunks of scaffolding were used the entire day to install the great room ceiling.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The great room ceiling corner boards were being installed. Plywood underlayment was being completed on the second floor of the main house. All interior doors were delivered. HVAC units were being installed in the main house attic. Exterior siding was being installed on the front of the garage.


Tim Beaulieu entered the following on 05:33:54 Jun/17/2009:
Weather Conditions:Sunny and clear high in the mid 90's
Date
:
June 16, 2009
Employees Working on site: Tim Beaulieu, Rolando Nunez, Danny Tracy, Jeff Collins, Steve Stone
Subcontractors on site: CCS-3, AGA-1, OM Roofing
Visitors: The home owners were on site today to review progress.
Equipment Used: The man lift was on site but not used. The forklift was on site and used for 1 hour to move plywood into the house. Two temp HVAC units were on site and used the entire day to condition the main house. 30 bunks of scaffolding were onsite and used the entire day to install the great room ceiling.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The great room ceiling fuax beam was completed. Plywood subfloor was completed on the first floor. The additional layer of plywood on the second floor was started in the 2nd floor studio. HVAC units were being installed in the main house attic. Electrical work was being completed in the main house attic. Roof flashing was being completed on the main house.


Tim Beaulieu entered the following on 07:54:13 Jun/16/2009:
Weather Conditions:Sunny and Clear, high in the low 90's
Date
:
June 15, 2009
Employees Working on site: Tim Beaulieu, Rolando Nunez, Danny Tracy, Steve Stone, Jeff Collins
Subcontractors on site: CCS-1, JTS Construction-1, AGA-1, Joey Dooline-1, ACC-1, Big Horn-1
Visitors: Mrs Sneddon was on site to review paint selections for the great room.
Equipment Used: The man lift was on site but not used. The fork lift was on site and used for 1 hour to move materials. Two temp HVAC units were on site and used the entire day to condition the main house. 30 bunks of scaffolding were on site and used in the great room to frame the fuax beam.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The fuax beam was being framed in the great room. Plywood was being installed on the first floor sleeper system. The foyer art lighting change order was completed. The pool deck retaining wall was laid out and construction will begin on Wednesday. The second floor was being leveled. Garage door casing was completed in the single car garage.


Tim Beaulieu entered the following on 07:47:29 Jun/16/2009:
Weather Conditions:Sunny and Clear
Date
:
June 12, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Danny Tracy, Greg Barber, Steve Stone, Jeff Collins
Subcontractors on site: CCS-3, AGA-1, JTS-1, OM Roofing-5
Visitors: No visitors today
Equipment Used: The manlift was on site and used for 1 hour to install siding on the garage. The fork lift was on site and used for 2 hours to move and stage materials. Two temp HVAC units were on site and used the entire day to condition the main house. 30 bunks of scaffolding were used the entire day to install the great room ceiling.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Electrical work was being completed in the main house attic. The great room ceiling is now 50 percent completed. The fuax beam framing is being completed. The first floor sleeper system is now 30 percent completed. All insulation was delivered today by Capital Materials.


Tim Beaulieu entered the following on 07:41:13 Jun/16/2009:
Weather Conditions:Sunny and clear
Date
:
June 11, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Danny Tracy, Greg Barber, Steve Stone, Jeff Collins
Subcontractors on site: CCS-3, AGA-1, JTS Construction-1
Visitors: No visitors today
Equipment Used: The man lift and fork lift were on site but not used. 30 Bunks of scaffolding were used the entire day to install the great room ceiling boards. Two temp HVAC units were on site and used the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Add washer and dryer to single car garage.
Work Completed or Work in Progress notes: Ceiling boards were being installed in the great room. HVAC duct work was being completed in the main house attic. The main house sleeper system was being completed on the first floor.


Tim Beaulieu entered the following on 08:08:30 Jun/11/2009:
Weather Conditions:Hot and Humid, High in the mid 90's
Date
:
June 10, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Danny Tracy, Jeff Collins, Steve Stone, Rolando Nunez, Greg Barber
Subcontractors on site: CCS-3, OM Roofing-5,
Visitors: Wood Tec was on site to deliver 1x6 SYP for ceiling material. Joey Dooline and Dorithy Sneddon were on site to review fuax painting schedule. Becky from the Light Post was on site
Equipment Used: The man lift, fork lift, and artic heater were on site but not used. Two temp HVAC units were on site and used the entire day to condition the main house. 23 Bunks of scaffolding were being used in the great room to install SYP ceiling boards.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: SYP ceiling boards were being installed on the great room ceiling. Roof panels were being installed on the covered walkway. Garage door casing was installed. Garage doors are scheduled for installation on Tuesday.


Tim Beaulieu entered the following on 07:32:22 Jun/11/2009:
Weather Conditions:Sunny and clear, high in the low 90's
Date
:
June 09, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Jeff Collins, Steve Stone, Greg Barber, Danny Tracy
Subcontractors on site: CCS-1, JTS-1, ACC-5, OM roofing-5
Visitors: No visitors today
Equipment Used: The man lift was on site and used for 1 hour to install siding on the front of the garage. The forklift and artic heater were on site but not used. Two temp HVAC units were on site and used the entire day to condition the main house. 6 bunks of scaffolding was used for 8 hours to install V Groove cypress on the covered walkway ceiling.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Cyrpess ceiling board were installed on the covered walkway. The interior of the main house was being primed. Roof flashings were being completed on the front of the garage. The 2nd floor of the main house was being sanded and prepared for underlayment.


Tim Beaulieu entered the following on 20:05:14 Jun/09/2009:
Weather Conditions:Sunny High in the upper 80's, Light AM showers
Date
:
June 08, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Jeff Collins, Steve Stone, Greg Barber, Danny Tracy
Subcontractors on site: ccs-1, OM Roofing=5, Butch-1, JTS Construction-1, ACC-4,
Visitors: No visitors today
Equipment Used: The man lift was on site and used for 1 hour to install exterior trim on the garage. The forklift was on site but not used. Two temp HVAC units were on site and used for the entire day to condition the main house. 4 bunks of scaffolding were on site and used to install v groove cypress for 7 hours. The artic heater was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: V Groove cypress ceiling boards were being installed on the covered walkway. Electrical transfer switch wiring was completed. Interior priming was being completed in the main house. Sheet rock mud work was being completed in the garage. Exterior trim was being completed on the garage gable. Roof panels were being installed on the main house lower gable roof.


Tim Beaulieu entered the following on 08:16:31 Jun/08/2009:
Weather Conditions:Sunny and Clear in the AM, Heavy afternoon rains
Date
:
June 05, 2009
Employees Working on site: Tim Beaulieu, Jeff Collins, Steve Stone, Nicholas Royas, Danny Tracy, Greg Barber
Subcontractors on site: CCS-2, JTS Construction-1, OM Roofing-5, ACC-1, Butch-4
Visitors: No visitors today
Equipment Used: The man lift and artic heater were on site but not used. 6 bunks of scaffolding were being used the entire day to trim the covered walkway. The fork lift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The rear porches box beam framing was completed. The covered walk ways roof underlayment was completed. Sheet rock mud work was being completed in the main house and garage. Roof panels were installed on teh main house lower gable.


Tim Beaulieu entered the following on 11:31:11 Jun/05/2009:
Weather Conditions:Sunny and clear afternoon Light AM rain showers, High in the mid 80s'
Date
:
June 04, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Nicholas Royas, Jeff Collins, Steve Stone
Subcontractors on site: CCS-4, JTS Construction-1, Butch-4, OM Roofing-5
Visitors: The home owners were on site to review progress
Equipment Used: The man lift and artic heater were on site but not used. The fork lift was on site and used for 1 hour to move materials. Two HVAC units were on site and used the entire day to condition the main house. 8 bunks of scaffolding was on site and used the entire day to install the main house shed roof walkway connection.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Covered walkway sheathing and underlayment was completed. Sheet rock mud work was finished in the main house. Electrical circuits were being installed in the covered walkway. The garage attic sheet rock was installed. Roof panels were installed the main house lower roof system. Primer was dropped off for the main house. Shutter mock ups were being completed and reviewed. The porchs box beam trim out is now 95 percent complete. HVAC units were being installed in the main house attic.


Tim Beaulieu entered the following on 06:56:05 Jun/04/2009:
Weather Conditions:Sunny and clear, High in the upper 80's
Date
:
June 03, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Greg Barber, Danny Tracy, Jeff Colllins
Subcontractors on site: CCS-4, JTS Construction-1, Butch-2
Visitors: Espy was on site to deliver the all underlayment and the first floor sleeper system. Mrs Sneddon was on site to review shutter colors.
Equipment Used: The fork lift was used for 6 hours to installed sheathing on the covered walkways roof. 6 Bunks of scaffolding was used the entire day to install main house rafters and the rear porches box beam trim. The man lift and artic heater were on site but not used. Two temp HVAC unit were on site and used the entire day to condition the main house.
Urgent Items and Equipment Needed
:
Skip called regarding the flooring and 1x6. I discussed what to do with material. Skip is onboard.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The covered walkway had roof sheathing and v groove cypress installed. The connection at the main house was completed all rafters have been tied to the connector. Sheet rock mud work was completed in the main house and garage apartment. HVAC units were being installed in the main house attic. The rear porches box beam was being completed and is now 75 percent finished.


Tim Beaulieu entered the following on 07:24:32 Jun/03/2009:
Weather Conditions:Sunny and Clear High in the low 90's
Date
:
June 02, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Jeff Collins, Greg Barber, Danny Tracy
Subcontractors on site: CCS-4, OM Roofing-5, Butch-4, JTS Construction-1
Visitors: No visitors today
Equipment Used: The man lift was on site but not used. Two temp HVAC unit were on site and used the entire day. The fork lift was on site and used for 3 hours to install sheathing on the covered walkways roof. 4 bunks of scaffolding was used the entire day to install trim on the rear porch and covered walkway framing.
Urgent Items and Equipment Needed
:
The Sneddon called and stated that they did not want the C grade SYP flooring. I have discussed options with the Sneddons. The home owners stated they would like to purchace an additional 3000 LFT of D grade Syp and mix it with the already purchased C grade. 3000 LFT C Grade and 3000 LFT D Grade SYP will be used for flooring. The additional 3000 lft of C grade SYP will be milled down to 1x6 and used on the great room ceiling and garage apartments ceiling.
Possible Change Order Items: Purchace 3000 LFT D Grade SYP ASAP. MMC has been directed to purchace this material today.
Work Completed or Work in Progress notes: The covered walkways roof system was being sheathed. Electrical circuits were being installed in the walkway. The main house shed roof at the walkways connection was being taken apart and prepared for framing. THe rear porches box beam was being trimmed out. Sheet rock mud work was being completed in the main house and garage. THe brackets were installed on the garage apartments balconies. Roof panels were being installed on the gable roof of the main house. Hurricane clips were being installed on the covered walkways framing. Sheet rock was scheduled for priming on Friday, the house will be prepared on Thurdays. The floors sleeper system will be delivered on Wednesday.


Tim Beaulieu entered the following on 16:26:15 Jun/02/2009:
Weather Conditions:Sunny and Clear, High in the low 90's
Date
:
June 1, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Jeff Collins, Greg Barber, Danny Tracy
Subcontractors on site: CCS-1, JTS Construction-2, Butch-4, OM Roofing-6
Visitors: No visitors today
Equipment Used: The manlift was on site and used for 1 hour to complete garage roof flashings. Two temp HVAC unit were on site and used the entire day to condition the main house. The fork lift and artic heater were on site but not used. 8 Bunks of scaffolding were on site and used the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Roof panels were being installed on the front porches shed roof. Garage balcony brakets were being completed. Covered walkway framing was ongoing. Sheet rock mud work was being completed in the main house and garage apartment. The rear porch box beam was being trimmed out.


Tim Beaulieu entered the following on 07:42:26 Jun/01/2009:
Weather Conditions:Sunny and Clear, high in the upper 80's
Date
:
May 29, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Nicholas Royas, Jeff Collins, Steve Stone
Subcontractors on site: CCS-2, AGA-1, JTS Construction-1, OM Roofing-6, Butch-4,
Visitors: The Home owners were on site to review shutter colors. 2 16' 1x12 s4s cypress were cut into 8 foot sections for shutter mock ups.
Equipment Used: The fork lift was on site and used for 1 hour to move materials. The artic heater and man lift were on site but not used. Two temp hvac units and 6 bunks of scaffolding were on site and used for the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Sneddons called late in the day to ask if the Gliddon store in Blufton could provide all the paint to paint the house. I advised the Sneddons that we did already award paint contract but I would discuss with Danny.
Work Completed or Work in Progress notes: The covered walkways rafters were being installed. The main house interior stair case framing was completed. Roof panels were being installed on the front of the main houses porch shed roof. The rear porches box beam pack out was being completed. Sheet rock mud work was being completed in the great room and garage apartment.


Tim Beaulieu entered the following on 21:04:55 May/28/2009:
Weather Conditions:Sunny and Clear, High in the mid 80's
Date
:
May 28, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Jeff Collins, Steve Stone, Greg Barber
Subcontractors on site: CCS-1, AGA-1, JTS Construction-1, Hunter Plubming-2, OM Roofing-4, Butch-4, MMC-2
Visitors: The home owners were on site with three guest to view the site. BJSWA was on site to review the finished sewer tie in. Year Round Pool was on site to drop off pool and patio material.
Equipment Used: The artic heater, forklift, manlift, Yamaha Generator were on site but not used. Two temp HVAV units were on site and used for the entire day. 5 bunks of scaffolding were on site and used for 9 hours to install the covered walkway rafters.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The main house stair stringers were installed. The covered walkway roof system was being assembled. Roof panels were being installed on the main house lower gable section. The plumbing vent was installed through the roof. The pot fillers water line above the stove in the main house kitchen was roughed in. Sheet rock mud work was being completed in the main house and guest house. Electrical conduit was installed to the driveways middle planter. The main sewer and water supply line was completed and the trench covered. An additional line was run from the house to the street for irrigation. The rear porch beams pack out was worked on and is nearing completion. All silt fencing was cleaned up and erected.


Tim Beaulieu entered the following on 15:12:55 May/28/2009:
Weather Conditions:Sunny and clear in PM, Heavy AM showers
Date
:
May 27, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Jeff Collins, Steve Stone, Danny Tracy, Nicholas Royas
Subcontractors on site: CCS-1, AGA-1, Butch-4, OM Roofing-4, Hunter Plumbing-2, JTS Construction-1
Visitors: David Sneddon and Paul Miller for PBDRB were on site to review rear porch columns. BJSWA inspections department was on site to approve the main sewer tie in.
Equipment Used: The man lift and artic heater were on site but not used. Two temp HVAC units were on site and used the entire day. The fork lift was on site and used for 1 hour to unload an Espy delivery. 6 Bunks of scaffolding was used the entire day to install the rafters on the cover walkway.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time..
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The covered walkway rafters were being installed. Sheet rock bedding compound was being applied through out the main house. The main house stair case was being framed. The roof was being installed on the rear hip section. The roofers departed in the AM due to heavy rains. The sewer was excavated and inspected. The sewer ditch as been approved to cover by BJWSA. Rear porch beam framing pack outs were being completed. Screen porch, take off and material list were being collected for pricing and approval.


Tim Beaulieu entered the following on 08:27:21 May/27/2009:
Weather Conditions:Sunny and Clear, high in the mid 80's
Date
:
May 26, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Jeff Collins, Steve Stone, Nicholas Royas, Danny Tracy
Subcontractors on site: CCS-3, Hunter Plumbing-3, Cuda Company-4, AGA-1, JTS Construction-1, Big Horn-1, OM Roofing-4
Visitors: David was on site with guest to show house. Buds and Blooms was on site to review status of the site and hardscapes.
Equipment Used: The fork lift was on site and used for 1 hour to organize the yard and prepared site for sewer installation. 4 Bunks of scaffolding was used for 6 hours to install the covered walkway. The manlift and artic heater were on site but not used. Two temp HVAC units were on site and used for the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The column change order on the rear porch was completed. The main house interior stair case was being framed. The porch ceiling was being prepared for exterior paint. Sheet rock taping was being completed through out the main house. Screen porch material take offs were being completed. The main house attic walls and ceiling were being painted. The brick piers on the rear porch were motified for the column change order. The covered walkway ceiling joist were being installed. The main sewer line was installed to the street. The main house roof was being installed on the rear hip section. Hardscapes take offs were completed and are being priced out. Low voltage step lights conduit were being installed on the rear of the site.


Tim Beaulieu entered the following on 08:16:41 May/27/2009:
Weather Conditions:Sunny and Clear, high in the mid 80's
Date
:
May 26, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Jeff Collins, Steve Stone, Nicholas Royas, Danny Tracy
Subcontractors on site: CCS-3, Hunter Plumbing-3, Cuda Company-4, AGA-1, JTS Construction-1, Big Horn-1, OM Roofing-4
Visitors: David was on site with guest to show house. Buds and Blooms was on site to review status of the site and hardscapes.
Equipment Used: The fork lift was on site and used for 1 hour to organize the yard and prepared site for sewer installation. 4 Bunks of scaffolding was used for 6 hours to install the covered walkway. The manlift and artic heater were on site but not used. Two temp HVAC units were on site and used for the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The column change order on the rear porch was completed. The main house interior stair case was being framed. The porch ceiling was being prepared for exterior paint. Sheet rock taping was being completed through out the main house. Screen porch material take offs were being completed. The main house attic walls and ceiling were being painted. The brick piers on the rear porch were motified for the column change order. The covered walkway ceiling joist were being installed. The main sewer line was installed to the street. The main house roof was being installed on the rear hip section. Hardscapes take offs were completed and are being priced out. Low voltage step lights conduit were being installed on the rear of the site.


Tim Beaulieu entered the following on 08:15:39 May/27/2009:
Weather Conditions:Sunny and Clear, high in the mid 80's
Date
:
May 26, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Jeff Collins, Steve Stone, Nicholas Royas, Danny Tracy
Subcontractors on site: CCS-3, Hunter Plumbing-3, Cuda Company-4, AGA-1, JTS Construction-1, Big Horn-1, OM Roofing-4
Visitors: David was on site with guest to show house. Buds and Blooms was on site to review status of the site and hardscapes.
Equipment Used: The fork lift was on site and used for 1 hour to organize the yard and prepared site for sewer installation. 4 Bunks of scaffolding was used for 6 hours to install the covered walkway. The manlift and artic heater were on site but not used. Two temp HVAC units were on site and used for the entire day to condition the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The column change order on the rear porch was completed. The main house interior stair case was being framed. The porch ceiling was being prepared for exterior paint. Sheet rock taping was being completed through out the main house. Screen porch material take offs were being completed. The main house attic walls and ceiling were being painted. The brick piers on the rear porch were motified for the column change order. The covered walkway ceiling joist were being installed. The main sewer line was installed to the street. The main house roof was being installed on the rear hip section. Hardscapes take offs were completed and are being priced out. Low voltage step lights conduit were being installed on the rear of the site.


Tim Beaulieu entered the following on 10:29:49 May/26/2009:
Weather Conditions:Overcast through out the day, Sunny in PM
Date
:
May 22, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Greg Barber, Jeff Collins, Steve Stone
Subcontractors on site: CCS-3,
Visitors: No visitors today
Equipment Used: The man lift was on site but not used. The fork lift was on site and used for 1 hour to move materials. Two temp HVAC unit were on site but not used. The artic hearter was on site but not used. 6 Bunks of scaffolding was on site and used the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Flooring is going to be 1x12 C grade SYP.
Work Completed or Work in Progress notes: Ceiling joist were being installed on the covered walkway. The yard was cleared and prepared for the main sewer line installation. The main house interior stair case was being priced out and materials ordered. The cypress v groove ceilings were being prepared for paint. Hardscape material take offs were being completed and priced out. Main service feeders were being installed in the main house panels.


