Todd Bowers 7/24/10 entered the following on 09:35:22 Jul/26/2010:
Memo:
Abbink Daily Report     7 24 10 

The weather was hot about 97 with no rain.

The forklift was used on site today.

BTV had 8 men on site today.
Todd B. Greg B. Danny T. Ed E. Francisco T. Pedro I. 
Martin H. Duane C.

Pour floor leveling compound in Opel’s office.
Install ceiling boards in family room.
Install outlets for appliances in the kitchen.
Install plywood sub floor in the exercise room.
Go over list of all needed part to complete the kitchen 
cabinets with Steve.

Downs view had 1 man on site today.
Install kitchen cabinets and make list of needed parts.

Webb had 4 men on site today.
Mix floor leveling compound.

Hans was on site today.

Todd Bowers




Todd Bowers 7/23/10 entered the following on 09:34:12 Jul/26/2010:
Memo:
Abbink Daily Report         7 23 10

The weather was hot about 96 with no rain.

The forklift was used on site today.

BTV had 7 men on site today.
Todd B. Greg B. Danny T. Ed E. Francisco T. Pedro I. 
Martin H.
Shim kitchen knee wall to accept panel.
Prep Opel’s office floor for floor leveling compound.
Install ½ panel to attic stair.
Install laundry room cabinets.
Remove stone at k nee wall to accept panel.
Install and finish sheet rock at kitchen knee wall.

Webb had 5 men on site today.
Prep upper porch ceiling for plywood.

Downs View had 1 man on site today.
Install kitchen cabinets.

MMC had 2 men on site today.
Install cabinets.

Todd Bowers


Todd Bowers 7/22/10 entered the following on 09:30:00 Jul/26/2010:
Memo:
Abbink Daily Report     7 22 10

The weather was hot about 95 with no rain.

The forklift was used on site today.

BTV had 7 men on site today.
Todd B. Greg B. Danny T. Ed E. Francisco T. Pedro I. 
Martin H.
Install heat wire for master shower bench.
Adjust thickness of kitchen wall for cabinet panel.
Install ¾ plywood to exercise room floor so that the 
carpet will finish out at the same height as the stone.
Move cabinets.
Clean the attic of dust and construction debris. 

CCS had 1 man on site today.
Install ELC transformers. 

Downs View had 1 man on site today.
Install kitchen cabinets.

ACC had 2 men on site today.
Paint EXT siding and trim.

Webb had 5 men on site today.
Shim beams and prep ceiling upper porch.

ACG had 5 men on site today.
Install gutters.

Todd Bowers



Todd Bowers 7/21/10 entered the following on 09:28:58 Jul/26/2010:
Memo:
Abbink Daily Report    7 21 10

The weather was hot about 95 with no rain.

The forklift was used on site today.

BTV had 7 men on site today.
Todd B. Greg B. Danny T. Ed E. Francisco T. Pedro I. 
Martin H.

Install living room ceiling boards.
Clean upper porch floor.
Prep upper porch floor for leveling.
Take water pipes though the roof for floor heat.
Site meeting.
Install metal for base board.

MMC had 2 men on site today.
Install cabinets.

CCS had 1 man on site today.
Install transformers for shades.

Webb had 5 men on site today.
Shim beam upper porch.

Downs View had 1 man on site today.
Install kitchen cabinets

ACG had 5 men on site today.
Install gutters

ACC had 2 men on site today..
Paint EXT siding and trim.

Site meeting 
Duane, Ed, Todd, Linda, Terry, Hans and Opel  

Todd Bowers


Todd Bowers 7/20/10 entered the following on 09:27:53 Jul/26/2010:
Memo:
Abbink Daily Report       7 20 10

The weather was hot about 96 with no rain.

The fork lift was used on site today.

BTV had 6 men on site today.
Greg B. Danny T. Ed E. Francisco T. Pedro I. Martin H.
Install round metal in the foyer.
Install ceiling board in the family room.
Go over porch flooring details.
Install metal for base boards.
Unload cabinets 
Start clean upper porch floor.

