DiIorio Phase 2 Daily Project Log
Add: Site report | Memo
Ed Ernst. entered the following on 17:03:12 Sep/18/2009:
Weather Conditions:Cloudy with Heavy Rain.
Date:09-18-09
Employees Working on site:
Ed E.
Greg B.
Dan B.
Rolando N.
Subcontractors on site:
Sturre Construction.
MMC.
Visitors:
No visitors today.
Equipment Used: Scaffold.
Urgent Items and Equipment Needed: Delay in obtaining additional Quartz Aggregate for decks.
Possible Change Order Items:
N//A.
Work Completed or Work in Progress notes:
Install leveling material on two front decks.
Complete carpentry repairs to service yard fence.
Confirm gate measurements.
Clean up job site.
Work on decks was curtailed due to heavy rain.
Ed Ernst entered the following on 20:32:57 Sep/17/2009:
Weather Conditions:Cloudy with Rain
Date:09-17-09
Employees Working on site:
Ed E.
Greg B.
Danny T.
Dan B.
Subcontractors on site:
Cuda Company.
Coastal Carolina Specialty.
Big Horn Construction.
Sturry Construction.
Visitors:
No visitors today
Equipment Used: Scaffold
Urgent Items and Equipment Needed: N/A
Possible Change Order Items:
N/A
Work Completed or Work in Progress notes:
Completed window trim.
Repaired stucco at window.
Caulked window.
Painted window and trim.
Installed deck coating at rear decks.
Installed switched WP outlet for stair rail lights.
Installed leveling base on two front decks.
Removed scaffold from front of house at window.
Erected scaffold at front porch.
Work on decks was suspended due to rain.
Cleaned site.
Ed Ernst entered the following on 14:52:49 Sep/16/2009:
Weather Conditions:Partly Cloudy
Date:09-16-09
Employees Working on site:
Ed E.
Greg B.
Danny T
Dan B.
Subcontractors on site:
Big Horn Construction.
Cuda Company
Sturry Construction
Visitors:
Linda Conkland
Equipment Used: Scaffold
Urgent Items and Equipment Needed: N/A
Possible Change Order Items:
N/A
Work Completed or Work in Progress notes:
Trim Window.
Apply deck primer on rear decks.
Install deck fabric on rear decks.
Reset gates.
Install new gate hinges. Weld hinges to gates.
Start prep work at front decks.
Clean/check rear drain.
Procure materials.
Touch up floors.
Patch stucco at window.
Patch stucco at entry columns.
Ed Ernst entered the following on 14:42:55 Sep/16/2009:
Weather Conditions:Partly Cloudy
Date:09-15-09
Employees Working on site:
Ed E.
Greg B.
Danny T.
Dan B.
Subcontractors on site:
Cuda Company
Visitors:
No visitors today
Equipment Used: Scaffold
Urgent Items and Equipment Needed: N/a
Possible Change Order Items:
N/A
Work Completed or Work in Progress notes:
Install protection.
Remove Window.
Install new window.
Mill trim for window.
Install forms at rear decks.
Clean and prep rear decks.
Procure material.
Check breakfast area electrical outlets. Breaker was off. There was no other problem.
Touch up floors.
Touch up wall at master bedroom fireplace.
Clean up.
Ed Ernst entered the following on 14:34:20 Sep/16/2009:
Weather Conditions:Partly Cloudy
Date:09-14-09
Employees Working on site:
Ed E.
Subcontractors on site:
Big Horn Construction
Visitors:
No visitors today
Equipment Used: Scaffold
Urgent Items and Equipment Needed: N/A
Possible Change Order Items:
N/A
Work Completed or Work in Progress notes:
NOTE:
Jobsite log is being activated with commencement of on site work by BTV in house crews.
Grout driveway entrance columns.