Tim Beaulieu entered the following on 08:16:09 May/22/2009:
Weather Conditions:Heavy rains through out the day, High in the low 70's
Date
:
May 21, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Greg Barber, Jeff Collins, Steve Stone
Subcontractors on site: AGA-1, JTS Construction-1, Cuda Company-3, CCS-5
Visitors: Waste Co was on site to change out dumpsters
Equipment Used: The man lift was on site but not used. The fork lift was on site and used for 1 hour to unload material. 6 Bunks of scaffolding were used the entire day to install the covered walkway framing. Two temp HVAC units were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The covered walkway beam work was being completed. Showers were being prepared for pans and liners. The front door was being primed. The main service conductors were being installed from the garage service yard to the 2nd floor mechanical room. V groove cypress was installed on the front porch ceiling. The rear porch beam was being packed out and prepared for finish trim work.


Tim Beaulieu entered the following on 19:23:01 May/21/2009:
Weather Conditions:Clear through out the day, high of 75 degrees
Date
:
May 20, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Nicholas Royas
Subcontractors on site: CCS-5, AGA-1, JTS Construction, Butch-6, OM Roofing-4, Big Horn-4
Visitors: The home owners were on site today with Jen from Stone works to review tile and stone areas of the project.
Equipment Used: The man lift was on site but not used. The fork lift was on site and used for 30 minutes to move materials. Two temp HVAC units were on site and being installed to the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time. David has approved the 35 KW gen set.
Work Completed or Work in Progress notes: The covered walkway columns were being installed. The LVL beam on the covered walkway is now 40 percent completed. Electrical conduit work was being completed on the rear porch step lights. Concrete was installed around all porch columns. Roof panels were being installed on the rear hip roof. Sheet rock was being installed in the guest house. The main houe sheet rock clean up process was underway and completed. The main house attic was fire taped. Temp HVAC duct work was installed on the main house.


Tim Beaulieu entered the following on 20:34:03 May/20/2009:
Weather Conditions:High of 55, Scattered Showers
Date
:
May 19, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Greg Barber
Subcontractors on site: JTS Construction-1, AGA-1, CCS-3, Butch-6, Big Horn-3, OM Roofing-5
Visitors: The home owners were on site to review progress, Espy was on site to deliver framing package for covered walkway
Equipment Used: The forklift was on site and used for 1 hour to move and unload material.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Covered walk way columns were being installed. Sheet rock hanging was being completed in the main house and garage 2nd floor. Electrical conduits were installed between the main house and garage service yards. The roof was being installed on the rear of the main gable.


Tim Beaulieu entered the following on 19:16:58 May/19/2009:
Memo:
Addendium previous site reports date should rear May 18, 2009.


Tim Beaulieu entered the following on 19:13:32 May/19/2009:
Weather Conditions:High of 56, Rain through out the day
Date
:
May 16, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Greg Barber, Jeff Collins
Subcontractors on site: CCS-4, AGA-1, Butch-5
Visitors: The owners were on site today to view progress
Equipment Used: Two temp HVAC units were delivered to the site, installation of units will begin in the AM. The fork lift and man lift were on site but not used. 4 Bunks of scaffolding was used for 3 hours.
Urgent Items and Equipment Needed
:
A power failure happened today through out Palmetto Bluff. Power was lost for roughly two hours. Sheet rock installers left the job early do to power failure.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Sheet rock was being installed on the great room ceiling. Exterior trim was installed on the rear porch. Rock wool was completed in the garage bonus rooms. The job site was cleaned and organized during the power failure.


Tim Beaulieu entered the following on 07:51:24 May/17/2009:
Weather Conditions:Heavy AM showers, High in the low 80's
Date
:
May 15, 2009
Employees Working on site: Tim Beaulieu, Greg Barber, Jeff Collins, Steve Stone, Nicholas Royas
Subcontractors on site: Butch-11, CCS-3, OM Roofing-4, AGA-1, JTS Construction-1
Visitors: Ryan with SCAD class to view construction
Equipment Used: The man lift was on site but not used. The forklift was on site and used for 30 minutes to move materials
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Sheet rock was being on in the kitchen and great room of the main house. Garage door jams were being completed. Low voltage punch work was being completed through out main house. Conduit work was being completed in the garage and main house service yard. Cypress v groove ceiling material was being installed on the rear porch. The rear porch chimmeny was being flashed.


Tim Beaulieu entered the following on 20:24:09 May/14/2009:
Weather Conditions:Sunny and Clear in the AM, PM Showers, high of 83.
Date
:
May 14, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Jeff Collins, Greg Barber, Steve Stone, Danny Tracy
Subcontractors on site: CCS-3, Butch-8, Big Horn-8, AGA-1, JTS Construction-1
Visitors: David Sneddon was on site to review rear porch piers and column work.
Equipment Used: The man lift and fork lift was on site but not used. All scaffolding was on site but not used.
Urgent Items and Equipment Needed
:
The PBDRB did not approve the new column design. CCS would like to pour concrete over exsisting conduit work from the main house to the guest house. The concrete solution will not work do to the pipe work running through a plant bed. The current pipe work will have to be lowered. Sat dish location as not been determined. This needs to be established as soon as possible.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Sheet rock was installed in the second floor guest bedroom and studio. Crown blocking was being installed through out. Feeder cables were delivered from Graybar. Exterior siding was installed on the master bedroom exterior wall. Rock wool was being installed in the guest house. The covered walkway material take off was completed and materials ordered. Garage door jams were being installed. Brick pier work was being completed on the covered walkway.


Tim Beaulieu entered the following on 17:33:30 May/14/2009:
Weather Conditions:AM Sunny and Clear, Heavy PM Showers
Date
:
May 13, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Greg Barber, Danny Tracy, Jeff Collins, Steve Stone
Subcontractors on site: CCS-1, JTS Construction-1, AGA-1
Visitors: Capital was on site to deliver sheet rock.
Equipment Used: The man lift was on site but not used. 10 Bunks of scaffolding was used for 3 hours. The forklift was on site and used for 1 hour to move material. The artic heater was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Rock wool was being installed in the main house. Dead wood blocking was being installed for crown, base and towel bars. The house was stocked with sheet rock. Speaker wire was being installed in the master bedroom and bath. Exterior siding and trim was being installed on the front porch. The garage covered walkway material take off was being completed.


Tim Beaulieu entered the following on 08:38:39 May/13/2009:
Weather Conditions:Sunny and Clear through out the day high in the mid 60's
Date
:
May 12, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Jeff Collins, Greg Barber, Steve Stone, Rolando Nunez, Billy Bowers, Danny Tracy
Subcontractors on site: AGA-1, JTS Construction-1, CCS-3, Big Horn-8,
Visitors: No visitors today
Equipment Used: THe man lift was on site but not used. The fork lift was on site and used for 1 hours to move materials. 12 Bunks of scaffolding was used the entire day to install exterior trim on the porch ceilings.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Exterior trim was being installed on the rear porch. Rock wool was installed in the foyer, kitchen, and great room. Speaker rough in kits were installed through out. Brick peirs were completed on the rear porch. Roof panels were being installed on the rear of the main house. Conduits were being installed in the main house service yard and garage service yard. Shower niches and shower curbs were being installed through out. The house was cleaned out and prepared for sheet rock stocking. The sheet rock contracter was contacted and will begin work on Thursday.


Tim Beeaulieu entered the following on 07:27:35 May/12/2009:
Weather Conditions:Sunny and Clear in AM, Heavy rain showers in afternoon, High in the low 90's
Date
:
May 11, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Greg Barber, Steve Stone, Billy Bowers
Subcontractors on site: AGA-1, JTS Construction-1, OM Roofing-4, Big Horn-8, Wildcat Steelworks-1
Visitors: Espy Lumber was on site to deliver additional framing material and plywood for shear walls.
Equipment Used: The man lift, and artic heater were on site but not used. The fork lift was on site and used for 30 minutes to unload material. 22 Bunks of scaffolding was used the entire day to install exterior trim and plywood install on great room shear wall.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The great room shear wall had plywood installed. Rock wool was installed in the master bedroom closets, 2nd floor guest bedroom, and 1st floor studio. Bricks were being installed on the rear porch peirs. Exterior trim ceiling fan blocks were being fabricated and prepared for installation. Crown moulding was installed on the front porch. Guest house shower walls and niches were being framed. The master bedroom exterior half column was installed. Chimmeny flashing was installed on the great room chimmeny.


Tim Beaulieu entered the following on 08:42:35 May/11/2009:
Weather Conditions:Sunny and Clear, high in the upper 80's
Date
:
May 09, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Jeff Collins, Greg Barber, Steve Stone
Subcontractors on site: CCS-4, AGA-1, JTS Construction-1, Big Horn-8, OEM Roofing-6
Visitors: Clyde Beaufort County building codes, The owners were on site to view progress
Equipment Used: The man lift, artic heater, and fork lift were on site but not used. 30 bunks of scaffolding was used to install exterior trim on the porches.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Sound Proof entire main house.
Work Completed or Work in Progress notes: Rock wool was being installed on the entire first floor. Crown moulding was being installed on the rear and side porch. Siding was being installed on the exterior of the master bedroom. Electrical conduit work was being completed in the guest house service yard. Capital Material was on site to deliver the remaining rock wool. Metal roof panels were being installed on the rear of the main house. Concrete was being poured for new column piers on the rear porch. Brick was being installed on the covered walkway.


Tim Beaulieu entered the following on 09:17:35 May/08/2009:
Weather Conditions:Sunny and Clear, High in the upper 80's
Date
:
May 07, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Greg Barber, Jeff Collins, Steve Stone, Billy Bowers, Rolando Nunez
Subcontractors on site: CCS-4, AGA-1, JTS Construction-1, Big Horn-8
Visitors: David was on site to review progress.
Equipment Used: The manlift was on site but not used. The fork lift was on site and is having issues with the onboard computer. Grist Equipment was onsite to service and order a rebuild kit for the controls. 30 Bunks of scaffolding was used the entire day to install exterior trim on the rear and side porch.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David stated he would like sound insulation installed in the entire structure.
Work Completed or Work in Progress notes: Rock wool was being installed in all bathrooms and hall walls. The front door columns were being installed. The crown was being installed on the rear porch. Cypress v groove was completed on the rear porch. A curb was constructed and installed on the main house roof for the outdoor grill vent termination. Roof panel take off was completed and material ordered. The roofs drip edge was installed around the entire main house. The walls were being cleaned and prepared for sheet rock. Additional rock wool was ordered. Brick piers were being constructed at the covered walkway.


Tim Beaulieu entered the following on 08:44:59 May/07/2009:
Weather Conditions:Sunny and Clear in AM, Overcast and light rain in PM, High of 85 Degrees
Date
:
May 06, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Steve Stone, Jeff Collins, Nathan Klien
Subcontractors on site: AGA-1, JTS-1, CCS-5, Big Horn-8, MMC-3
Visitors: No visitors today
Equipment Used: The man lift, fork lift, artic heater were on site but not used. The foam trailer was on site and used for 7 hours to spray foam in the garage. 30 Bunks of scaffolding was on site and used for 9 hours to installed exterior trim on the porch ceilings.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The front door was delivered and installed without the glass. Capital material was on site to deliver rock wool. Rock wall was being installed in the master bath room walls. The interior transom window rough opening was framed. Electrical panels were being dressed out in the main house. V groove cypress was installed on the rear porch and is nearing completion. Brick piers were being installed along the covered walkway. Spray foam insulation was being touched up in the garage. Foam insulation was being scraped from framing in the main house. Exterior siding and trim was being removed from the garage to make room for sheet rock work.


Tim Beaulieu entered the following on 06:42:25 May/06/2009:
Weather Conditions:Heavy PM Rains, Clear in the AM, High in the low 80's
Date
:
May 05, 2009
Employees Working on site: Tim Beaulieu, Jeff Collins, Nicholas Royas, Steve Stone
Subcontractors on site: CCS-3, AGA-1, JTS-1, Big Horn-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, and artic heater were on site but not used. The foam trailer was on site and used the entire day to complete touch up work in the main house. 30 bunks of scaffolding was used the entire day to install the porch ceilings.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: V Groove cypress was installed on the side and rear porch ceiling. Speaker rough in kits were installed on the rear porch. The covered walk way print was review by Kurt from Big Horn. Foam insulation touch ups were completed in the main house. Rock wool was being installed around all can lights. Electric panel work was being completed in the garage. The missing transom window was recieved and installed in the master bedroom.


Tim Beaulieu entered the following on 06:42:37 May/05/2009:
Weather Conditions:Sunny and Clear in the AM, Overcast in PM High in low 80's
Date
:
May 04, 2009
Employees Working on site: Tim Beaulieu, Gerson Moreales, Nicholas Royas, Dan Burke, Danny Tracy, Jeff Collins, Steve Stone
Subcontractors on site: CCS-3, JTS Construction-1, AGA-1, Hunter Plubming-3
Visitors: No visitors today
Equipment Used: The man lift, fork lift, and artic heater were on site but not used. The foam trailer was on site and used for the entire day to insulate the main house. 30 Bunks of scaffolding was used the entire day to install the porch ceilings.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: V Groove cyrpress was being installed on the front and side porch. Speakers were being laid out on the rear porch. Electric panel work was being completed in the guest house. Foam insulation was being sprayed in the foyer, great room and porch exterior. A header was installed about the master shower wall. Hunter plumbing was onsite to install all tub drain kits. Mechanical cut and heading off was completed in the powder room below the 2nd floor studios tub.


Tim Beaulieu entered the following on 19:58:06 May/03/2009:
Weather Conditions:Sunny and Clear high in the mid 90's
Date
:
May 1, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Jeff Collins, Steve Stone, Danny Tracy, Dan Burke, Rolando Nunez, Greg Barber
Subcontractors on site: AGA-1, JTS Construction-1, CCS-5
Visitors: Phil N. From the Beaufort County Building Codes Department.
Equipment Used: The foam trailer was on site and used for 4 hours to spray foam in the attic and 2nd floor mechanical room and guest bedroom. The man lift, fork lift, and artic heater was on site but not used. 20 Bunks of scaffoldng was used for 3 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Mechanical inspection was passed today by the Beaufort County building department. Sheet rock was ordered and the house will be stock on Wednesday. Foam insulation was being completed in the attic and second floor. HVAC duct work was being completed in the main house. The front and side porch ceiling was laid and and installation started. Fire stop and draft stop was being completed in the main house mechanical chase. Low voltage wiring was being installed in the great room. Can lights were installed in the gallery. the porch beam was completed. Electrical panel rough in work was being completed in the garage.


Tim Beaulieu Cuda C entered the following on 19:37:55 May/03/2009:
Weather Conditions:Sunny and Clear High in the mid 80's
Date
:
April 30, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Jeff Collins, Steve Stone, Dan Burke, Todd Bowers, Ed E.
Subcontractors on site: AGA-1, JTS Construction-1, CCS-5, Cuda Company-4
Visitors: No visitors today
Equipment Used: The man lift, fork lift, artic heater, foam trailer were on site but not used. 20 Bunks of scaffolding were used for 9 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Fire stop and draft stop work was being completed in the main house and garage. Electrical rough in work was being completed in the garage. The main house siding was being painted. A drop ceiling was being installed in the main house 2nd floor guest bedroom. HVAC duct work was being installed to below the main house stairs from the attic.


Tim Beaulieu entered the following on 20:29:03 Apr/30/2009:
Weather Conditions:Sunny and Clear, High in the mid 80's
Date
:
April 29, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolondo Nunez, Jeff Collins, Steve Stone, Duane Constantino
Subcontractors on site: AGA-1, CCS-3, Cuda Company-4
Visitors: The Home owners were on site to review main house staircase. Russel Love was on site to review staircase
Equipment Used: The man lift, fork lift, artic heater, and foam trailer were on site but not used. 18 bunks of scaffolding was used for 6 hours to installed exterior trim on the side porch of the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The I-line panel was being assembled for the garage service yard. Low voltage AV wiring was being installed in the panel under the main house staircase. Exterior trim was installed on the rear porch. Fire stop was being completed in the master bedroom closets. Exterior siding was being painted on the main house. Recessed can lights were being installed in the 2nd floor guest bedroom and the apartment. Stairway fabrication was being completed in the garage. A walk thru with Ed and Duane was conducted to review remaining mechanical rough in work. David was on site with Russell Love to review the stair case and lay out. David has requested that Russell propose a price for the frame work of staircase.


Tim Beaulieu entered the following on 07:13:55 Apr/29/2009:
Weather Conditions:Sunny and clear high in the low 80's
Date
:
April 28, 2009
Employees Working on site: Tim Beaulieu, Greb Barber, Gerson Morales, Nicholas Royas, Rolando Nunez, Jeff Collins
Subcontractors on site: AGA-1, JTS Construction-1, CCS-3, Cuda Company-4
Visitors: David Sneddon was on site to review progress. David Schepp (safety management Consultant with Selctive Insurance was on site to view job job site and working conditions.
Equipment Used: The fork lift, man lift, foam trailer, artic heater were on site but not used. 12 Bunks of scaffolding was on site and used 8 hours to install exterior trim.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Possible add sub panel in garage depending on current generator loads.
Work Completed or Work in Progress notes: Ectrical rough in work was bein completed in the garage. The I-Line panel was recieve and was being laid out. AV wiring in the main house was being terminated in the panel locations under the stairs. Paint was being sprayed on the main house siding. Windows were being prepared for paint. A walk thru with Ed was completed to review mechanical inspection items. Exterior trim was installed on the side porch beams. Fire stop was being installed in the 2nd floor guest bedroom. The garage staircase framing was being completed. Siding was being installed on the garage below the door heights to allow room for covered walkway framing.


Tim Beaulieu entered the following on 07:09:48 Apr/28/2009:
Weather Conditions:Sunny and clear, High in the low 80's
Date
:
April 27, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Jeff Collins, Steve Stone, Rolando Nunez, Danny Tracy
Subcontractors on site: CCS-4, JTS Construction-1, AGA-1, Cuda Company-4
Visitors: No visitors today
Equipment Used: The man lift, fork lift, artic heater, and foam trailer were on site but not used. 20 Bunks of scaffolding was used the entire day to install siding and exterior trim.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known change to report at this time.
Work Completed or Work in Progress notes: The front porch box beam was completed. Exterior siding was being Exterior siding was completed on the main house. The electrical panel was installed in the garage. Electrical circuits were being installed in the garage apartment. HVAC duct work was laid out to the main house stair closet to the attic. Mechanical cutting and heading off was completed in the first floor studio. The limestone sample was recieve and cleaned for the Sneddons review. HVAC duct work was completed in the second floor guest bedroom. Windows were being protected and insulated. The main house was being cleaned and organized. Low voltage wiring was being installed in the foyer.


Tim Beaulieu entered the following on 07:31:35 Apr/27/2009:
Weather Conditions:Sunny and Clear high in the low 80's
Date
:
April 24, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Steve Stone, Jeff Collins, Danny Tracy, Greg Barber
Subcontractors on site: CCS-4, JTS Construction-1, AGA-1
Visitors: No visitors today
Equipment Used: The back hoe was transported to 12 Marshland today. The Fork lift, man lift, artic heater, and foam trailer were on site but not used. 40 bunks of scaffolding was used the entire day to install exterior siding and trim on the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Closet below garage staircase.
Work Completed or Work in Progress notes: Exterior siding and trim was installed on the master bedroom exterior gable wall. Low voltage wiring was installed from the main house to the garage. Receptacles and switch boxes were being taped off in the garage and bonus rooms. Copper flashing was installed on the column capitals. Fire stop was completed in the main house. Can lights were being installed in the 2nd floor main house guest bedroom. The garage stair case was laid out and fabrication started. The Sneddons would like to add a closet below the stair as in Oldfield. This will be a change order.