MMC had 2 men on site today.
Install cabinets.

Webb had 5 men on site today.
Beam wrap 1st floor porch.

ACC had 2 men on site today.
Painting in the front of the house.
	
Downs View had 1 man onsite today.
Install kitchen cabinets.

Todd Bowers















Todd Bowers 7/19/10 entered the following on 09:24:56 Jul/26/2010:
Memo:
Abbink Daily Report     7 19 10

The weather was hot about 95 with no rain.

The forklift was used on site today.

BTV had 7 men on site today.
Todd B. Danny T. Greg B. Pedro I. Martin H. Francisco T. 
Ed E.
Install Duarock in the kitchen for the back splash.
Install cabinets 
Install ELC boxes for cabinets.
Install metal for base board.
Unload cabinets.

Webb had 5 men on site today.
Wrap beam lower porch.

ACC had 2 men on site today.
Prep and paint siding and trim in the front of the house.

MMC had 2 men on site today.
Install cabinets.

Todd Bowers


Todd Bowers 7/17/10 entered the following on 10:32:00 Jul/19/2010:
Memo:
Abbink Daily Report    7 17 10

The weather was hot about 99 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Danny T. Greg B. Pedro I. Martin H. Ed E.
Install cabinets. 
Install appliances. 
Move water supply for dish washer.
Remove stones from upper porch.
Wash upper porch.

MMC had 2 men on site today.
Install cabinets 

Webb had 3 men on site today.
Wrap beam lower porch.

Todd Bowers


Todd Bowers 7/16/10 entered the following on 10:25:28 Jul/19/2010:
Memo:
Abbink Daily Report    7 16 10

The weather was hot about 96 with no rain.

The forklift was used on site today.

BTV had 7 men on site today.
Todd B. Ed E. Danny T. Greg B. Pedro H. Martin I. 
Francisco T.
Install appliances.
Install outlets for appliances.
Install cabinets.
Sand and prime walls in the laundry room and pull out 
closet at master.
Move supply for dish washer.

MMC had 2 men on site today.
Install cabinets.

Webb had 5 men on site today.
Install ceiling boards 1st floor porch. 
Shim beam and set posts. 

Todd Bowers






Todd Bowers 7/15/10 entered the following on 08:57:07 Jul/19/2010:
Memo:
Abbink Daily Report       7 15 10

The weather was hot about 96 with no rain.

The forklift was used on site today.

BTV had 7 men on site today.
Todd B. Ed E. Greg B Danny T. Pedro H. Martin I. Francisco 
T.

Ext Trim.
Install cabinets.
Install Appliances.
Install outlet in cabinets
Install flat metal for base board.
Install outlets for appliances

MMC had 3 men on site today.
Install cabinets.
Lay out stones 2nd floor porch.

Webb had 5 men on site today.
Install v groove ceiling on screen porch.
Shim beam and straighten post.

Todd Bowers



Todd Bowers 7/14/10 entered the following on 09:01:42 Jul/15/2010:
Memo:
Abbink Daily Report    7 14 10

The weather was hot about 96 with afternoon rain.

The forklift was used on site today.

BTV had 7 men on site today
Todd B. Danny T. Greg B. Ed E. Pedro I. Francisco T. 
Martin H.

Install cabinets.
Install outlets in the cabinets.
Red Gard master shower.
Prime sheet rock behind appliances.
Finish sheetrock behind cabinets and pull out closet in 
master.
Clean and organize garage.
Lay out stones and grid out the upper porch floor.
Lay out and check appliances to kitchen cabinets.

MMC had 2 men on site today.
Install cabinets in the master bed room.

Downs View had 1 man on site today.
Install kitchen cabinets.

Site meeting with Duane, Ed , Joe, Hans, Opel and Terry

Todd Bowers


Todd Bowers 7/13/10 entered the following on 09:00:47 Jul/15/2010:
Memo:
Abbink Daily Report     7 13 10

The weather was hot about 94 with afternoon rain

The forklift was used on site today.