Tim Beaulieu entered the following on 20:38:46 Apr/23/2009:
Weather Conditions:Sunny and clear, high in the low 80's
Date
:
April 23, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Danny Tracy, Jeff Collins, Steve Stone, Greg Barber
Subcontractors on site: AGA-1, JTS Construction-1, CCS-2, Hilton Head Security-1, Hunter Plumbing-2, Cuda Company-4
Visitors: No visitors today
Equipment Used: The man lift, back hoe, fork lift, artic heater, and foam trailer were on site but not used. 20 bunks of scaffolding were used for 9 hours to install exterior siding and front porch exterior trim.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: We need to have the rear porch column modification finalized as soon as possible.
Work Completed or Work in Progress notes: The front porch box beam framing and pack out was completed. Attic fire stop work around ERV dampeners was finished. Lutron panel rough in work was completed. 2nd floor Cable and phone panel wiring is now completed. Rock wall was installed around all IC cans in the 2nd floor main house. Rough in plumbing work was complete. Plumbing supply and waste line water tests are underway. All DWV pipes have been filled with water. Exterior siding was installed on the master bedrooms wall. The 2nd floor guest bedrooms mechanical pick up framing was complete. Low voltage wiring pulls, from the guest house to the main house were completed. Fire and Security rough in work was completed. The garage stair framing was reviewed and construction started. Copper flashing caps were being installed on the porch columns. Garage exterior trim repaint was underway. Rafter tails and fascia were being sprayed. The cooks tops exterior vent trim work was completed. The Oldfield residence was visited today to review and field measure AV equipment, main house and guest house stair cases.


Tim Beaulieu entered the following on 20:00:34 Apr/22/2009:
Weather Conditions:Sunny and Clear, high in the low 80's
Date
:
April 22, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Jeff Collins, Steve Stone
Subcontractors on site: CCS-4, JTS Construction-1, AGA-1, Cuda Company-4
Visitors: No visitors today
Equipment Used: The man lift was used for 4 hours to install the front porch beam pack out. The back hoe, fork lift, artic heater, and foam trailer were on site but not on site. 8 Bunks of scafolding was used for 9 hours to install exterior and trim.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: I visited the Oldfield home this morning to review lighting and take field measurement. The Sneddons state that the gallery lights would be the same as they are in Oldfield. All interior scones heights were measured. All interior scones will be set at 8' 6" off the finish floor. David stated that he would like to have the staircase priced out through other sources. All exterior sconces will be 73" off finished surfaces.
Work Completed or Work in Progress notes: Electrical circuits were installed in the second floor mechanical room. Lutron smart switch boxes were being made up. Can lights were being installed in the 2nd floor guest bedroom bathroom. Exterior siding was installed on the master bedroom of the main house. The front porch beam was being packed out and nearing completion. Firestop was being completed in the 2nd floor mechanical chase. Low voltage wiring was installed in the 2nd floor mechanical panels. Paint was being applied to the main houses soffits and window trims. Fire stop was being completed around all attic dampeners.


Tim Beaulieu entered the following on 20:34:29 Apr/21/2009:
Weather Conditions:Sunny and Clear high of 81 degrees
Date
:
April 21, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Danny Tracy, Jeff Collins, Steve Stone
Subcontractors on site: AGA-1, JTS Construction-1, CCS-2, HHS-1, Cuda Company-4
Visitors: The home owners were on site today to view progress. David stated that he did not want the lutron shades in the first floor studio. David stated that they would not have the cameras and DVR installed. David also mention that he would like to have the staircase priced out through a few other companies.
Equipment Used: The fork lift, back hoe, artic heater, and foam trailer were on site but not used. 12 Bunks of scaffolding was used for 3 hours to install exterior trim. The man lift was on site and used for two hours to install exterior trim on the front porch.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Electircal circuits were being installed in the main house service yard. Attic framing was being completed around HVAC dampeners. Low voltage wiring was pulled between the main house and garage. Fire stop was being installed in the 2nd floor mechanical chase. Pick up framing was being completed in the second floor studio closet. Fire caulking was being completed through out the main house and garage. Nail plate installation was completed in the main house. Cuda company begin the change order exterior paint recoat on the main house.


Tim Beaulieu entered the following on 20:45:46 Apr/20/2009:
Weather Conditions:Heavy afternoon showers, High in the low 70's
Date
:
April 20, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Jeff Collins, Steve Stone
Subcontractors on site: JTS Constrcution-1, AGA-1, CCS-2, Cuda Company-3
Visitors: No visitors today
Equipment Used: The man lift, fork lift, foam trailer, back hoe, artic heater were on site but not used. 14 bunks of scaffolding was used for 9 hours. The back hoe was prepared to return to Hilton Head. All fluids were topped off and the fittings greased.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The side porch beam was being packed out and prepared for exterior trim. The front porch columns had captial flashings completed. Electrical wiring was being completed on all porch recepticals. Siding was being installed around the master baths tub bay. AV wiring was being completed on the first floor of the main house. Can lights were being installed in the 2nd floor guest bedroom.


Tim Beaulieu entered the following on 18:30:30 Apr/19/2009:
Weather Conditions:Sunny and Clear, High in the low 70's
Date
:
April 17, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Steve Stone, Jeff Collins
Subcontractors on site: AGA-1. JTS Construction-1, CCS-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used. 6 bunks of scaffolding was used for 4 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Flashing was being installed on the front and side porch columns. The rear and side porch beam was being packed out and prepared for siding. Electrical rough in work was being completed in the garage and bonus rooms. Siding was being installed on the exterior of the master bedroom. Low voltage wiring was being installed through out the main house.


Tim Beaulieu entered the following on 18:30:26 Apr/19/2009:
Weather Conditions:Sunny and Clear, High in the low 70's
Date
:
April 17, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Steve Stone, Jeff Collins
Subcontractors on site: AGA-1. JTS Construction-1, CCS-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used. 6 bunks of scaffolding was used for 4 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Flashing was being installed on the front and side porch columns. The rear and side porch beam was being packed out and prepared for siding. Electrical rough in work was being completed in the garage and bonus rooms. Siding was being installed on the exterior of the master bedroom. Low voltage wiring was being installed through out the main house.


Tim Beaulieu entered the following on 19:49:22 Apr/16/2009:
Weather Conditions:Sunny and Clear, high in the low 70's
Date
:
April 16, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Jeff Collins, Rolando Nunez
Subcontractors on site: CCS-5, JTS Construction-1, AGA-1, Cuda Company-3
Visitors: The home owners were on site today to review paint colors. The Sneddons have selected the formula from Weather Shield for the trim.
Equipment Used: The man lift, back hoe, fork lift, artic heater, and foam trailer were on site but not used. 3 Bunks of scaffolding was used for 8 hours to install siding on the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: All exterior trims color has changed. Cuda Company has submitted a change order for 10,000 dollars. I will discuss with owners in AM and seek approval prior to starting the schedule change. Review of the covered walkway plans was completed. It has been determined at this time that the current drawing will work with minor modification. The proposed beam height of 8’ 9” as seen on the print is not possible. The beam leveled over to the front of the garage at the height would cause conflict with the garage windows. The beam height at the main house should be installed at 8’ 3” to avoid conflict. This will leave 8’9” head room at the front of the garage. A follow up email to Hunter to report findings and discuss minor details has been sent.
Work Completed or Work in Progress notes: The exterior porch beam was being packed out and prepared for exterior trim. Copper flashing was being installed on all exterior columns. Electical rough in work was being installed in the garage and bonus room. HVAC duct work was being completed on the garage ERV. Siding was being installed on the master bedrooms gable wall. Low voltage AV wiring was being installed to the second floor of the main house. Backer rod and NP1 was being applied around all windows and exterior trim. ERV duct termination wall caps were installed on the garage.A complete budgetary cost analysis of the exterior trim labor, interior trim labor, and decking labor was completed today and findings submitted to Nathan.


Tim Beaulieu entered the following on 10:25:21 Apr/16/2009:
Weather Conditions:Sunny and Clear through out the day, High in the upper 60's
Date
:
April 15, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Rolando Nunez, Steve Stone, Jeff Collins
Subcontractors on site: JTS Construction-1, AGA-1, CCS-6, Cuda Company-4
Visitors: The home owners were on site to review paint colors.
Equipment Used: The man lift, fork lift, foam trailer, artic heater, and back hoe were on site but not used. 6 Bunks of scaffolding was used for 6 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The paint color is still undetermined at this point several colors have been sampled. The exact window color formula was obtained from the Weather Shield. The new color will be painted on the upper main house dormer for the home owners review.
Work Completed or Work in Progress notes: Exterior trim was being installed on the master bedrooms exterior. All corner boards and window trim has now been installed. The front and rear porches beam is being packed out and prepared for exterior trim. Electrical rough in work is being completed in the garage and garage apartment. There is approximately 5 day work remaining till rough in inspection. HVAC work was being finished up in the main house. Low voltage wiring was being installed in the main house. 95 percent of all wiring is completed at this time.


Tim Beaulieu entered the following on 16:03:06 Apr/14/2009:
Weather Conditions:Overcast through out the day, light am rains
Date
:
April 14, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Steve Stone, Danny Tracy, Jeff Collins, Rolando Nunez, Nathan Klien, Billy Bowers
Subcontractors on site: RWK Sub-Contracting-1, JTS Construction-1, CCS-6, 2 Brothers Stucco-3, Cuda Company, Hilton Head Security Systems-2
Visitors: The home owners were on site to review paint selections for the exterior trim. David also stated that he would like to remove the square columns on the back porch and replace with 16 inch round fiberglass columns.
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used. 10 Bunks of scaffolding was used the entire day.
Urgent Items and Equipment Needed
:
The home owners would like to change the color of all exterior trim and siding. 50 of the main house and garage have been painted. Bill with Cuda has been notified of the change.
Possible Change Order Items: The rear porch square columns are being switched to round fiberglass columns. A new exterior trim paint color has been selected and the mock up painted.
Work Completed or Work in Progress notes: The dryer duct was installed in the laundry room. The exterior band board on the master bedroom side of the house was being installed. Garage rough in electrical work was being completed on the 2nd floor. HVAC low voltage wiring was being installed in the main house attic. AV wiring was being installed in the master bedroom. Electrical circuits were being installed in the main house great room. Exterior siding was being installed on the front of the main house. Finish stucco work was being complete around the windows and doors on the first floor. The main porch beam was being packed out and prepared for trim. Fire and security rough in wiring was being completed in the garage apartment. The exterior trim was being sanded and prepared for paint. Caulking and backer rod was being installed around all 2nd floor windows. The erv wall penetrations were completed in the garage.


Tim Beaulieu entered the following on 08:26:02 Apr/14/2009:
Weather Conditions:Overcast through out the day, Heavy PM rains
Date
:
April 13, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas, Rolando Nunez, Gerson Morales, Steve Stone, Danny Tracy
Subcontractors on site: JTS Construction-1, AGA-1, RWK Sub-Contracting-1, CCS-2, Cuda Company-4
Visitors: The owners were on site to review AV keypad locations.
Equipment Used: The man lift, fork lift, back hoe, foam trailer, and artic heater were on site but not used. 6 bunk of scaffolding was used for 8 hours.
Urgent Items and Equipment Needed
:
The Sneddon are unhappy with the paint color they have selected. I have stop all paint work until a new color has been selected and approved by the PB review board.
Possible Change Order Items: The rear porch columns David would like a price to remove 2 columns and replace all remaining square columns with 16 inch fiberglass columns.
Work Completed or Work in Progress notes: The front porch beam was being packed out and prepared for trim. The exterior band board was being installed on the master bedroom side of the house. AV wiring was being installed through out the main house. The ironing boards rough framing was completed in the laundry room. Joist hangers were being installed on the rear porch. Siding was being installed on the main house. Painting was being completed on all main house dormers. HVAC duct work was being installed in the guest house. All HVAC low voltage wiring was installed in the main house. Can lights were being wired and installed on the rear porch.


Tim Beaulieu entered the following on 07:36:48 Apr/14/2009:
Weather Conditions:Sunny and Clear High in the mid 70's
Date
:
April 10, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas
Subcontractors on site: CCS-3, AGA-1
Visitors: No visitors today
Equipment Used: The manlift, forklift, back hoe, artic heater, and foam trailer were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Exterior siding and trim were installed on the front porch of the main house. HVAC Duct work was installed in the guest house. The porch beam was being packed out and prepared for trim. AV wiring was being installed through out the main house. All electrical wires were being installed in all panels in the 2nd floor mechanical room.


Tim Beaulieu entered the following on 19:43:25 Apr/09/2009:
Weather Conditions:Sunny and Clear, High of 80 degrees
Date
:
April 09, 2009
Employees Working on site: Tim Beaulieu, Jeff Collins
Subcontractors on site: CCS-4, AGA-1, Cuda Company-4
Visitors: No visitors today
Equipment Used: The manlift was on site and used for 2 hours to install exterior trim on the front porch. The fork lift, back hoe, foam trailer, artic heater were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: AV wires were being installed through out the main house. Electrical panels were being made up in the mechanical room. HVAC duct work was installed in the main house attic. The front porch beam was being packed out for the exterior trim detail. Siding was being installed on the front of the main house. All upper window on the roof section were being prepared for paint. Once the paint process is completed the main house roof will be ready for installation.


Tim Beaulieu entered the following on 07:34:33 Apr/09/2009:
Weather Conditions:Sunny and clear high of 74
Date
:
April 08, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor Trejas, Steve Stone, Danny Tracy, Jeff Collins
Subcontractors on site: AGA-1, RWK Sub Contracting-1, CCS-2
Visitors: No visitors today
Equipment Used: The manlift was on site and used for 1 hour to install exterior trim. The fork lift was on site and used for 30 minutes to unload framing material. The back hoe, Artic heater, and foam trailer were on site but not used. 12 bunks of scaffolding was used the entire day to install felt and siding.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Speaker wire was being installed to the rear porch. Exterior siding and trim was being installed on the front and rear porch. HVAC duct work was installed in the garage apartment. The lower band was being installed around the main house.


Tim Beaulieu entered the following on 07:16:19 Apr/08/2009:
Weather Conditions:Sunny and Clear, High in the low 60's
Date
:
April 7, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor Trejo, Steve Stone, Jeff Collins, Danny Tracy
Subcontractors on site: CCS-2, AGA-1, RWK SubContracting-1, 2 Brothers Stucco-2,
Visitors: No visitors today
Equipment Used: The manlift, forklift, backhoe, artic heater, foam trailer were on site but not used. 6 Bunks of scaffolding were used the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Ipe door sill and trim were being installed on the rear porch. The lower band on the front porch was being installed. The front porch beam was bein packed out and prepared for trim. DVA and HVAC wires were being installed through out the main house. Stucco was being finished on the second floor of the main house. Light boxes were installed on the in foyer and great room. Can lights were being installed in the 2nd floor guest bedroom.


Tim Beaulieu entered the following on 20:20:00 Apr/06/2009:
Weather Conditions:AM rains clear to PM sun
Date
:
April 06, 2009
Employees Working on site: Tim Beaulieu, Jeff Collins, Steve Stone, Gerson Morales, Nicholas Royas, Pastor T, Danny Tracy
Subcontractors on site: CCS-4, AGA-1, RWK Sub Contracting-1, 2 Brothers Stucco
Visitors: Capital Material for sheet rock take off
Equipment Used: The man lift, back hoe, fork lift, artic heater, foam trailer were on site but not used. 6 bunks of scaffolding wrere used for 3 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Exterior siding and trim were installed on the front porch. The lower band was being installed around the master bedroom. Sills for all doors were being fabricated and installed. HVAC duct work was being installed in the guest house. The DVA duct were completed today. Electrical panels were being completed in the second floor mechanical room. Ceiling light boxes were installed in the great room and foyer. Can lights were being installed in the 2nd floor guest bedroom. Stucco work was being completed on the 2nd floor exterior.


Tim Beaulieu entered the following on 08:47:56 Apr/06/2009:
Weather Conditions:AM rain, Sunny and clear in PM
Date
:
April 03, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T
Subcontractors on site: AGA-1, 2 Brother Stucco-2, RWK Sub Contracting-1
Visitors: No visitors today
Equipment Used: The back hoe was on site and used for 2 hours to work on rough grading. The man lift, fork lift, artic heater, and foam trailer were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Add pool equipment to generator panel.
Work Completed or Work in Progress notes: Exterior siding and trim was installed on the front of the main house. HVAC duct work was install in the guest house. Felt was install on the north gable wall. Finsh coat of stucco was applied to the lower half of the main house. The entire job site was cleaned and organized.


Tim Beaulieu entered the following on 06:26:08 Apr/03/2009:
Weather Conditions:Heavy rains and gusting winds through out the day, High in the low 70's
Date
:
April 02, 2009
Employees Working on site: Tim Beaulieu, Gerson Morals, Nicholas Royas, Pastor T
Subcontractors on site: RWK Sub Contracting-1, AGA-1, Hilton Head Securty Systems-3, 2 Brother Stucco-2, MMC-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, artic heater, and foam trailer were on site but not used. The back hoe was used for 1 hour to grade and drainage work.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was installed in the guest house. Siding was being installed on the fron of the main house. Stucco work was completed on the entire first floor. Ipe sills were being fabricated for all exterior doors. Matt from MMC was on site to review the front door details. Hilton Head Securtiy Systems was working the fire and burgalar alarm.


Tim Beaulieu entered the following on 06:34:18 Apr/02/2009:
Weather Conditions:Heavy rains through out the day, high in the upper 60's
Date
:
April 01, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T.
Subcontractors on site: RWK Sub Contracting-1, AGA-1, Hilton Head Security-4, Big Horn-2, SCE&G-2, 2 Brother Stucco-2, CCS-3
Visitors: No visitors today
Equipment Used: The backhoe, foam trailer, artic heater, and manlift were on site but not used. The fork lift was onsite and used for 1 hour to move siding material.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was being installed in the guest house. Siding was being installed on the front porch. Can lights were being installed on the rear porch. Electrical and light boxes were being installed on the rear porch at the master bedroom. Stucco mud work was being completed on the exterior 1st floor walls.


Tim Beaulieu entered the following on 07:21:40 Apr/01/2009:
Weather Conditions:Sunny, Overcast in PM
Date
:
March 31, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nichols Royas, Pastor T
Subcontractors on site: AGA-1, RWK Sub Contracting-1, CCS-2, Grist Equipment-1
Visitors: The Sneddons were on site to review AV and Alarm proposals.
Equipment Used: The forklift joystick was replaced today. The back hoe, man lift, foam trailer, and artic heater were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The Sneddons would like to had Lutron shades to the four windows in the 1st floor studio.
Work Completed or Work in Progress notes: Exterior trim was being installed on the front porch. HVAC duct work was installed in the guest house. HVAC vents were being painted in the main house. Siding was being installed on the side porch.


Tim Beaulieu entered the following on 07:28:52 Mar/31/2009:
Weather Conditions:Sunny
Date
:
March 25-30, 2009
Employees Working on site: Gerson Morales, Nicholas Royas, Pastor T.
Subcontractors on site: RWK Sub Contracting-1, AGA-1, CCS-2, 2 Brother Stucco-3
Visitors: No visitors today
Equipment Used: The back hoe, man lift, artic heater, and foam trailer were on site but not used. The fork lift was on site and used for 5 hours. 6 Bunks of scaffolding were used for 24 hours during this period to install siding onn the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No know changes to report at this time.
Work Completed or Work in Progress notes: Siding was being installed on the main house 1st floor studio exterior. Dormer siding was being installed on the rear porch. Stucco mud work was being completed on the main house. HVAC duct work was installed in the guest house. The entire main house was cleaned and the slab prepared for vapor barrier and concrete sealer.


Tim Beaulieu entered the following on 10:19:35 Mar/25/2009:
Weather Conditions:Sunny and Clear, High in low 70's
Date
:
March 24, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Ed E
Subcontractors on site: AGA-1, RWK Sub-Contracting-1, CCS-1, 2 Brothers Stucco, Hilton Head Securty Systems-1
Visitors: The owners were on site to review progress.
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used. 3 bunks of scaffolding were used the entire day
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Exterior trim and siding was installed on the main house rear dormers. The entire first floor of the main house was cleaned and prepared for concrete sealer. Corner bead and metal lath was being installed on the main house. Can lights were installed on the front and side porch. HVAC duct work was completed in the main house. A walk thru was completed with Hilton Head Security Systems to review alarm system. Work on the alarm system will begin next week.


Tim Beaulieu entered the following on 13:12:21 Mar/24/2009:
Weather Conditions:Sunny and Clear, High in the low 70's
Date
:
March 23, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas
Subcontractors on site: RWK Sub-Contracting-1, AGA-1, CCS-2
Visitors: No visitors today
Equipment Used: The man lift, back hoe, fork lift, artic heater, foam trailer were on site but not used. All scaffolding was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was installed in the master bedroom, laundry room, water closet, and master bathroom. Siding was installed on the main house dormers. Sand was delivered for stucco work. Mechanical cut and heading off was completed in the garage apartment for hvac duct work.


Tim Beaulieu entered the following on 13:06:30 Mar/23/2009:
Weather Conditions:Sunny and clear
Date
:
March 20, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T.
Subcontractors on site: 2 Brothers Stucco-3, AGA-1, CCS-3, RWK Sub Contracting-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used. All scaffolding was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Nathan has report the double sink in the 2nd floor guest bedroom is now going to be a single sink centered in the vanity. Stuart has provided drawings.
Work Completed or Work in Progress notes: HVAC duct work was installed in the master bedroom and 2nd floor guest bedroom. Can lights were installed in the 2nd floor study. Low voltage wiring was installed to the gas light tranformer location. Exterior siding and trim was installed on the rear gables dormers. Lath was installed on the main house.


Tim Beaulieu entered the following on 10:08:28 Mar/20/2009:
Weather Conditions:Sunny and Clear, High in the upper 70's
Date
:
March 19, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T.
Subcontractors on site: RWK Sub Contracting-1, AGA-1, CCS-2, 2 Brothers Stucco-3
Visitors: No visitors on site today.
Equipment Used: The man lift, back hoe, fork lift, artic heater, and foam trailer were on site but not used. 3 Bunks of scaffolding were used for 2 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The track lights in the front hall will be can lights.
Work Completed or Work in Progress notes: HVAC duct work was installed in the master bedroom and 2nd floor guest bedroom. Can lights were installed in the great room and 2nd floor study. Exterior trim and siding was installed on the main house dormers. Lath was being installed on the exterior of the 2nd floors main gable. Cable and phones were installed to the great room. The rear gas lights low voltage wiring was installed.


Tim Beaulieu entered the following on 15:13:22 Mar/18/2009:
Weather Conditions:Sunny and Clear, Mid 70's
Date
:
March 18, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T.
Subcontractors on site: RWK Sub Contracting-1, AGA-1, 2 Brothers Stucco-3, CCS-3, MMC-1
Visitors: Waste Pro, Grist Equipment
Equipment Used: The man lift, back hoe, fork lift, artic heater, and foam trailer were on site but not used. The fork lift radiator was repaired and installed. All scaffolding was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No know changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was completed in the 2nd floor guest bedroom. Door bell wiring was installed. All low voltage gas light wiring was installed. 2 electrical circuits were installed to the main house service yard. Exterior trim and siding was being installed on the main house. Metal lath was being installed around exterior portion of the first floor on the main house.


Tim Beaulieu entered the following on 15:01:19 Mar/17/2009:
Weather Conditions:Sunny and Clear High in the low 70's
Date
:
March 17, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T.
Subcontractors on site: AGA-1, RWK Sub Contracting-1, 2 Brother Stucco-3, CCS-3, PGP&A-1, OEM Roofing-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used. All Scaffolding was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Metal lath was being installed on the proch walls. Felt paper was installed on the gable wall of the main house. HVAC duct work was being installed in the master bedroom. Gas lines were installed to all gas lantern locations. Exterior tirm was installed in on the upper roof for stucco termination. Gas lantern blocking was installed on the rear porch. Starting and stopping points were established around the front door and straight edges installed. Copper flashing was beiing installed around the front porch between the deck and porh walls. Eletrical boxes were being wired through out the main house.


Tim Beaulieu entered the following on 13:25:00 Mar/17/2009:
Memo:
Site Meeting Minutes Via Nathan

All,

We have meeting on the site today to verify some mechanical 
requirement for coding and to verify scope of work and 
pricing:

 

Audio System:

The Sneddon described a very simple system with rooms pre-
wired by not devised out. Joe with CCS with provide a 
proposal based on the discussions. 
 

Generator:

Gary and Ed with CCS described and reviewed the generator 
panel schedule with the Sneddons. There was a concern that 
the current loads would require two panels. After reviewing 
the panel schedule and their current needs, it was 
determined that having air conditioning in the main living 
room was not needed in an emergency situation. By removing 
this very substantial load, they now can have most every 
need satisfied. Air conditioning for the master suite, 1st 
floor general lighting, all refrigeration and freezer 
needs, Lutron power and dedicated outlets for TV, computer 
and other communication devices. 
Ed with CCS will provide a proposal from a Cummings Dealer. 
CCS prefers their better service record after the sale. 
David agreed that the service was important and that he was 
unhappy with his current company. 
 

Location of Pool control panel

The Jandi Pool Control panel was located on the exterior 
wall of the master bedroom between the two French doors. 
The panel will be mounted above the Lutron Keypad. Tim 
confirmed that a conduit could be installed. 
 

Location of the Gas Lanterns

The 2 gas lanterns on the front of the house will be on 
either side of the front door, mounted on the pilasters and 
between the third and fourth hinge vertically. 
On the back of the house, 4 lanterns will be centered 
between the exterior doors and between the third and fourth 
hinge vertically. 
A seventh lantern will be mounted between the two french 
doors into the master suite and between the third and 
fourth hinge vertically. 
 

The meeting broke and we are now awaiting two proposals 
from CCS.


Tim Beaulieu entered the following on 13:23:30 Mar/17/2009:
Weather Conditions:Heavy Rains in PM, High in the upper 60's
Date
:
March 16, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T, Nathan Klien, Ed E
Subcontractors on site: CCS-6, 2B Stucco-2, AGA-1, RWK Sub Contracting-1
Visitors: The home owners were on site today to review AV, Security, and HVAC.
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used. 5 Bunks of scaffolding was used for 2 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was installed in the guest bedroom and master bedroom. Phone and cable wiring was installed through out the main house. Metal lath was delivered for stucco work. Exterior receptical blocking was installed. A site meeting with the owners and CCS was conducted. Notes to follow.


Tim Beaulieu entered the following on 17:36:20 Mar/14/2009:
Weather Conditions:Overcast, high in the low 60's
Date
:
March 14, 2009
Employees Working on site: Tim Beaulieu
Subcontractors on site: CCS-4, AGA-1
Visitors: The owners were on site to review progress
Equipment Used: The man lift, fork lift, artic heater, foam trailer were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The owners are considering wainscoating in the foyer and master hall. David stated that they did not want to have the skylights installed.
Work Completed or Work in Progress notes: Lutron, phone and cable wiring were installed through out the main house. The low voltage wiring is 90 percent completed at this time. HVAC duct work was being installed in the master bedroom and the 2nd floor guest bedroom. Siding was being installed on the front dormer of the main house.


Tim Beaulieu entered the following on 17:43:03 Mar/13/2009:
Memo:
Notes from Nathans Meeting with the Sneddons.

Nathan sent 

I just finished a very productive meeting with Sneddon’s. 
Here are the decisions made, items confirmed and meetings 
set:

 

Items needed to close up the walls

Appliances, washer and dryer selection. Nathan is to call 
Camilla @ Livingoods for the model number and spec sheet. 
Lighting Fixtures, confirm Becky’s selection Meeting is 
scheduled for Wednesday 3/19 at 2 pm(at the Sneddon’s 
current home) to verify that the specified light fixtures 
match what is in their home now. 
Gas Lanterns, Confirm the actual fixture. Gas Lanterns will 
be verified with the electrical fixtures. 
Generator load and specification. Meeting set for Monday 
3/16 2 pm at the jobsite to Verify Generator, Audio Visual 
and Security. 
Audio Visual specifications and scope of work. Meeting set 
for Monday 3/16 2 pm at the jobsite to Verify Generator, 
Audio Visual and Security. 
Security system specifications and scope of work. Meeting 
set for Monday 3/16 2 pm at the jobsite to Verify 
Generator, Audio Visual and Security. 
Gas Log selection needed. Sneddon’s to make selection at 
Grill in on Argent Road. 
Jandi pool control panel location. To be verified on site 
during 3/16 meeting on site. 
Confirm Electrical Device style and color. All device 
plates are to be painted by faux finisher, Joey Dulin. 
Please order Snow White, by Lutron.. 
 

Items needed to for exterior siding and trim

Covered Walkway framing and detailing. The covered 
connector is to be built as currently shown on the drawings 
with the exception of the round tapered columns.  They 
would like the ceiling to match the porch in style and 
color with the same can lights. These lights are to be 
controlled by Lutron. Layout of lights can be verified in 
the field. 
 

Items needed to smoothly transition into interior trim

Wood Flooring, selection and confirmation of materials. 
Southern Yellow Pine No.1, 12” wide, clear finish. 
Countertops selections confirmed (Green Onyx & Rain Forest 
Green) Light Green Onyx slabs have been reserved @ DGM. 
Rain Forest Green has been changed to Calcutta Gold. An 
onyx slab will be confirmed once we have a template of the 
master bath vanity. 
Tile and Grout selections confirmed, depending on Rain 
Forest Change. Jenny with Stoneworks will revise the 
selections and verify the grouts with Dorothy. 
Paint Schedules and finishes confirmed. Dorothy and David 
are working on this. Nathan is to provide a blank schedule 
format for them to fill in. 
Closet Shelving Design, lay out and material confirmations. 
To be reviewed in the field after sheetrock is installed. 
The Sneddon’s would like to work with Tim to build shelves 
and rods with pre-finished materials. The master closets 
may require revisions and adjustments to Stuarts existing 
drawings. 
Mirror style and method of attachment confirmed. All 
mirrors will be hung/furniture. Tim has already coordinated 
blocking with the Sneddon’s. 
Interior handrail design and layout confirmed. Russell Love 
is preparing a single panel for the Sneddon’s review and 
will field measure at the same time. 
 

Items needed to complete the project and determine cost 
sand scheduling

Door Hardware, I have alternate options on the exterior 
hardware. All door hardware is to remain the same, except 
the weather shield exterior doors will have different 
hardware. They have chosen a 2 x10 Tuscany Plate with a 
Medici lever in oil rubbed bronze. Tanner from Bird 
Hardware has the specs. 
Cabinet Hardware, Confirm selection and counts. The 
Sneddon’s will be looking at these in the near future. 
Bath Accessories, Selection and confirmation. The Sneddon’s 
will be looking at these in the near future. 
Mirrors, selected and purchased. The Sneddon’s will be 
looking at these in the near future. 
Exterior handrail design and layout confirmed. Russell Love 
is preparing a single panel for the Sneddon’s review and 
will field measure at the same time. 
 

Other Notables(to borrow from Jamie):

·        David would like to discuss the cabinetry with 
Stuart or Jamie during or after the 3/16 meeting, on-site.

·        The possibility of skylights or additional 
lighting in the great room has been removed from the table. 
We are to progress as before and no longer consider these 
options.


Tim Beaulieu entered the following on 17:37:27 Mar/13/2009:
Weather Conditions:Sunny and Clear, high in the mid 60's
Date
:
March 13, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nichoas Royas, Pastor T
Subcontractors on site: AGA-1, RWK Sub Contracting-1, CCS-6
Visitors: David was on site to review progress.
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David would like to move one of the floor outlet in the great room. I discussed with David and told him that it could be done without cutting up the concrete and the wiring could be completed below the floors sleeper system.
Work Completed or Work in Progress notes: Electrical circuits were installed on the rear porch. Lutron wires were being installed on the 2nd floor. Phone lines were installed to the master bedroom. HVAC duct work was being completed in the master bedroom and 2nd floor guest bedroom. Siding was being installed on the main house dormers. Can lights were being installed in the great room. The job site was cleaned and organized.


Tim Beaulieu entered the following on 17:31:52 Mar/13/2009:
Weather Conditions:Sunny and Clear, High in the mid 70'
Date
:
March 12, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholes Royas, Pastor T
Subcontractors on site: AGA-1, RWK Sub Contracting-1, CCS-5
Visitors: No visitors today
Equipment Used: The backhoe, forklift, manlift, artic heater, and faom trailer were on site but not used. Six bunks of scaffolding were used for 8 hours
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Add trey ceiling to to master closets
Work Completed or Work in Progress notes: Closet ceiling framing was completed. Lutron keypad and smart switch cable was completed on the first floor. HVAC duct work was installed in the second floor bedroom and 1st floor powder room. Electrical circuits were being installed on the rear porch. Crown freeze board was installed around the entire front porch.


Tim Beaulieu entered the following on 15:01:10 Mar/11/2009:
Weather Conditions:Sunny and clear, High in the low 80's
Date
:
March 11, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T, Nicholas Royas
Subcontractors on site: CCS-4, AGA-1, RWK Sub Contracting-1, Grist Equipment-1, Big Horn-4
Visitors: David was on site to review progress
Equipment Used: The man lift, back hoe, artic heater, foam trailer were on site but not used. The fork lift was being repaired by Grist Equipment. The radiator has been pulled. Grist Equipment is checking to see if the radiator can be repaired.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Trey ceilings will be installed in the master bedroom closets rather than just a standard drop ceiling.
Work Completed or Work in Progress notes: Fresh air intakes were installed to include trim and wall caps. The ceiling was installed in Davids master closet. Mechanical cut and heading was completed in the great room and second floor hall. The ceiling was dropped 5 1/2 inches in the 2nd floor hall to allow duct work to pass through the area. Siding was being installed on the main house dormers. The great room mantel was installed and is completed. HVAC duct work was being installed in the master bedroom and the 2nd floor guest bedroom.


Tim Beaulieu entered the following on 14:42:46 Mar/10/2009:
Weather Conditions:Sunny and clear, High in the upper 70's
Date
:
March 10, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T.
Subcontractors on site: AGA-1, RWK Sub Contracting-1, PGP&A-2, CCS-5
Visitors: No visitors today
Equipment Used: The artic heater, man lift, foam trailer, back hoe, and fork lift were on site but not used. All equipment was greased and fluids check. The fork lift has a radiator leak. Matt of MMC has been notified.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was installed in the attic and 2nd floor guest bedroom. Nail plates were being installed through out the main house. Fire caulking was being applied in all main house top plate penetrations. Siding was being installed on the main gables dormers. Drop ceilings were being constructed in the master bedroom closets. Gas lines were installed to the great room fireplace and the kitchens cook top. Becky from the Light Post was contacted regarding the rear porches gas lanterns layout. Becky stated she was meeting with the Sneddons on Wednesday and would discuss locations and amounts. MMC was contacted regarding the front door fabrication. The propsal was signed and fabrication is underway.


Tim Beaulieu entered the following on 06:28:46 Mar/10/2009:
Weather Conditions:Sunny and Clear, low 80's
Date
:
March 09, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T, Nicholas Royas
Subcontractors on site: RWK Sub Contracting-1, AGA-1, PGNPA-2, CCS-4, 2b Stucco-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used. 8 Bunks of scaffolding was used for 3 hours
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The mantel was delivered and checked for damage, no damage noted. The framing for the second floor safe was completed. HVAC duct work was installed in the foyer and attic. Fresh air intakes were installed in the attic. Gas lines were run from the service yard to the kitchen. Drop ceilings were completed in the master bedroom closets.


Tim Beaulieu entered the following on 08:14:53 Mar/09/2009:
Weather Conditions:Sunny and Clear high in the low 70's
Date
:
March 06, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T.
Subcontractors on site: RWK Sub Contracting-1, AGA-1, CCS-5
Visitors: No visitors today
Equipment Used: The back hoe, man lift, fork lift, artic heater, and foam trailer were on site but not used. 4 bunks of scaffolding were used for 5 hours to install HVAC duct work in the great room.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Add cedar closet to mechanical room on 2nd floor.
Work Completed or Work in Progress notes: Light fixtures were being installed though out the main house. Siding was being installed on the garage dormers. Fresh air intakes and exhaust were installed in the main house attic. HVAC duct work was installed in the main house great room, 2nd floor study. The safe framing and DVA framing in the mechanical room was completed.


Tim Beaulieu entered the following on 16:50:51 Mar/05/2009:
Weather Conditions:Sunny and clear high in the upper 60's
Date
:
March 05, 2009
Employees Working on site: Tim Beaulieu, Pastor T, Nicholas Royas
Subcontractors on site: CCS-5, RWK Sub Contracting-1, AGA-1
Visitors: No visitors today
Equipment Used: The manlift was on site and used for 5 hours to install siding on the garage. The artic heater was on site and used for 2 hours. The back hoe, fork lift were on site but not used. 6 bunks of scaffolding were used for 5 hours in the great room to install duct work.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Framing for gun safe in 2nd floor mechanical room.
Work Completed or Work in Progress notes: The gun safe framing was installed. Rock wall and fire caulking was installed in the main house attic. Light cans were being installed on the first floor. Siding was being installed on the garage. HVAC duct work was installed in the great room, study and second floor study.


Tim Beaulieu entered the following on 16:31:22 Mar/04/2009:
Weather Conditions:Sunny and Clear, High in the mid 50's
Date
:
March 04, 2009
Employees Working on site: Tim Beaulieu, Nicholas Royas
Subcontractors on site: CCS-5, RWK Sub Contracting-1, AGA-1
Visitors: Bill Upton Builders Risk Managment
Equipment Used: The man lift, back hoe, fork lift, and foam trailer were on site but not used. The artic heater was on site and used for 2 hours. Two bunks of scaffolding were used for 9 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problem to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was installed in the 2nd floor studio and first floor studio. The cedar closet was framed and completed. Can lights were installed in both master bedroom closets. Mech cutting and heading off was completed in the studio to house an HVAC return. Siding was being installed on the front of the garage.


Tim Beaulieu entered the following on 15:39:50 Mar/03/2009:
Weather Conditions:Sunny and Clear high in upper 40's
Date
:
March 03, 2009
Employees Working on site: Tim Beaulieu, Pastor T. Nicholas Royas
Subcontractors on site: CCS-4, RWK Sub Contracting-1, AGA-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, foam trailer, back hoe were on site but not used. The artic heater was on site and used for three hours. 6 Bunks of scaffolding was used for 4 hours to install siding on the garage.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: An ERV will be installed in the mechanical rooms chase. A plateform will be framed along with two walls and a ceiling for sheetrock.
Work Completed or Work in Progress notes: HVAC duct work was installed in the great room attic, 2nd floor study, and 2nd floor guest bathroom. Siding was installed on the single car side of the garage. Knee walls were being framed in the main house attic. Cypress vertical siding was primed and is now completed. Nail plates were being installed on the first floor.


Tim Beaulieu entered the following on 15:59:00 Mar/02/2009:
Weather Conditions:High of 45 Degress, Overcast
Date
:
March 02,2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T
Subcontractors on site: RWK Sub Contracting-1, AGA-1, CCS-3, MMC-2
Visitors: No visitors today
Equipment Used: The man lift, back hoe, artic heater, and foam trailer were on site but not used. The forklift was onsite and used for 1 hour to unload material (IPE) The forklift radiator is leaking Matt of MMC was notified.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was installed in the 2nd floor guest bedroom, 2nd floor study and main house foyer. Knee walls were being constructed in the main house attic. Ice and water shield was installed on the main house dormers. Cypress siding was being primed. Siding was being installed on the garage.


Tim Beaulieu entered the following on 07:47:27 Mar/02/2009:
Weather Conditions:Sunny and Clear, high in the low 70's
Date
:
February 27, 2009
Employees Working on site: Gerson Morals, Nicholas Royas, Pastor T.
Subcontractors on site: CCS-3, AGA-1, RWK Sub Contracting-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, foam trailer, and artic heater were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The man door to the 2 car garage was installed. Siding was completed on the front portion of the garage. Temporary plywood was installed on the decks. HVAC duct work was installed in the guest bedroom and the main house attic.