BTV had 8 men on site today.
Todd B. Tim B. Danny T. Greg B. Francisco T. Martin H. 
Pedro I. Ed E.
Install cabinets.
Install outlets for cabinets.
Protect floors.
Grade work in the yard.
Shim and install plywood porch ceiling.

MMC had 2 men on site today
Install cabinets.

Webb had 5 men on site today.
Plywood and shim ceiling on the back porh.

G&D had 4 men on site today.
Install thresholds.

Todd Bowers


Todd Bowers 7/12/10 entered the following on 10:40:19 Jul/13/2010:
Memo:
Abbink Daily Report      7 12 10

The weather was hot about 95 with afternoon rain.

The forklift was used on site today.

BTV  had !0 men on site today.
Todd B Tim B. Greg B. Danny T. Francisco T. Nicolas R. 
Rolando N. Pedro I. Martin H. Ed E.

Install cabinets
Take down scaffolding
Remove stone from back porch so we can start the ceiling.
Lay out tile at master bath vanity.
EXT trim
Build walls behind pull out cabinet at master bed room.

G&D had 4 men on site today.
Grout family room, powder room, laundry room and mech. 
rooms
Install thresholds

Webb had 5 men on site today.
Siding and trim in the front of the house.
Install ceiling in the entry.
Shim ceiling back porch.

Downs View ha d1 man on site today.
Install kitchen cabinets.

Ricky Brown had 3 men on site today.
Install block work at the service yard wall.


Terry was on site today. 
I went over trim detail at the garage. 
There will not be a stucco band at the bottom of the 
garage.
The trim around the louver on the side of the garage will 
not go all the way to the bottom of the garage and will 
have a 2x12 at the bottom like the laundry window. 

Linda was on site today.
Ed and I went over the glass lay out in the kitchen,
She is going to draw the glass on paper and I will put 
that on plywood so every one can view it and conform the 
design.

Todd Bowers


Todd Bowers 7/10/10 entered the following on 17:33:51 Jul/12/2010:
Memo:
Abbink   Daily Report     7 10 10 

The weather was hot about 94 with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Greg B. Francisco T. Pedro I. Martin H.
Seal family room floor 
Install cabinets
Install outlets in cabinets.
EXT trim.
Install stone thresholds.

MMC had 2 men on site today.
Install cabinets.

Webb had 6 men on site today.
Install insulation in the ceiling over entry.
Install ceilings in the entry.
Install siding and trim bay window over entry.
Trim window at exercise window.

Downs View had 1 man on site today.
Install kitchen cabinets.

Todd Bowers


Todd Bowers 7/9/10 entered the following on 14:37:32 Jul/10/2010:
Memo:
Abbink Daily Report  7/9/10

The weather was hat about 94 with no ran..

The forklift was used on site today.

BTV had 9 men on site today.
Todd B. Ed E. Tim B. Greg B. Nicolas R. Rolando N. Pedro 
I. Martin H. Francisco T. 

Install cabinets. 
Lay out and map trees on lot for tank placement.
Install outlets in cabinets.
Clean and organize. 
Lay out thresholds.
Work on and lay out EXT trim details.


MMC had 3 men on site today.
Install cabinets.
Work on details around living room fire place.

G&D had 5 men on site today.
Install stone floors in the family room. Install mud set 
in master shower. Work tile in the down stairs bath room.

Clover Glass was on site to go over shower door details.

Webb had 6 men on site today. 
Install siding and ext trim. Set man door on the side of 
the garage.

Linda was on site today to go over placement of the 
kitchen cabinet hardware. She also gave us the location of 
the lights that are in the upper cabinets.

Todd Bowers


Todd Bowers 7/8/10 entered the following on 13:36:54 Jul/10/2010:
Memo:
Abbink Daily Report     7 7 10

The weather was nice about 96 with no rain.

The forklift was used on site today.