Tim Beaulieu entered the following on 05:17:15 Feb/27/2009:
Weather Conditions:AM rain, Sunny and Clear in the PM, High in the low 70's
Date
:
February 26, 2009
Employees Working on site: Gerson Morales, Pastor T, Nicholas Poyas
Subcontractors on site: CCS-3, RWK Sub Contracting-1, AGA-1
Visitors: No visitors today
Equipment Used: The back hoe, man lift, fork lift, foam trailer, and artic heater were on site but not used. Three bunks of scaffolding were used the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Siding was being installed on the garage dormers. Electrical boxs for outlets were installed on the second floor and was completed. Temp plywood was being put down on the front deck. HVAC duct work was being installed in the attic.


Tim Beaulieu entered the following on 07:52:24 Feb/26/2009:
Weather Conditions:Sunny and Clear, High in the low 60's
Date
:
February 25, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T., Ed E., Billy Bowers
Subcontractors on site: CCS-4, RWK Sub Contracting-1, AGA-1
Visitors: No visitors today
Equipment Used: The back hoe, man lift, fork lift, artic heater, and foam trailer were on site but not used. 3 Bunks of scaffolding were used for 8 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was being install in the main house attic. Siding was being installed on the garage. Tubs protecting was installed on all tubs. Outlet boxes were being installed on the second floor of the main house. A walk thru with Ed was conducted to review progress. Flashing was being installed on the main house dormers. Vertical cypress siding was delivered.


Tim Beaulieu entered the following on 07:00:13 Feb/25/2009:
Weather Conditions:Sunny and Clear high in the mid 50's
Date
:
February 24, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T. Nicholas Royas, Nathan Klein
Subcontractors on site: RWK Sub Contracting-1, AGA-1, CCS-6
Visitors: The home owners were on site to review progress.
Equipment Used: The man lift, fork lift, back hoe, artic heater, and foam trailer were on site but not used. 6 sets of scaffolding were used the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time
Work Completed or Work in Progress notes: Siding and exterior trim was being installed on the front of the garage. HVAC duct wrok was being installed in the main house attic. Fire stop was being installed in the main house attic. Mech cut and heading off was completed through out. Electrical circuits were being installed in all recepticals. An interior door take off was completed and is out for pricing.


Tim Beaulieu entered the following on 15:12:55 Feb/23/2009:
Weather Conditions:Sunny and clear high in the low 60's
Date
:
February 23, 2009
Employees Working on site: Tim Beaulieu, Pastor Trejo, Gerson Morales, Nichlas Royas
Subcontractors on site: CCS-3, AGA-1, RWK Sub-Contracting-1, Cuda Company-2
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, foam trailer, and artic heater were on site but not used. 3 bunks of scaffolding were used for 4 hours to install siding.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Mechanical cutting and heading was being completed in the 1st floor main hall for light fixtures. Outlets were boxes were being wired and taped off on the first floor of the main house. Felt paper, window wrap, and vinal were being installed on all main house dormers. Blocking and outlet boxes were being installed on the first floor. Siding and trim was being installed on the garage. The garage windows and doors were being primed.


Tim Beaulieu entered the following on 07:52:51 Feb/23/2009:
Weather Conditions:Sunny and Clear
Date
:
February 20, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T
Subcontractors on site: CCS-4, AGA-1, RWK Sub Contracting-1
Visitors: David Sneddon was on site to view progress.
Equipment Used: The backhoe, manlift, forklift, artic heater, and foam trailer were on site but not used. 6 bunks of scaffolding were used for 4 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Outlet boxes were being installed through out. HVAC duct work was being installed in the main house attic. Can lights were being installed in the kitchen. Upper dormer windows were being installed on the rear of the main house. the entire jobsite was cleaned.


Tim Beaulieu entered the following on 07:46:05 Feb/20/2009:
Weather Conditions:AM rains, Clearing to a high 75
Date
:
February 19, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor Trejo
Subcontractors on site: RWK Sub Contracting-1, Tony-1, CCS-3
Visitors: No visitors today
Equipment Used: The back hoe, man lift, artic heater, foam trailer were on site but not used. The fork lift was on site and used for 1 hour to unload materials from Cudas. 6 sets of scaffold was used the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Mech cut and heading was being completed in the great room, and 2nd floor mechanical chase. HVAC duct work was being installed in the main house attic. Siding was being installed on the rear wall of the garage.


Tim Beaulieu entered the following on 13:48:54 Feb/19/2009:
Weather Conditions:Sunny and Clear high in the Mid 60's
Date
:
February 18, 2009
Employees Working on site: Tim Beaulieu, Pastor T, Nathan Klein
Subcontractors on site: CCS-4, Tony-1
Visitors: Thomas Angell, Home Owners, Jason of YRP
Equipment Used: The back hoe, man lift, fork lift, artic heater, and foam trailer were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen problems or issues to report at this time.
Possible Change Order Items: David would like to move the generator location to the garage service yard. The service yard will have to be made larger. Some minor hardscapes revision were proposed. Thomas Angel will provide a revised plan and submitt to the PBRB.
Work Completed or Work in Progress notes: Mech cut and heading was completed in the 1st floor main hall. Siding was being installed on the garage. The kichens electrical circuits were installed. Duct work was being installed in the master bedroom.


Tim Beaulieu entered the following on 07:26:32 Feb/19/2009:
Weather Conditions:Sunny and Clear, High in the upper 50's
Date
:
February 17, 2009
Employees Working on site: Tim Beaulieu, Pastor T
Subcontractors on site: CCS-5, Tony-1
Visitors: The owners were on site to review progress
Equipment Used: The man lift, fork lift, back hoe, foam trailer, and artic heater were on site but not used. 5 sets of scaffolding were used today for 3 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No new changes to report at this time.
Work Completed or Work in Progress notes: Siding was being installed on the rear wall of the garage and is nearing completion. Electrical circuits were being installed in the main house. Mech Cut and heading was being completed in the great room. HVAC trunk lines were being installed in the attic.


Tim Beaulieu entered the following on 07:23:48 Feb/19/2009:
Weather Conditions:Sunny and Clear high in the upper 50's
Date
:
February 16, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor Trejos, Nicholas Royas
Subcontractors on site: RWK Sub Contracting-1, Tony-1, CCS-3
Visitors: No visitors today
Equipment Used: The man lift, fork lift, back hoe, foam trailer, and artic heater were on site but not used. 5 sets of scaffolding were used today for 3 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Siding was being installed on the rear wall of the garage. Electrical circuits were being installed in the main house. Mech Cut and heading was being completed in the main house foyer.


Tim Beaulieu entered the following on 08:07:56 Feb/16/2009:
Weather Conditions:Sunny and Clear high in the low 70's
Date
:
February 13, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T.
Subcontractors on site: RWK Sub Contracting-1, CCS-7, Hunter Plumbing-2, Tony-1, Year Round Pool-1
Visitors: David was on site to review the rear patio and grades
Equipment Used: The man lift, fork lift, back hoe, foam trailer, and artic heater were on site but not used. All scaffolding was on site but not used today.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David would like to change the rear patio. A meeting is being schedule with all parties to discuss changes. Meeting time is TBA.
Work Completed or Work in Progress notes: Siding was being installed on the garage. HVAC trunk lines were being installed in the main house attic. Mech cut and heading was being completed in the foyer. The rough plumbing was completed today. The lutron panel was being wired in the snd floor mech room. Can lights were being installed through out the main house. HVAC supply lines were being installed in the main house kitchen.


Tim Beaulieu entered the following on 08:00:41 Feb/16/2009:
Weather Conditions:Sunny and Clear high in the mid 70's
Date
:
February 12, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T, Nicholas Royas
Subcontractors on site: RWK Sub Contracting-1, Tony-1, CCS-6, Hunter Plumbing-2
Visitors: No visitors today
Equipment Used: The back hoe, man lift, fork lift, artic heater, and foam trailer were on site but not used. 6 sets of scaffolding were used for 4 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David would like to add two additional recepticals on each side of the fireplace.
Work Completed or Work in Progress notes: Mech cut and heading off was being completed in the master bedroom, and foyer. Receesed can lights were being install through out the main house. HVAC trunk lines were being installed in the main house attic. Hunter plubming was on site today and installed all tubs. Siding was being installed on the garage.


Tim Beaulieu entered the following on 16:08:47 Feb/12/2009:
Weather Conditions:Sunny and Clear, High in the low 70's
Date
:
February 11, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T.
Subcontractors on site: RWK Sub Contracting-1, Tony-1, CCS-6
Visitors: No visitors today
Equipment Used: The back hoe, man lift, fork lift, artic heater, and foam trailer were on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Electrical circuits were being installed on the first floor. Window flashing was being installed on the rear porch. Siding was being installed on the rear wall of the garage. HVAC duct work was being installed in the attic. Mech cutting and heading was being completed in the master bedroom and foyer.


Tim Beaulieu entered the following on 08:45:17 Feb/11/2009:
Weather Conditions:Sunny and Clear upper 60's
Date
:
February 09, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T, Nicholas Royas
Subcontractors on site: RWK Sub Contracting-1, Tony-1, CCS-5, OEM Roofing-5
Visitors: No visitors today
Equipment Used: The back hoe, man lift, fork lift, artic heater, and foam trailer were on site but not used. 9 bunks of scaffolding were used for 6 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC duct work was being installed in the main attic. Fire blocking was being installed in the guest bedroom. Electrical circuits were being installed in the second floor mechanical room. The standing seam roof was being installed on the garage. Siding was being installed on the wall of the garage.


Tim Beaulieu entered the following on 17:47:17 Feb/06/2009:
Weather Conditions:Cold in AM warming to mid 50's
Date
:
February 6, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T., Ed E.
Subcontractors on site: RWK Sub-Contracting-1, Tony-1, CCS-6, OEM Roofing-4, Cuda Company-5
Visitors: No visitors today
Equipment Used: The man lift, fork lift and back hoe were on site but not used. The artic heater was on site and used for 6 hours. All scaffolding was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Exterior siding and trim were being installed on the garage wall at the service yard location. Doors and windows were being primed through out the main house and garage. Electrical circuits were being installed on the first floor of the main house. HVAC duct work was installed in the main house attic. Mech heading off was being completed in the second floor mech chase. Knee walls were being constructed in the main house attic. Standing seam roofing was being installed on the garage.


Tim Beaulieu entered the following on 08:23:07 Feb/06/2009:
Weather Conditions:Cold but clear high in the upper 30's
Date
:
February 05, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T.
Subcontractors on site: Cuda Company-6, RWK Sub-Contracting-1, Tony-1, OEM Roofing-4, CCS-4
Visitors: No visitors today
Equipment Used: The back hoe, man lift, and fork lift were on site but not used. The artic heater was on site and used for 6 hours. The foam trailer was on site but not used. 10 bunks of scaffold were used for 5 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Electrical circuits were being installed through out the first floor. Mech cut and heading was being completed in the HVAC chase in the mech room. The french doors on the front of the house were being flashed. The three wing walls were framed in the kitchen. Main HVAC trunk lines were being installed in the main house attic. Roofing was being installed on the garage roof. Windows and doors were being primed through out the main house.


Tim Beaulieu entered the following on 09:25:44 Feb/05/2009:
Weather Conditions:Cold High in the low 30's, Heavy winds at times
Date
:
February 04, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Pastor T.
Subcontractors on site: CCS-5, RWK Sub-Contracting-1, Tony-1
Visitors: No visitors today
Equipment Used: The man lift, back hoe, and manlift were on site but not used. The artic heater was on site and used for 6 hours to heat the main house. 8 bunks of scaffolding was used for 8 hours. The foam trailer was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC trunk lines were being installed in the main house attic. Electrical circuits were being installed through out the first floor. The shed ceiling above the master bath tub was dropped level to the rest of the ceiling heights. The powder room door way was framed. The 30 x 30 HVAC return was framed in the great room wall. Window 210 was installed in the great room.


Tim Beaulieu entered the following on 08:54:18 Feb/04/2009:
Weather Conditions:Sunny and Clear, low 60's
Date
:
February 03, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T, Nicholas Royas
Subcontractors on site: CCS-5, RWK Sub-Contracting-1, Tony-1
Visitors: No visitors today
Equipment Used: The man lift, fork lift, and back hoe were on site but not used. The artic heater was on site and used for 3 hours to heat the main house. The foam trailer was on site but not used. Six bunks of scaffolding was used for 5 hour
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Electrical circuits were being installed on the first floor. HVAC duct work was being installed in the main attic and great room dormers. Window 210 was being framed for installation. Rear porch column bases were being installed. Windows were being flashed around the main house. Mechanical cut and head was being completed in the 2nd floor guest bedroom. Heading off will allow duct work to pass through the guest bedroom and supply the master bedroom.


Tim Beaulieu entered the following on 08:50:22 Feb/03/2009:
Weather Conditions:Clear in AM, PM showers
Date
:
February 02, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Gerson Morales, Pastor T
Subcontractors on site: RWK Sub-Contracting-1, Tony-1, CCS-4
Visitors: No visitors today
Equipment Used: The back hoe, man lift, and fork lift were on site but not used. The artic heater and foam trailer were on site but not used. Two sets of scaffold were used for 3 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Electrical circuits were being installed on the first floor. Lightning protect was completed on the great room chimmeny. Rear porch columns were being installed. Mechanical cut and heading was being completed in the main house attic.


Tim Beaulieu entered the following on 15:20:43 Jan/30/2009:
Weather Conditions:Sunny and Clear, high in the upper 50's
Date
:
January 30, 2009`
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas
Subcontractors on site: RWK Sub-Contracting-1, Tony-1, OEM Roofing-2, 4m Metals-3, CCS-3
Visitors: No visitors today
Equipment Used: The fork lift was on site and used for 1 hour to move exterior window and door trim. The man lift was on site and was used to install the garage roof. The back hoe, artic heater and foam trailer were on site but not used. 3 bunks of scaffold were used for 6 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Columns were being installed on the rear porch. Mech heading off was being completed in the 2nd floor guest bathroom and closet. HVAC duct work was being installed in the main house attic. 4m Metal was on site and delivered all garage roof panels. Coastal Machine finishing was on site and delivered all exterior window and door trim. All trim was staged in the garage. Electrical circuit were being installed in the 2nd floor study.


Tim Beaulieu entered the following on 14:45:14 Jan/30/2009:
Memo:
Site meeting minutes 012809

Meeting Minutes from the 1/28/09 Electrical/Mechanical Walk-
through:

 

Attendance: David and Dorothy Sneddon, Tim Beaulieu, Nathan 
Klein, Gary Thomas, and Joe Curcio

 

Room-by-Room Walk through:

 

Master Bath/Bedroom –

·         Owners would like a price on Floor Heat

·         Owners want a quote on bottom-up mecho shades for 
the windows at the tub and the water closet

·         Added a dedicated (? – need cut sheet) receptacle 
at the toilet for a heated toilet seat

·         The vanity lights will be grouped together which 
frees up one zone on the Lutron system

·         They have accepted that the bath fans will 
operate via an ERV through the touch of a light switch, and 
have a grill in both the shower and the Water closet.

·         Relocate a receptacle in the water closet to 
below the window.

·         Tub has jets and heater.  Need cut sheet.

·         Closets – lights will operate on motion sensors 
with override and timer 

·         Door entering the master bedroom was revised to a 
single 36” door in lieu of double doors. The swing was 
confirmed on site (LH) in swing to master, centered in 
current RO, will require additional framing. 

 

Laundry Room

·         Clarify: 2 - Surface mounted fluorescence on a 
smart switch

·         Add 1 Built ironing board 

·         The location of this ironing board was changed to 
the hall wall in the laundry room. The ironing board will 
be center between the transom and pocket door. The finish 
height above the extended board needs to be just above the 
counter height to avoid conflict in the close quarters.

·         Add 1 under cabinet light 

 

Pantry

·         Clarify: 1 – Surface mounted fluorescent on a 
smart switch

 

Hall to Bedroom

·         Add recessed can so that all picture wall receive 
adequate and direct lighting for artwork

 

Front Hall

·         Add 2 recessed cans on the Studio side of the 
hall in a 2 x 2 layout, and add two additional cans on the 
pantry side; one over the Piano and the other by the door 
for art work (I have sketches of the layout for 
clarification)

 

Great Room

·         Added two Lutron circuits

o        1 – set of switched receptacles in the floor next 
to the couch

o        1 – set of receptacles next to the fireplace

·         We need to run speaker wire for AV

 

Kitchen

·         We need to as-build lights from existing house 
and install them identically in the new house.  (Meeting 
will be on Friday at 1530 (3:30PM))

·         Garbage disposal to be on a toggle switch

 

Studio

·         OK as is

 

Studio Bath

·         Add receptacle at vanity

·         Add receptacle across from vanity? (need this 
confirmed) 

·         Dorothy would like the receptacle across from the 
vanity. It was discussed that it would be better to have it 
now then add it later.

 

Porch

·         Gas Lanterns were relocated to the wall

o        They would like to be able to switch the lanterns 
from the Lutron System.  This needs to be researched further

·         Fan location is ok  (Fan location at swing is 
still unclear we will install box and wire, but blank plate 
for future use 

·         Check to see what the current recessed can 
situation on the porch is.  They will want to keep it the 
same on the new house.  Will verify this today.

·         Check on the back side of the fireplace

·         Add 8 receptacles in the screened porch

·         Add a recessed can by the grill

·         Add front porch and cottage lutron switched 
receptacles for Christmas

 

Storage

·         Add Light and receptacle for Cedar Closet being 
added to the storage 

·         David, Tim, Joe and I discussed the cedar storage 
closet.

·         David would like approximately a  4 foot x 4 foot 
cedar lined closet for storage of garments. 

·         David would like a safe installed in the wall 
adjacent to the bathroom/mechanical wall. The approximate 
allowable dimensions for this safe would be 5 feet +/- 
tall, 32” +/- wide, and a maximum of 30” deep.

 

Guest House

·         Add two lutron keypads (change order required)

·         Check porches for existing lights

 

As a side note; here are some items that need confirmed or 
discussed so that they may proceed. 

Front entry proposal needs reviewed and confirmed for 
production. 
The garage door final selections need confirmed. 
Dorothy requested a confirmation on the bidet seat specs. I 
confirmed that it is has all the features offered, with the 
exception of automatic opening/closing and self flushing. 
These seem to be indigent care features that may not be 
necessary to the Sneddon; however I will confirm. 
Cabinet changes in Bath 207, single bowl vanity to a double 
bowl vanity needs confirmed with MMC. Two sets of plumbing 
fixtures have been confirmed for this bath. 
2 sink cut-outs have been confirmed for Bath 207 
countertop. 
Connector style needs confirmed for final drawings to be 
issued from the architect. 
Service yard revisions are being submitted to Palmetto 
Bluff Review Board for approval 
Thomas Angell is discussing retaining wall concerns with 
review board 
Gas Lanterns are being added at the end of the driveway, 1 
on each side of drive 
Are we installing a Unico system for attic? Service yard 
revision will hold 4 units 


Tim Beaulieu entered the following on 09:35:44 Jan/30/2009:
Weather Conditions:Heavy AM rain, Clearing in PM
Date
:
January 29, 2009`
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas
Subcontractors on site: CCS-5, RWK Sub-Contracting-1, Tony-1, OEM Roofing-1
Visitors: Thomas Angell was on site to review retaining wall and service yards.
Equipment Used: The man lift, back hoe, scaffolding, foam trailer, and artic heater were on site but not used. The fork lift was on site and used for 1 hour.
Urgent Items and Equipment Needed
:
Finalize covered walkway as soon as possible
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Mechanical cut and head was being completed in the 2nd floor guest bedroom. Mechanical cut and head was underway in the great room ceiling this will allow room for a 22 inch HVAC return. Garage man doors were being installed in the bonus room. Porch columns were being installed on the rear porch of the main house. Eletrical circuits were being install on the second floor. HVAC duct work was being completed in the main house attic. Thomas was on site to review service yard requirements and retaining wall elevations. Thomas stated it will take about two hours to complete revision. Thomas will submit revisions to the review board for approval. The roof material take off was complete for the garage.


Tim Beaulieu entered the following on 20:21:10 Jan/29/2009:
Weather Conditions:Sunny and clear, high in the mid 60's
Date
:
January 28, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas, Nathan Klien
Subcontractors on site: CCS-7, RWK Sub-Contracting-1, Tony-1, Coastal Door and Sash-1
Visitors: The Sneddons were on site today to go over MEP lay outs, door swings, cabinet lay out.
Equipment Used: The back hoe, and man lift were on site but not used. The fork lift was on site and used for 1 hour. The artic heater was on site but not used. The foam trailer was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues at this time.
Possible Change Order Items: The floor outlets will now be switched outlets. The master bedroom doors will now be a single 3/0 8/0 door LH in swing. Additional receptical will be installed on the porches. Can lights will be added to the foyer for wall/art lighting.
Work Completed or Work in Progress notes: HVAC duct was underway in the main house attic. Columns were being installed on the side porch of the main house. The back ordered windows and doors were delivered. We still have 1 transom that is still back ordered. Electrical lay out was being conducted through out the main house. Cabinetry was laid out in the kitchen. Mech/ Cut and head was being completed in the mech room on the 2nd floor of the main house.


Tim Beaulieu entered the following on 10:22:40 Jan/28/2009:
Weather Conditions:Sunny and Clear, lower 60's
Date
:
January 27, 2009`
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas
Subcontractors on site: RWK Sub Contracting-1, Tony-1, CCS-3, Able Contracting-1, Cregger-2, Big Horn-4
Visitors: No visitors today
Equipment Used: The manlift was on site but not used. The back hoe was on site and used for 1 hour to grade the driveway. The fork lift was on site and used for 2 hours to unload materials. The artic heater was on site but not used. The foam trailer was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Recycled concrete was delivered for the drive. Electrical circuits were being installed on the 2nd floor. HVAC duct work was being installed in the garage apartment. Concrete was cut out in the kitchen, master bathroom. Cregger delivered all tubs with the exception of the master bathroom.


Tim Beaulieu entered the following on 10:05:49 Jan/28/2009:
Weather Conditions:Sunny and Clear mid 50's
Date
:
January 26, 2009`
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas
Subcontractors on site: CCS-3, RWK Sub-Contracting-1, Tony-1
Visitors: No visitors today
Equipment Used: The manlift, fork lift, back hoe, and artic heater were on site but not used. All scaffolding was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Exterior columns were being installed on the front porch. Electrical circuts were being installed on the second floor. HVAC duct work was being installed in the garage apartment. Rafter ties were being installed in the main house attic.


Tim Beaulieu entered the following on 09:58:25 Jan/28/2009:
Weather Conditions:Sunny and Clear upper 50's
Date
:
January 23, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Royas
Subcontractors on site: RWK Sub-Contracting-1, Tony-1, CCS-5, Hunter Plumbing-2
Visitors: No visitors today
Equipment Used: The fork lift, back hoe, and JLG lift was on site but not used. All scaffolding was on site but not used. The artic heater was on site and used for 2 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Porch ceiling fan boxes were being installed around main house porches. Garage windows were being installed. Rough in plumbing work was completed today. All shower valves have been installed. Fan controls boxes were being install in the mech room. HVAC line sets were being install in the main house attic.


Tim Beaulieu entered the following on 14:18:23 Jan/23/2009:
Weather Conditions:Sunny clear, high in the low 40's
Date
:
January 22, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Rojas
Subcontractors on site: CCS-6, Tony-1, RWK Sub Contracting-1, Hunter Plumbing-2
Visitors: No visitors today
Equipment Used: The man lift was on site and used for 4 hours to install windows on the garage. The fork lift was on site and used for 2 hours to move material. The back hoe was on site but not used. The Artic heater was on site and used for 6 hours. The foam trailer was on site but not used. 2 Sets of scaffold was used for 3 hours to install windows.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The garage windows were being installed in the bonus room. Rough in electrical work was being completed on the 2nd floor of the main house. Lightning protection was being completed on the main house roof. Rough in plumbing work was being insulated. Framing modification was completed in the guest bedroom of the main house. HVAC line sets were being installed across the master bedroom ceiling.


Tim Beaulieu entered the following on 14:11:19 Jan/23/2009:
Weather Conditions:Sunny and Cold high in the low 40's
Date
:
January 21, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Rojas
Subcontractors on site: Tony-1, CCS-6, Hunter Plumbing-2
Visitors: No visitors today
Equipment Used: The man lift, and back hoe were on site but not used. The fork lift was on site and used for 2 hours. The artic heater was on site and used for the 6 hours. All scaffolding was on site but not used
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Rough in plumbing was being completed in the kitchen of the main house. All pipes are being insulated. Ceiling fan boxes were being installed on the main house porches. Line sets were being installed in the main house. Transoms were being installed over the french doors in the great room.


Tim Beaulieu entered the following on 12:01:36 Jan/21/2009:
Weather Conditions:Cold high in the low 40's
Date
:
January 20, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas R
Subcontractors on site: Tony-1, CCS-5, Hunter Plumbing-2
Visitors: No visitors today
Equipment Used: The manlift, forklift, and back hoe were on site but not used. The artic heater was on site and used for the entire day. No scaffolding was used today. The foam trailor was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes at this time.
Work Completed or Work in Progress notes: Fan boxes were being installed on the front and rear porch of the main house. Rougg in plumbing was being installed in the laundry room. All tubs were delivered but are the wrong hand tubs. The supplier was contacted for pickup and informed about the their mistake. Lightning protection was being installed on the main house front porch roof. The temporary garage doors were installed. Windows and doors were being installed in the main house. Coastal door and sash was contacted. Toby stated that the back ordered doors would be delivered on Thursday.


Tim Beaulieu entered the following on 11:53:22 Jan/21/2009:
Weather Conditions:Cold high in the upper 40's
Date
:
January 19, 2008
Employees Working on site: Gerson Morales, Nicholas R.
Subcontractors on site: Tony-1, CCS-5, Hunter Plumbing-2
Visitors: David and Guest were on site today to veiw progress
Equipment Used: The manlift, forklift, and backhoe were on site but not used. The Artic heater was on site used for 9 hours. The foam trailor was on site but not used. Three sets of scaffold was used for 2 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David would like to add shades in the master bathroom around the tub bay.
Work Completed or Work in Progress notes: Lightning protection was being installed on the main house front porch roof. Electrical lay out is underway. Rough plumbing supply lines were being installed in the main house. Temp garage doors were fabricated and will be install in the AM. Doors and windows were being installed in the master bedroom.


Tim Beaulieu entered the following on 06:48:19 Jan/19/2009:
Weather Conditions:Sunn but cold high in the low 40's
Date
:
January 16, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas R
Subcontractors on site: RWK Sub Contracting-1, Tony-1, CCS-6, Hunter Plumbing-2
Visitors: David was on site today to view progress.
Equipment Used: The fork lift was on site and used for 1 hour. The man lift was on site and used for 2 hours to install windows on the garage. The back hoe was on site but not used. 1 Big horn bobcat was on site and used for 1 hour to grade the front drive. 4 sets of scaffolding was used for 5 hours today. The artic heater was on site and used for the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC rough in work was being completed in the main house attic and garage bonus room. Rough in plumbing was being completed in the main house. Electric panels were being installed in the second floor mech room. The garage was cleaned out and all exterior trim and siding was place in to the 2 bay section. Temp doors will be fabricated to secure the area.


Tim Beaulieu entered the following on 06:41:49 Jan/19/2009:
Weather Conditions:Sunny but cold high in the mid 40's
Date
:
January 15, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas R
Subcontractors on site: CCS-5, Tony-1, Hunter Plumbing-2, PGPNA-2
Visitors: No visitors today
Equipment Used: The fork lift, man lift, and back hoe were onsite but not used. All equipent had all fluids topped off and equipment was greased. No scaffolding was used today.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: HVAC rough in work is on going in the garage and main house. Plumbing rough ins are nearing completing. Plubming valves are needed as soon as possible. Windows were being installed on the front of the house. Lightning protection was worked on today on the main house front gable.


TIm Beaulieu entered the following on 06:36:22 Jan/19/2009:
Weather Conditions:Sunny and Clear, High in the low 50's
Date
:
January 14, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas R
Subcontractors on site: CCS-5, Tony-1, Hunter Plumbing-2
Visitors: David was on site to view progress
Equipment Used: The back hoe, man lift and fork lift were on site but not used. Two sets of scaffold were used for 3 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: Drop ceiling in second floor guest bathroom. Move guest bedroom clostet wall forward 16 inches to allow room for HVAC unit. Add bases to columns.
Work Completed or Work in Progress notes: Line sets were being installed in the main house. Duct work was being completed in the garage. The rear doors were being installed in the great room. Supply plumbing rough in was on going through out the main house.


Tim Beaulieu entered the following on 18:35:19 Jan/14/2009:
Weather Conditions:Sunny and clear, High in the Mid 50's
Date
:
January 13, 2009
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas, Ed E.
Subcontractors on site: CCS-6, RWK Sub Contracting-1, Tony-1, Hunter Plubming-2
Visitors: David was on site to review progress
Equipment Used: The man lift, back hoe, and fork lift were on site but not used. No staging was used today.
Urgent Items and Equipment Needed
:
No foreseen issues to report at this time.
Possible Change Order Items: A drop ceiling is in order for the 2nd floor guest bathroom. This will allow room for HVAC duct work to come down from the attic. 1 Hub drain will be added to the attic.
Work Completed or Work in Progress notes: Exterior doors were being installed around the first floor of the main house. Lightning protection was being installed on the main house. Electrical panels were being installed in the 2nd floor mech room. A walk thru with CCS was completed to go over HVAC lay out. Revisions will be made to the current drawings. Plubming supply lines were being installed through out the first floor. Hunter Plubming was on site to discuss the Hub drain in the attic space.


Tim Beaulieu entered the following on 18:28:00 Jan/14/2009:
Weather Conditions:Rain through out the day
Date
:
Jaunuary 12, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas
Subcontractors on site: CCS-5, Hunter Plubming-2
Visitors: No visitors today
Equipment Used: The manlift, forklift, and back hoe were on site but not used. 3 Sets of staging was used for 3 hours.
Urgent Items and Equipment Needed
:
No foressen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Windows were being installed in the main house. Foam insulation was completed in the garage. Lightning protection was being installed in the main house. Electrical boxes were being installed through out the main house. Supply water lines were being installed through out the first floor of the main house. HVAC lay out was being completed.


Tim Beaulieu entered the following on 18:02:56 Jan/08/2009:
Weather Conditions:Sunny and clear
Date
:
January 8, 2009
Employees Working on site: Tim Beaulieu, Nicholas R
Subcontractors on site: CCS-5, RWK Sub Contracting-1, Hunter Plumbing-2
Visitors: No visitors today
Equipment Used: The fork lift, man lift, and back hoe were on site but not used. All scaffold on site but not used.
Urgent Items and Equipment Needed
:
Cabinet drawings and HVAC lay out is needed as this could affect existing rough in work.
Possible Change Order Items: Two drain hubs will be installed in the main house attic for HVAC drains.
Work Completed or Work in Progress notes: Lightning protection was installed on the main house front dormer. Rough in plumbing work was being installed on the second floor of the main house. The scuddle hole in the garage apartment was completed. Mech/Cut and head was completed in the main hall. HVAC line sets were being installed in the main house. Foam insulation was being installed in the garage bonus rooms. The front windows in the front upper dormer were installed.


Tim Beaulieu entered the following on 17:52:49 Jan/08/2009:
Weather Conditions:Sunny and Heavy afternoon winds
Date
:
January 7, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas R
Subcontractors on site: CCS-7, MMC-2, Hunter Plumbing-2, RWK Sub Contracting-1
Visitors: The Sneddons were on site today to review cabinet details with MMC
Equipment Used: The fork lift, man lift, and back hoe were on site but not used. 3 sets of scaffold were used for 5 hours.
Urgent Items and Equipment Needed
:
HVAC lay out is needed for the main house as duct work may affect existing DWV plubming work.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Lightning protection was being installed in the garage. Foam insulation was being sprayed in the garage second floor. HVAC line sets and drains were being installe in the garage. Windows were being installed on the second floor. DWV plubming rough in were on going in the 1st floor of the main house.


Tim Beaulieu entered the following on 17:52:45 Jan/08/2009:
Weather Conditions:Sunny and Heavy afternoon winds
Date
:
January 7, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas R
Subcontractors on site: CCS-7, MMC-2, Hunter Plumbing-2, RWK Sub Contracting-1
Visitors: The Sneddons were on site today to review cabinet details with MMC
Equipment Used: The fork lift, man lift, and back hoe were on site but not used. 3 sets of scaffold were used for 5 hours.
Urgent Items and Equipment Needed
:
HVAC lay out is needed for the main house as duct work may affect existing DWV plubming work.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Lightning protection was being installed in the garage. Foam insulation was being sprayed in the garage second floor. HVAC line sets and drains were being installe in the garage. Windows were being installed on the second floor. DWV plubming rough in were on going in the 1st floor of the main house.


Tim Beaulieu entered the following on 06:49:50 Jan/07/2009:
Weather Conditions:Sunny and clear upper 70's
Date
:
January 6, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas R
Subcontractors on site: CCS-5, Big Horn-8, Hunter Plumbing-2, RWK Sub Contracting-1
Visitors: No visitors today
Equipment Used: The man lift, Fork lift and back hoe were on site but not used. All scaffolding was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Lightning protection was installed in the garage. HVAC line sets were being installed in the garage. Windows were being installed on the second floor of the main house. Window RO's were being preped. Rough DWV plubming was being installed in the main house.


Tim Beaulieu entered the following on 06:45:26 Jan/07/2009:
Weather Conditions:Sunny and Clear
Date
:
January 5, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas R
Subcontractors on site: RWK Sub Contracting-1, Hunter Plumbing-2, CCS-3
Visitors: David was on site to view progress
Equipment Used: The back hoe, man lift were on site but not used. The forklift was on site and used for 1 hour to move materials. The Big Horn bobcat was on site and used for 30 minutes to fill in the driveway apron.
Urgent Items and Equipment Needed
:
Any HVAC plan is needed the the main house has plubming being roughed in.
Possible Change Order Items: David would like jam switches in the upstair closets. David has also requested sensors to turn on the master closet lights, he does not want jam switched as he may just end up leaving the doors open. David stated he was ok with all the electrical panels going in the upstairs storage room.
Work Completed or Work in Progress notes: Lightning protection was being installed in the main house. Windows RO's were being preped for window installation. The entire door package was delivered. Rough in DWV was being installed in the main house.


Tim Beaulieu entered the following on 15:20:56 Dec/18/2008:
Weather Conditions:Sunny, Warm Low 80's
Date
:
December 17, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Reyas, Pastor T, Rolando Nunez
Subcontractors on site: Big Horn-1, CCS-4, RWK Sub Contracting-1, Hunter Plumbing-2
Visitors: No visitors today
Equipment Used: The man lift was on site but not used, The forklift was on site and used for 1 hour, The back hoe was on site and not used, The foam trailer was on site and used for 8 hours. One big horn bob cat was on site and used for 1 hour to complete grade work.
Urgent Items and Equipment Needed
:
Toby called and stated the windows did not get delivered to his shop and they were being rescheduled for delivery on Thursday.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Rough plumbing work was being completed in the garage and bonus room. Spray foam insulation was being installed in the main house. Lightning protection was being installed in the garage and bonus rooms above.


Tim Beaulieu entered the following on 10:50:15 Dec/18/2008:
Weather Conditions:Sunny and Clear, High 60's
Date
:
Decmeber 16, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Reyas
Subcontractors on site: CCS-3, RWK Sub Contracting-1, Hunter Plumbing-2
Visitors: No visitors today
Equipment Used: The manlift was on site and used for 1 hour. The back hoe was on site but not used. The forklift was on site and used for 1 hour to move materials. 1 Big horn bobcat was on site but not used. The desiel heater was on site but not used. The foam trailer was on site and used the for 8 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Lightning protection was installed around the front and rear porch. Rough plumbing was installed in the garage. Foam insulation was installed in the main house.


Tim Beaulieu entered the following on 19:26:41 Dec/17/2008:
Weather Conditions:Sunny and clear
Date
:
December 15, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales
Subcontractors on site: RWK Sub Contracting-1, CCS-3
Visitors: No visitors today
Equipment Used: The manlift, back hoe and forklift were on site. The Big Horn bobcat was on site but not used. The back hoe was used for 30 minutes to grade the driveway.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time
Work Completed or Work in Progress notes: Lightning protection was installed on the main house. Foam insulation was being installed in the master bedroom and closets.


Tim Beaulieu entered the following on 12:53:56 Dec/15/2008:
Weather Conditions:Overcast through out the day
Date
:
December 12, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales
Subcontractors on site: CCS-3, Hunter Plumbing-2
Visitors: No visitors today
Equipment Used: The forklift, manlift, and back hoe were on site but not used. 1 bob cat was delivered to the site by Big Horn construction.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The exterior of the project was being cleaned and regraded. Felt was installed on the rear of the main house. Lightning protection was installed on the rear and front porch. Rough plubming was installed in the garage bonus room .


Tim Beaulieu entered the following on 12:49:36 Dec/15/2008:
Weather Conditions:Sunny and Clear
Date
:
December 11, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales
Subcontractors on site: CCS-2, Big Horn-1, Hunter plumbing-2
Visitors: No visitors today
Equipment Used: The forklift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Lightning protect was being installed in the attic. The main ground conductor was installed. Felt paper was being installed on the rear of the main house. Counter flashing blocking was installed on the main house.


Tim Beaulieu entered the following on 10:19:14 Dec/15/2008:
Weather Conditions:Sunny and Clear
Date
:
December 10, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales
Subcontractors on site: JTS Construction-2, CCS-2
Visitors: No visitors today
Equipment Used: The forklift was on site and used for 1 hour to move materials.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes at this time.
Work Completed or Work in Progress notes: Counter flash blocking was being installed on the roof dormers. Felt and was being installed on the front of the main house. Lightning pretection lay out was underway. The driveway was laid out and the review board has been schedule for viewing.


Tim Beaulieu entered the following on 18:16:08 Dec/10/2008:
Weather Conditions:Sunny and Clear
Date
:
December 09, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales
Subcontractors on site: JTS Contruction-2, RWK Sub Contracting-1, CCS-2
Visitors: No visitors today
Equipment Used: The BTV forklift was on site and used for 2 hours to move materials.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Felt was being installed on the main house. Brick work was being cleaned at the garage apron. Foam insulation was being scraped from the studs and cleaned. Electrical wiring was installed in the attic for lighting. The main electrical panels were delivered.


Tim Beaulieu entered the following on 15:37:12 Dec/09/2008:
Weather Conditions:Sunny and Clear
Date
:
Decmeber 08, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Reyas
Subcontractors on site: Big Horn-8, JTS Consruction-2, RWK Sub-Contracting-1, OEM Roofing-2
Visitors: No visitors today
Equipment Used: The BTV forklift was on site and used for 1 hour to move materials. The CCS Foam insulation trailer was on site used the entire day to install insulation on the 2nd floor of the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Install foam insulation in the 2nd floor of the main house. Install foam blocking at rafter and top plate connection. Mortar was being install on the garage apron. Foam was being scraped from the attic. The 2nd floor bathroom and closet interior walls were framed. The review board was contacted and was asked to come and look at the driveway lay out. Karen stated the DRB would be on site on Thursday afternoon.


Tim Beaulieu entered the following on 15:30:17 Dec/09/2008:
Weather Conditions:Overcast light rain at times
Date
:
December 05, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Nicholas Reyas
Subcontractors on site: Big Construction-6, CCS-1, JTS Construction-2, RWK Sub Contracting-1
Visitors: No visitors today
Equipment Used: The BTV forklift was on site and used for one to move materials. The CCS foam trailor was on site and used the entire day to insulate the main house
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Foam insulation was being applied to the attic in the main house. Brick work was being laid out at the front stairs. Pocket doors were being framed.


Tim Beaulieu entered the following on 17:29:07 Dec/08/2008:
Weather Conditions:Sunny and Clear
Date
:
December 4, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales
Subcontractors on site: RWK Sub Contracting-1, JTS Construction-2, CCS-2, OEM Roofing
Visitors: No visitors today
Equipment Used: The foam rig was on site and used for half the day. The fork lift was on site and used for 1 hour to move material.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Foam insulation was being installed in the attic. Valley and roof flashing was being installed aroung the main house roof. Foam blocking was being installed in the great room.


Tim Beaulieu entered the following on 19:54:42 Dec/03/2008:
Weather Conditions:Sunny and clear 32 in the AM, high of 60
Date
:
December 03, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: JTS Construction-2, OEM Roofing-2, Cuda Company-5, Big Horn-6
Visitors: The home owners were on site today to discuss covered walk, generator, recirc loop, and lutron.
Equipment Used: The fork lift was on site and used for 2 hours. The artic heater was delivered and used for 6 hours. The foam trailor was delivered to the site and is staged in front of the main house.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: The generator rough in work will be completed but we will not purchase the generator or transfer switch. The Sneddon are interested in Lutron and would like to see a home with the system. David has approved construction of the covered walk way. David would like to add the recirc loop.
Work Completed or Work in Progress notes: Brick work was being installed on the garage apron. Counter flashing and blocking was installed on the main house dormers. Fascia and rafter tails were being painted. All exterior stairs have now had the bricks installed. The artic heater was installed into the laundry room. Foam blocking was being installed in the great room.


Tim Beaulieu entered the following on 19:46:46 Dec/03/2008:
Weather Conditions:Cold high in the low 60's
Date
:
December 2, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales
Subcontractors on site: Big Horn-11, JTS Construction-2, RWK Sub Contracting-1, Cuda Company-5
Visitors: The owners were on site to view progress
Equipment Used: The fork lift was on site and used for 1 hour
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: I met with the Phil from the Beaufort County Inspection Department. Phil has granted us permission to go ahead and install the closed cell insulation. Insulation blocking was being installed at the gable walls. Rafters and fascia boards were being primed and prepared for paint. All window and door opening were covered with Tyvex. A heater will be installed in the space during the insulation process. Brick was being installed at the garage apron and front stairs. Counter flashing blocking was being installed on the front dormers. The roof flashing material take off was completed and ordered work will begin in the morning.


Tim Beaulieu entered the following on 19:31:44 Dec/01/2008:
Weather Conditions:Sunny and Clear
Date
:
December 1, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales
Subcontractors on site: RWK Sub Contracting-1, JTS Construction-2, Big Horn Construction-11, Cuda Company-5, Hilton Head Exterminators-4, CCS-2
Visitors: David Sneddon was on site today to review progress
Equipment Used: BTV forklift was on site and used for 1 hour
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The garage apron and all exterior stairs were poured today. Conduits were being installed in the garage service yard. Felt paper and window flashing was being installed on the main house and garage. Borate treatment was completed on the garage, garage apartment, and main house. Chase framing was being completed in the storage room. Facia and rafter tail were being primed on the main house.


Tim Beaulieu entered the following on 09:09:36 Dec/01/2008:
Weather Conditions:Sunny and Clear
Date
:
November 28, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Cuda Company-5
Visitors: No visitors today
Equipment Used: The BTV fork lift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Rafter tails, facia, and v groove cypress was being prepared for primer.


Tim Beaulieu entered the following on 09:07:47 Dec/01/2008:
Memo:
Holiday Routine 

November 27, 2008 


Tim Beaulieu entered the following on 09:03:49 Dec/01/2008:
Weather Conditions:Sunny and clear
Date
:
November 26, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Danny Tracy
Subcontractors on site: JTS Construction-2, Big Horn Construction-11, CCS-2
Visitors: The home owners were on site today to view progress. David would like to drive the driveway prior to pouring the center circle.
Equipment Used: The fork lift was on site and used for 1 hour.
Urgent Items and Equipment Needed
:
J. Jordan of Big Horn Construction suffered from LOC and was transported to Coastal via Beaufort Country
Possible Change Order Items: The rear stairs off the rear porch of the master bed room will return to the origanal plans.
Work Completed or Work in Progress notes: The roof was wrapped with Grace Ice and water shield. Conduits were being installed to service yard locations. Steel was being installed in the garage apron and stairs. Step light conduits were installed. The attic had 3/4 plywood being installed. This space will house all HVAC equipment.


Tim Beaulieu entered the following on 08:57:21 Dec/01/2008:
Weather Conditions:Sunny and Clear
Date
:
November 25, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Danny Tracy
Subcontractors on site: Big Horn Construction-11, JTS Construction-2, CCS-1
Visitors: The home owners were on site today to view progress. Phil of Beaufort County insepection department.
Equipment Used: The fork lift was on site and used for 2 hours.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The main house was inspected. We now have permission to cover the roof and walls. Service yards were being laid out. The pool equipment slabs corners were staked out. All stairs were being formed up. Borate treatment is scheduled for Monday.


Tim Beaulieu entered the following on 08:53:23 Dec/01/2008:
Weather Conditions:Sunny and clear
Date
:
November 24, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Danny Tracy, Pastor T
Subcontractors on site: Big Horn Construction-11, JTS Construction-2, CCS-1
Visitors: No visitors today
Equipment Used: The forklift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The closet door in the garage apartment will be framed in so there will be no closet. This will allow room for to queen size beds. David has approved this change.
Work Completed or Work in Progress notes: Main gable framing was completed. The front dormer roof was being completed. Conduits were being installed for the service yards. The garage apron and walk were formed up and will be poured on Monday. The nailing inspection was called in for Tuesday. Pocket door framing was being completed in the master bedroom.


Tim Beaulieu entered the following on 13:35:22 Nov/21/2008:
Weather Conditions:Cold, High in the upper 40's
Date
:
November 20, 2008
Employees Working on site: Tim Beaulieu, Nicholas Reyes, Pastor T, Danny Tracy, Jose B, Gerson Morales
Subcontractors on site: MMC-2, JTS Construction-1, Big Horn-12
Visitors: The owners were on site today
Equipment Used: The fork lift was on site and used for 1 hour.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Main gable rafter tails and v groove cypress was being installed. Pickup framing was being completed. Mirror and picture blocking was installed. The 2nd floor hall ceiling was dropped to accommodate HVAC duct work. All brick work was being acid washed. The brick band and porch border was installed around the front and side porches. Concrete work was laid out for a Monday pour. The rear porch columns were being installed and plumbed up. The front dormer was being framed over the front door. The silt fence and tree protection was straightened up.


Tim Beaulieu entered the following on 09:44:58 Nov/20/2008:
Weather Conditions:Cold high in the upper 40's
Date
:
November 19, 2008
Employees Working on site: Tim Beaulieu, Nicholas R, Pastor T, Danny Tracy, Jose B,
Subcontractors on site: Big Horn-11, JTS Construction-1
Visitors: David was on site today to view progress
Equipment Used: The BTV fork lift was on site and used for 1 hour.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Pocket door framing was being completed in the master bedroom. Brick band and porch borders were being installed on the front and side porch. Porch roof sheathing was installed. Blocking was installed in the main house for pictures and mirrors. The rear porch posts were being installed. All posts have been epoxied and will be set on Thursday. Rafter tails were installed across the front porch. Fire blocking was installed on the second floor of the main house.


Tim Beaulieu entered the following on 16:29:14 Nov/19/2008:
Weather Conditions:Cold, high in the low 50's
Date
:
November 18, 2008
Employees Working on site: Tim Beaulieu, Nicholas R, Pastor T, Danny Tracy, Jose B
Subcontractors on site: Big Horn-11, JTS Construction-2
Visitors: David was on site to view progress
Equipment Used: The fork lift was on site and used for 30 minutes to move materials.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David was on site and stated that he did not what the double pocket door going into the bathroom. I asked David what and when the door was going to be. David stated that he wanted a single pocket door that will moved left to provide a longer wall by his bed.
Work Completed or Work in Progress notes: Roof framing was underway on the front porch. Brick band work was being completed on the front of the house. Exterior trim was being priced. Pocket door framing was underway in the main housee master bedroom. The great room fireplace and chimney were completed. Sheet rock blocking was being installed in the main house. The yard was being organized and cleaned.


Tim Beaulieu entered the following on 17:49:49 Nov/18/2008:
Weather Conditions:Sunny and Clear high in the mid 60's
Date
:
November 17, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Danny Tracy, Rolando Nunez, Pastor T, Jose B
Subcontractors on site: Big Horn-11
Visitors: No visitors today
Equipment Used: The fork lift was on site and used for 1 hour to move materials
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The great room chimney was being installed and is now above the roof line. Foam blocking was installed in the main house gable wall. Blocking was being installed in the garage. The Palmetto Bluff review board approved the Hardscape and grading plan. We have requested to move silt fences out to the property line and remove tree protection in areas that will be effected by retaining walls. Brick work was being completed on the front porch band. Rafter tails were being installed on the front porch.


Tim Beaulieu entered the following on 17:44:59 Nov/18/2008:
Weather Conditions:Overcast light AM rains
Date
:
November 14, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Danny Tracy, Pastor T. Jose B, Rolando Nunez
Subcontractors on site: Big Horn-11, JTS Construction-2, CCS-2
Visitors: The owners were on site to go over HVAC lay out
Equipment Used: The fork lift was on site but not used
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time
Work Completed or Work in Progress notes: HVAC lay out was conducted. The hall in the 2nd floor of the main house will drop down 3 feet. The master closet will have drop ceiling. Height will be determined by Joe once ducting requirements are determined. The storage room wall will be furred out exact dimensions are to be determined. A floor will be added above the great room ceiling to house mechanical equipment Brick work was ongoing around the side and rear porch. Rafter tails were being installed on the main gable. Electrical lay out was worked on in the kitchen. Exterior siding and trim take offs were completed and MMC is providing proposals.


Tim Beaulieu entered the following on 17:04:44 Nov/13/2008:
Weather Conditions:Overcast through out the day
Date
:
November 13, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Danny Tracy, Pastor T, Jose B, Rolando Nunez
Subcontractors on site: Big Horn Construction-14. JTS Construction-2, MMC-1
Visitors: No visitors today
Equipment Used: The BTV fork lift was on site and used for 1 hour.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Rear gable dormers were completed today. Side porch framing was underway and is 80 percent completed. The great room fireplace was being installed. Pocket doors were being framed in the master bedroom. Felt and window flashing was being installed on the main house. V groove cypress was being primed. Foam blocking was installed in the garage and garage bonus room. Picture and mirror blocking was being installed in the main house in the foyer.


Tim Beaulieu entered the following on 16:52:50 Nov/12/2008:
Memo:
111208
The rear porch columns were removed today by MMC. They will 
spend two days in the mill and then return for installation.


Tim Beaulieu entered the following on 16:49:50 Nov/12/2008:
Weather Conditions:Sunny and clear high in the upper 60's
Date
:
November 12, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Jose B, Danny Tracy, Rolando Nunez, Pastor T
Subcontractors on site: Big Horn-12, JTS Construction-2, MMC-3, Year Round Pool-6
Visitors: The owners were on site today to view progress
Equipment Used: BTV Fork lift was on site and used for 1 hour to move material.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Main gable sheathing was being installed. The rear porch rafter tails installation was underway and completed. Plumbing was completed on the pool. Blocking was installed in the garage bonus room. Brick work was being completed around the rear porch. The front porch beams and columns were installed. V Groove cypress was being primed. Electrical light fixture was worked on is 50 percent completed.


Tim Beaulieu entered the following on 18:51:48 Nov/11/2008:
Weather Conditions:Sunny and clear, low 70's
Date
:
November 11, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Jose B, Danny Tracy, Pastor T, Rolando Nunez
Subcontractors on site: Big Horn Construction-14, JTS Construction-2, Year Round Pool-6
Visitors: No visitors today
Equipment Used: Grist Equipment was on site today to service the fork lift. The fork lift was not used today.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Garage change order wall removal was completed today. Rafter tails were being installed on the main gable. Deck framing was underway on the side porch. The great room fireplace was being erected. Pocket doors in the main house were being framed. The master shower was framed and is completed. Electrical was being laid out and will be verified by the owners prior to installation. Concrete was pour in the front of the house for the brick work base. HVAC requirments were discussed with the home owners.


Tim Beaulieu entered the following on 15:35:27 Nov/10/2008:
Weather Conditions:Sunny and clear high in the low 70's
Date
:
November 10, 2008
Employees Working on site: Tim Beaulieu, Danny Tracy, Nicolas, Rolando Nunez, Gerson Morales, Jose B, Pastor T
Subcontractors on site: Big Horn Construction-10, Year Round Pool-8
Visitors: The home owners were on site today to go over showers and blocking for pictures and mirrors.
Equipment Used: The fork lift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Add door to bonus room apartment corner for closet. The door will be a 2/0 opening.
Work Completed or Work in Progress notes: Main gable roof sheathing is underway. Form boards were removed from the pools concrete work. Tile was being installed on the pool. The side porch is being framed and is nearing completion. Pickup framing was being completed in the garage bonus room. The ceiling was dropped in the garage stair well to accommodate 1 air handler. The closet in the master bath room was changed so it is now in the water closet. The closet will no longer have a door and will be open shelving. Staging was erected around the garage. Felt paper and vinyl was installed on the garage. The great rooms fire place had the arch installed today.


Tim Beaulieu entered the following on 15:25:34 Nov/07/2008:
Weather Conditions:Sunny and clear high in the upper 70's
Date
:
November 07, 2008
Employees Working on site: Tim Beaulieu, Pastor T, Dan M, Greg Barber, Danny Tracy, Gerson Morales, Nicholas, Rolando Nunez, Jose B,
Subcontractors on site: Big Horn 12
Visitors: David Sneddon was on site to walk thru the site. HVAC layout was discussed. A meeting needs to be scheduled for next week with CCS, BTV and owners.
Equipment Used: The BTV forklift was on site but not used. The dump truck was on site for the entire day.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: David would like to remove the corners framed in the garage bonus room.
Work Completed or Work in Progress notes: Main gable framing was completed. Sheathing will be installed on Monday. Temp stairs were installed in the main house to the 2nd floor. Staging was erected around the garage. Felt and window flashing was being installed on the garage. Temp plywood was installed on all decks. The outdoor fireplace and chimney was acid washed.


Tim Beaulieu entered the following on 16:21:21 Nov/06/2008:
Weather Conditions:Sunny and clear, Mid to high 70's in PM
Date
:
November 06, 2008
Employees Working on site: Greb Barber, Nicholas, Pastor, Gerson Morales, Rolando Nunez, Jose B, Tim Beaulieu, Danny Tracy
Subcontractors on site: Big Horn Construction-12, Year Round Pool-11
Visitors: The home owners were onsite today
Equipment Used: The forklift was on site and used for 1 hour to unload scaffold and plywood. The dump truck was on site and used for 4 hours to transport materials and staging.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Main gable framing was completed and plywood sheathing was being installed. Scaffolding was delivered and being staged around the garage. Plywood was delivered and will be used on the porches. Gunite was shot in the pool. The pools concrete work was completed today. Temp stairs and handrails were installed the garages 2nd floor. MMC is fabricating temp stairs for the main house and will be delivered in the AM.


Tim Beaulieu entered the following on 16:15:35 Nov/06/2008:
Weather Conditions:Sunny and Clear Low 70's
Date
:
November 05, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Rolando Nunez
Subcontractors on site: Big Horn-12, Year Round Pool-7
Visitors: The home owners were on site
Equipment Used: The BTV forklift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Main gable roof framing is underway and nearing completion. The pools rebar was being installed. The pool was inspected and approved for concrete. The garage was being wrapped with felt. Rafter tails were being installed on the rear porch. T&G soffit material was being install on the rear porches roof.


Tim Beaulieu entered the following on 12:48:02 Nov/05/2008:
Weather Conditions:Low 60's, Light rain
Date
:
November 04, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Rolando Nunez
Subcontractors on site: Big Horn Construction-10, Year Round Pool-8
Visitors: No visitors today
Equipment Used: The fork lift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The chimmeny detail on the current drawings is not the same as Oldfield. Pictures of Oldfield were taken and given to the mason to reproduce same.
Work Completed or Work in Progress notes: Great room gable roof framing is on going. Pool form work is on going. Pool rough plumbing was completed and pressure put onto the system. Rear porch rafters were being installed. The outdoor fireplace chimmeny was completed up to the top detail.


Tim Beaulieu entered the following on 17:46:51 Nov/03/2008:
Weather Conditions:Low 60's, Overcast and light rain
Date
:
November 03, 2008
Employees Working on site: Tim Beaulieu, Rolando Nunez
Subcontractors on site: Big Horn-12, Year Round Pool-5
Visitors: No visitors today
Equipment Used: The BTV forklift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The main gable roof framing was worked on today. 95 percent of all rafter were installed. The garage was being flashed and wrapped with felt. Year Round Pool was installing rebar and completed form work. All rough in pool plubming work was completed today. The rear porch rafter tails were installed today. Borate treatment was schedule for 17NOV08.


Tim Beaulieu entered the following on 09:31:38 Nov/03/2008:
Weather Conditions:Sunny and clear in PM, High in the upper 60's
Date
:
October 31, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Roland Nunez
Subcontractors on site: Big Horn-12, Year Round Pool-4
Visitors: No visitors today
Equipment Used: The BTV fork lift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The rear porch roof and ceiling framing was completed. Sheathing and decrotive tails still need to be installed. Felt and flashing was being installed on the garage and bonus room. The main gable roof framing was started and is 25 percent completed. The rear porches fireplace had conduits for the tv installed. The great room fireplace fire box was being constructed.


Tim Beaulieu entered the following on 09:27:43 Nov/03/2008:
Weather Conditions:Sunny and Clear high in the mid 60's
Date
:
October 30, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Rolando Nunez
Subcontractors on site: Big Horn-10, Year Round Pool-6
Visitors: No visitors today
Equipment Used: THe fork lift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Rear porch ceiling and roof framing was underway. The pool rough plumbing was being installed. The garage was being wrapped with felt and the RO's were being flashed.


Tim Beaulieu entered the following on 07:00:52 Oct/30/2008:
Weather Conditions:Sunny and clear high in the low 60's
Date
:
October 29, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Rolando Nunez
Subcontractors on site: Big Horn-10, JTS Construction-1, Year Round Pool-8
Visitors: David Sneddon was on site today to view progress.
Equipment Used: The forklift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The pool was being excavated. Rear porch rafters were being installed. Blocking was being installed in the garage apartment. Window and door RO's were being verified and flashed with window wrap. The great room fireplace had the fire boxes rear wall installed.


Tim Beaulieu entered the following on 06:56:11 Oct/30/2008:
Weather Conditions:Sunny and Clear High in the low 60's
Date
:
October 28, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Rolando Nunez
Subcontractors on site: Big Horn-10
Visitors: No visitors today
Equipment Used: The forklift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Rear porch beam setting and ceiling framing is underway. The window RO's were being wrapped with window wrap. The jobsite was cleaned and organized. The pool was being laided out.


Tim Beaulieu entered the following on 19:02:28 Oct/27/2008:
Memo:
October 27, 2008 

Year Round Pool was on site for a preconstruction meeting. 
Pool Construction will begin on Wednesday and all heavy 
equipment will be finished in the area on Thursday. Side 
porch framing will resume at that time. 


Tim Beaulieu entered the following on 18:57:57 Oct/27/2008:
Weather Conditions:Sunny and clear, Windy in PM
Date
:
October 27, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales
Subcontractors on site: MMC-1, JTS Construction-1, Big Horn-10
Visitors: The home owners were on site today
Equipment Used: The forklift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report
Work Completed or Work in Progress notes: Window RO's were being wrapped. The rear porch roof framing and ceiling joist were being installed. The outdoor fireplace was being constructed and is 24 brick courses high. Thompsons water seal was applied to the 2nd floor of the main house. Window RO's were being verified.


Tim Beaulieu entered the following on 16:36:40 Oct/26/2008:
Weather Conditions:Heavy rains at time, Mid 60's
Date
:
October 24, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-7
Visitors: No visitors today
Equipment Used: The BTV forklift was on site but not used
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The garage stairs framing is underway. Fireplace work has been delayed due to heavy rains. Work will resume on Saturday.


Tim Beaulieu entered the following on 17:32:19 Oct/23/2008:
Weather Conditions:Cloudy, mid 60's
Date
:
October 23, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: JTS Construction-1, Big Horn-12
Visitors: The home owners were on site
Equipment Used: The Bay Ten fork lift was on site but not used.
Urgent Items and Equipment Needed
:
The rear porch square post
Possible Change Order Items: David stated that the rear porches post were the wrong size. The current post are 12x12 as specified on the plans. David stated that the framer in I should go to the Oldfield house to look at the detail he wants. The post on the rear porch are 8x8's. All post in Palmetto Bluff have been installed and will need to be removed ans sent to MMC to be milled down to 8x8 and reinstalled.
Work Completed or Work in Progress notes: Fire place installation is on going. The rear porch post and beams were installed. Blocking was installed in the main house. Current plans were being reviewed for changes and a schedule was being constructed. The pool work is schedule to begin on Wednesday.


Tim Beaulieu entered the following on 14:54:14 Oct/22/2008:
Weather Conditions:Sunny and Clear
Date
:
October 22, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-11, PGP&A-2
Visitors: The Home Owners were on site today.
Equipment Used: One BTV forklift was on site but not used.
Urgent Items and Equipment Needed
:
David was on site today and stated that the fireplaces were the wrong sizes. It is my understanding that the fireplace were previously laid out and approved. David stated that he told me that the outdoor fireplace was to be the same size as the fireplace on the inside the great room. David was advised to take all changes to his meeting with Hunter and Grandy so all changes would be on the prints. This change never was added to the prints.
Possible Change Order Items: Hunter needs to draw the brick detail and wall removal on the rear porch.
Work Completed or Work in Progress notes: Blocking was being installed in the main house. Gas lines were installed in the outdoor and great room fire place. Deck framing was ongoing on the rear porch. HLM 5000 was installed on the rear porch rim joist.


Tim Beaulieu entered the following on 18:54:47 Oct/21/2008:
Weather Conditions:Sunny and Clear
Date
:
October 21, 2008
Employees Working on site: Tim Beaulieu, Duane Constantino
Subcontractors on site: Big Horn-9
Visitors: The Beaufort County Inspector was on site and approved the partial nailing inspection.
Equipment Used: The BTV fork lift is on site.
Urgent Items and Equipment Needed
:
The details need to be correctly drawn by Spivey and Woods, Duane has sent several drawing to Hunter but they still have been yet to be drawn correctly. The Sneddons have approved the pool qoute. The pool drawing have been submitted to the DRB and are pending for approval. The pool needs to dug as soon as possible. This has delayed the overall progress on the framing portion of the project.
Possible Change Order Items: The rear wall on the back porch David would like to remove and position the grill as it is in Oldfield.
Work Completed or Work in Progress notes: Blocking was installed for base boards. Fireplace brick work was being completed on both fireplaces. Window wrap was being installed on the RO's. A meeting with BTV and Big Horn took place and and the brick band detail was discussed.


Tim Beaulieu entered the following on 10:34:21 Oct/07/2008:
Weather Conditions:Sunny and clear
Date
:
October 06, 2008
Employees Working on site: Tim Beaulieu, Duane Constantino
Subcontractors on site: Big Horn-7
Visitors: Mr and Mrs Sneddon
Equipment Used: No Bay 10 Equipment on site at this time.
Urgent Items and Equipment Needed
:
The pool needs to be excavated as soon as possible, this delaying the 2nd floor framing
Possible Change Order Items: The garage dormer is to remain how it is framed. The solder course of brick is not support as drawn. Hunter will be contact and notified of possible solutions. The colums will now have brick base details added.
Work Completed or Work in Progress notes: The garage roof framing was underway. Bricks were being installed on the front of the piers on the front of house.


Tim Beaulieu entered the following on 10:29:56 Oct/07/2008:
Memo:
Site Report September 29-Octorber 3, 2008 

The main house framing was worked on. The main house 2nd 
floor framing can not be completed at this point until the 
pool is excavated. All decks are framed with the exception 
of the right hand portion of the main house. The deck was 
left off on this area to allow access to the pool. Brick 
work was completed on the deck piers. Numerous changes have 
taken place and are on the newest revised Drawings date 29 
September. The garage dormer was affected by these changes. 
The wall will need to be remove to accommodate the 
revision. The three windows to the left of the front door 
were changed to allow room for larger windows. This 
required reframing the area. 


Tim Beaulieu entered the following on 08:05:57 Sep/29/2008:
Weather Conditions:Sunny and Clear, High in the upper 70's
Date
:
September 26, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-11
Visitors: No visitors today
Equipment Used: No BTV Equipment on site at this time.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: The gable wall on the garage will not be reversed. The review board did not approve this. The dormer or the gaarage was approved to be larger. Exterior paint colors were not look at. Paint colors need to be established as soon as possible.
Work Completed or Work in Progress notes: Second floor framing is ongoing. The rafters were installed on the west portion of the main house. Block work was being completed around the main house porches.


Tim Beaulieu entered the following on 07:58:30 Sep/29/2008:
Weather Conditions:Sunny and Clear, High in the upper 70's
Date
:
September 25, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-11
Visitors: No visitors today
Equipment Used: No BTV equipment on site at this time.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report. All changes have been submitted to the Review Board for approval.
Work Completed or Work in Progress notes: The 2nd floor walls were being raised. Block work was being completed around the porches. This block work will carry the solder course of brick on the porches.


Tim Beaulieu entered the following on 07:53:02 Sep/25/2008:
Weather Conditions:Sunny and Clear, windy at times
Date
:
September 24, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-10
Visitors: No visitors on site
Equipment Used: No Bay 10 Equipment on site at this time.
Urgent Items and Equipment Needed
:
Approved prints from the the Palmetto Bluff review board are needed as soon as possible.
Possible Change Order Items: No known changes at this.
Work Completed or Work in Progress notes: The second floor was were laid out. All bottome plates were installed. Second floor walls were being constructed.


Tim Beaulieu entered the following on 16:08:36 Sep/23/2008:
Weather Conditions:Sunny and Clear, Mid 80's
Date
:
September 23, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Tim Reed Painting and Drywall-1
Visitors: No visitors today
Equipment Used: No BTV equipment on site at this time.
Urgent Items and Equipment Needed
:
We need the revised prints as soon as possible
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The 2nd floor framing is on going, all floor joist have been installed.


Tim Beaulieu entered the following on 07:26:28 Sep/23/2008:
Weather Conditions:Sunny and clear in the low 80's
Date
:
September 22, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-6
Visitors: Mrs Sneddon was on site to review prints
Equipment Used: No BTV equipment on site at this time.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: Mrs Sneddon recieved the revised drawing from Hunter today. She was on site to review. The drawing will be submitted to the Palmetto Bluff Review board for approval.
Work Completed or Work in Progress notes: The main house framing is underway. The second floor system is being installed.


Tim Beaulieu entered the following on 16:15:42 Sep/22/2008:
Weather Conditions:Sunny and Clear, High 70's
Date
:
September 19, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-6
Visitors: No visitors today
Equipment Used: No BTV equipment on site at this time.
Urgent Items and Equipment Needed
:
Revised drawing of all the changes are needed as soon as possible. All drawing will need to go to the town and the Review Board for approval.
Possible Change Order Items: DThe dormers on the main house will be revised. The main gable wall of the single car garage will be reversed and two dormers will be added. Pocket doors were added to the master closets. An additional french door was added to the master bedroom.
Work Completed or Work in Progress notes: Main house framing is on going. The first floor walls were being erected and sheathing installed. A tarp was placed over the garage roof to prevent water damage.


Tim Beaulieu entered the following on 17:27:01 Sep/18/2008:
Weather Conditions:Sunny and Clear
Date
:
September 15-18, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-6
Visitors: The home owners were on site today
Equipment Used: No Bay 10 Equipment on site at this time.
Urgent Items and Equipment Needed
:
We need a revised set of drawings submitted to the Building Department and to the review board
Possible Change Order Items: All changes have been previously documented and submitted to Spivey and Woods for revisions
Work Completed or Work in Progress notes: The main house framing is underway. The second floor framing will not be able to get completed until the pool excavation is completed. HSA completed the soil boring and the report is pending. Thomas Angell did not submitt his plans to the review board prior to the deadline this could cause a deley in the framing portion of the project.


Tim Beaulieu entered the following on 17:21:57 Sep/18/2008:
Memo:
Several changes have been submitted to Hunter for a revised 
set of drawings. 
Master closets have been changed to pocket doors. This 
change took place after the original walls were framed 
(091808) Completed 
Add an additional French door to the master bedroom and 
remove two windows. This change took place after the 
original wall was framed. (091708) 
Extend garage dormer between the two existing dormers above 
the two car garage. This change took place after the 
original roof was framed (091808) 
Add a exterior door to the 2 car garage. 
Move front door to the garage over to the right to allow 
room for a closet by the staircase. 
Add an additional covered porch off the master bedroom. 
The balcony in the main house by the stairs has a few 
concerns. Steel will be needed in this area to make this 
work. 
Remove existing roof framing off the single car garage and 
reverse gable walls. Two additional dormers will be added 
and the two car garage pitch will be carried across to the 
single car garage. 

Big Horn has been working on site and has 80 Percent of the 
garage completed and all of the first floor walls on the 
main house framed.


Tim Beaulieu entered the following on 13:39:17 Sep/15/2008:
Weather Conditions:Sunny and Clear
Date
:
September 11, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-8
Visitors: Home Owners, Jason of Year Round Pool, Thomas Angel
Equipment Used: No BTV equipment on site at this time.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: David has dropped off revision to the site.
Work Completed or Work in Progress notes: The forms were removed from the main house slab. Garage framing is on going. The main house walls were laid out. Sill plate were being istalled. A site meeting was conducted to discuss pool layout and grading. Thomas will submitt plans to the Palmetto Bluff Review Board as soon as the are completed. New paint colors arrived for the mock up the mock up will be repainted on Friday.


Tim Beaulieu entered the following on 13:33:45 Sep/15/2008:
Weather Conditions:Sunny and clear
Date
:
September 10, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-6
Visitors: No visitors today
Equipment Used: No BTV Equipment on site at this time.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: Garage framing is well underway. The 2nd floor is being framed. Hunter was called regarding the 2x4 walls in the main house. It has BTV common practice to frame all interior wall out of 2x6. The ceiling height is 12 feet.


Tim Beaulieu entered the following on 11:31:03 Sep/10/2008:
Weather Conditions:Sunny and clear
Date
:
September 09, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn Construction-12
Visitors: No visitors today
Equipment Used: No BTV equipment on site at this time.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The main house slab was completed today. Garage framing is on going. The entire second floor is now framed and rafters are being installed.


Tim Beaulieu entered the following on 13:25:35 Sep/09/2008:
Memo:
August 27 - September 08 2008 

August 

Framing is on going with the garage. We have identified an 
issue with the North wall of the garage. The out swing door 
will not open do to the specified rafter layout. The tails 
of the rafters will end up being to low and will interfere 
with the door opening. Hunter was notified of the 
condition. The main house slab is scheduled to be completed 
on Tuesday. A compaction test was passed on September 5. 
Pretreatment of the fill was sprayed on September 8. The 
Beaufort County inspection department was on site on 
September 8 and pass the slab work and has approved to 
pour. All interior wall were verified prior to pouring the 
slab. A fair amount of work went into protecting the site 
during the past week to prepare for the incoming storm. The 
main house fill is now completly dry and ready for the pour.


Tim Beaulieu entered the following on 16:05:21 Aug/27/2008:
Weather Conditions:Sunny and Clear, mid 80's
Date
:
August 26, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-9, Hunter Plumbing-3
Visitors: No visitors today
Equipment Used: The fork lift was on site but not used.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time.
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The garage walls were being framed. The walls will be raised mid day Wednesday. All rough in plubming was installed in the main house fill. The main house fill was compacted. A compaction test will be called for once all fill is completly dry. The grade beam were escavated and number 5 rebar was installed in the old peirs. Turn downs were also installed around the block wall at 32 inch centers.


Tim Beaulieu entered the following on 14:56:18 Aug/26/2008:
Weather Conditions:Sunny and Clear
Date
:
August 25, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-9, CCS-2
Visitors: No visitors today
Equipment Used: The fork lift was on site but not used
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time
Work Completed or Work in Progress notes: The main house had grade work completed. Form boards were completed around the block wall. Electrical conduits were installed in the main house fill. The garage bottom plates were installed. Top plates and headers are being cut.


Tim Beaulieu entered the following on 15:24:10 Aug/22/2008:
Weather Conditions:Heavy rains and winds through out the day
Date
:
August 22, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn
Visitors: No visitors today
Equipment Used: The fork lift was on site but not used.
Urgent Items and Equipment Needed
:
Heavy rains are delaying the foundation construction
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: The form board were completed around the foundation. The fill in the foundation is to wet to complete a final grading and compaction. Heavy rains and winds have sent the framer home after a half day.


Tim Beaulieu entered the following on 15:06:21 Aug/21/2008:
Weather Conditions:Heavy rain and Wind
Date
:
August 21, 2008
Employees Working on site: Tim Beaulieu, Pastor T, Gerson Morales
Subcontractors on site: Big Horn-9, RWK Sub-Contracting-1
Visitors: Thomas Angell
Equipment Used: The fork lift was on site but not used
Urgent Items and Equipment Needed
:
Heavy Rains have delayed work
Possible Change Order Items: No known changes at this time
Work Completed or Work in Progress notes: Half day was worked today on the foundation. Heavy rain has delay all site work at this time.


Tim Beaulieu entered the following on 15:01:19 Aug/21/2008:
Weather Conditions:Heavy rain at times
Date
:
August 20, 2008
Employees Working on site: Tim Beaulieu, Gerson Morales, Pastor T.
Subcontractors on site: RWK Sub-Contracting, Survey Consultants-2, Big Horn-10, Hunter Plumbing-3
Visitors: No visitors today
Equipment Used: The fork lift was on site and used for 2 hours to move materials
Urgent Items and Equipment Needed
:
Heavy rain and wind is delaying the foundation
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: 4 blocks have now been removed from the entire foundation. The surveyors have shot top of form and will produce a report. Form boards were installed around the entire foundation. Fill was being compacted on the dust cap. Electrical conduits were roughed in. Tree protection was being isntalled around the property.


Tim Beaulieu entered the following on 10:34:14 Aug/20/2008:
Weather Conditions:Sunny and Clear
Date
:
August 19, 2008
Employees Working on site: Tim Beaulieu, Pastor, Gerson Morales
Subcontractors on site: RWK Sub Contracting-1, Big Horn-9
Visitors: No visitors today
Equipment Used: The fork lift and was on site and used for 1 hour to move materials.
Urgent Items and Equipment Needed
:
The house will be very difficult to work around. Staging will not be able to be used on 1 entire side of the site. Tree protection has blocked all access to the side and front of the garage.
Possible Change Order Items: The foundation is going to be a slab. Four block will be removed from the exsisting block walls. The plumber and electricians have been notified of the changes and will begin rough in work on Wednesday. New foundation elevations are required. Spivey and Woods have been notified.
Work Completed or Work in Progress notes: Fifty percent of the block wall has been taken down four blocks. Tree protection, catle fencing, and silt fencing is sixty percent completed at this time. Indigo Run has been notified that 5 additional truck loads of fill are needed at that site.


Tim Beaulieu entered the following on 10:26:06 Aug/20/2008:
Weather Conditions:Sunny and clear
Date
:
August 18, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Big Horn-6, RWK Sub-contracting-1
Visitors: No visitors today
Equipment Used: The fork lift was on site and used for 2 hours
Urgent Items and Equipment Needed
:
Receive final word on approved elevation. The DRB has quoted 3 blocks be removed from the main house. Three blocks will not bring the house down to the approved height of 23'5"
Possible Change Order Items: All tree protection needs to be moved off the trees
Work Completed or Work in Progress notes: Tree protecting and silt fencing is being installed around the property to the Town of Blufftons protocol. Big Horn construction is mobilizing equipment and preparing for the framing portion of the job. The framing package for the garage was delivered to the site.


Tim Beaulieu entered the following on 20:43:22 Aug/14/2008:
Memo:


Sneddon Site Report August 11-14 2008

Bay Ten Staff working on site this week- Tim Beaulieu, 
Gerson Morales, Dan Burke, Pastor T.

Sub Contractors on site this week- RWK Sub-Contracting, Big 
Horn

Heavy PM rains through out the week.

Post foundation clean up work is completed. The site was 
inspected by Mike Raymond of the Town of Bluffton 
Environmental Department on August 13, 2008. Mike stated 
that the site meets the Palmetto Bluff requirements. The 
RPOD line was reestablished and silt fencing installed. All 
tree protection was installed 8 feet from the base of all 
required trees.  Fill was removed from around all trees and 
put behind the silt fence on the foundation side of the 
RPOD and setback lines. 


Palmetto Bluff Review Board was contacted several times on 
August 14, 2008.
Karen Dill was reached who stated the review board will not 
have their finding till August 15, 2008. Upon talking to 
Karen I questioned her about the location of the concrete 
wash down area. Karen stated she would discuss this with 
the members of the board. 

The mock up was moved closer to the house as requested by 
the Palmetto Bluff review board. 


Tim Beaulieu entered the following on 08:36:12 Aug/11/2008:
Memo:
Last log entry is from 28Jul08-08Aug08

The framer is schedule to being his portion of the project 
on 15Aug08.

No grade work can be completed till we have a grade plan 
established and approved. 


Tim Beaulieu entered the following on 08:36:05 Aug/11/2008:
Memo:
Last log entry is from 28Jul08-08Aug08

The framer is schedule to being his portion of the project 
on 15Aug08.

No grade work can be completed till we have a grade plan 
established and approved. 


Tim Beaulieu entered the following on 08:36:04 Aug/11/2008:
Memo:
Last log entry is from 28Jul08-08Aug08

The framer is schedule to being his portion of the project 
on 15Aug08.

No grade work can be completed till we have a grade plan 
established and approved. 


Tim Beaulieu entered the following on 08:34:04 Aug/11/2008:
Weather Conditions:Severe storms through out the week
Date
:
July 29-Aug 08
Employees Working on site: Duane Constantino, Nathan Klien, Tim Beaulieu
Subcontractors on site: Big Horn-1, 2 Brothers-1, Thomas Angell, Year Round Pool-2, Buds and Blooms-2
Visitors: No visitors today
Equipment Used: No equipment on site at this time.
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time.
Work Completed or Work in Progress notes: A site meeting was conducted on Thursday 080708 to discuss the need for retaining wall and tree well. Thomas Angell was selected to do complete this study and provide a grading and hardscapes plan. Thomas will submit to the review board for approval.


Tim Beaulieu entered the following on 14:59:47 Jul/29/2008:
Weather Conditions:Sunny and Clear, Late PM Storms
Date
:
July 28, 2008
Employees Working on site: Tim Beaulieu
Subcontractors on site: Jason of Year Round Pool, HSA-2
Visitors: No visitors today
Equipment Used: No Bay 10 Equipment on site at this time
Urgent Items and Equipment Needed
:
No foreseen issues or problems to report at this time
Possible Change Order Items: No known changes to report at this time
Work Completed or Work in Progress notes: A meeting was conducted with Year Round Pool. The need for retaining walls were discussed. Jason agrees that we should have retaining walls installed. Jason is going to work on a new deck design. The design will include a split level deck. HSA was on site to do core samples in the pool area.


Tim Beaulieu entered the following on 20:08:26 Jul/25/2008:
Weather Conditions:Sunny, Hot, Humid, High in the mid 90's
Date
:
July 25, 2008