BTV had 9 men on site today.
Tim B. Danny T Greg B. Nicolas R. Rolando N. Martin I 
Pedro H. Todd B. Francisco T
Install cabinets, Locate outlets and ELC boxes and wires 
in cabinets, Hand pick stone for the floor. Lay out and 
install ply wood template for hand rail and glass.

CCS had 1 man on site.
Locate and install boxes in cabinets.

MMC had 2 men on site today.
Install cabinets.

ACC had 2 men on site today.
Prep and paint ext trim.

G&D had 3 men on site today.
Install stone flooring in the family room.

Webb had 6 men on site today.
Install freeze around garage, Install siding at the entry. 
Lay out ceiling over the entry.

Site meeting today with Duane, Linda, Ed, Terry and myself.

Todd Bowers


Todd Bowers 7/7/10 entered the following on 13:34:27 Jul/10/2010:
Memo:
Abbink Daily Report      7 8 10

The weather was hot about 95 with no rain.

The forklift was used on site today.

BTV had 9 men on site today.
Todd B. Danny T. Greg B. Nicolas R. Rolando N. Martin H. 
Pedro I. Francisco T. Ed E. 
Install cabinets. Install isolation membrane for the stone 
thresholds. Install ELC boxes in cabinets. 

CCS had 1 man on site today.
Install outlets in cabinets.

G&D had 3 men on site today.
Install stone floor in the family room.

ACC had 2 men on site today.
Prep and paint siding and EXT trim.

Webb had 6 men on site today.
Install siding and trim on the garage and entry.

Downs View had 1 man on site today.
Install kitchen cabinets.

MMC had 2 men on site today.
Install cabinets in master closets.

Todd Bowers


Todd Bowers 7/6/10 entered the following on 13:33:27 Jul/10/2010:
Memo:
Abbink Daily Report    7 6 10

The weather was nice about 92 with no rain.

The forklift was used on site today.

BTV had 9 men on site today.
Todd B. Danny T. Tim B. Greg B. Nicolas R. Rolando N. 
Francisco T. Martin I. Pedro H.
Lay out hand rails and make templates. Install cabinets. 
Install wood ceilings. Prime siding and ext trim. Patch 
sheetrock behind cabinets. Hand pick stone for the family 
room floor.

CCS had 3 man on site today.
Place outlets and ELC in cabinets. Work on boiler room 
manifold. 

MMC had 2 men on site today.
Install cabinets in Opel’s closet.

Downs view had 1 man on site today.
Install kitchen cabinets.

G&D had 3 men on site today. Install stone floors.

Webb had 6 men on site today.
Install EXT siding in the entry and freeze around the 
garage. Make copper pans for faux shutters.

Todd Bowers


Todd Bowers 7/5/10 entered the following on 13:32:10 Jul/10/2010:
Memo:
Abbink Daily Report     7 5 10

The weather was nice about 88 with no rain.

The forklift was used on site today.

BTV had  8 men on site today.
Todd B. Tim B. Greg B. Nicolas R. Rolando N. Francisco T. 
Martin H. Pedro I.
Install ceilings in the master bed room. Had pick stone 
for flooring. Lay out stairs hand rails and make 
templates. Prep showers for tile. 

CCS had 2 men on site today.
Install manifold in boiler room.

MMC had 1 man on site today. 
Install ceiling boards.

G&D had 2 men on site today.
Install tile flooring.

Todd Bowers


Todd Bowers 6/22/10 entered the following on 13:15:16 Jun/25/2010:
Memo:
Abbink Daily Report    6 22 10

The weather was hot about 96 with no rain.

The forklift and the man lift were used on site today.

BTV had 7 men on site today.
Todd B. Tim B. Nicolas R. Rolando N. Francisco Martin H. 
Pedro I
Install EXT trim.
Prep floors for stone.
Prep bath rooms for durarock.

The stone floor installers had  men on site today.
Install stone floors on the 2nd floor.

Todd Bowers

 


Todd Bowers 6/21/10 entered the following on 12:59:54 Jun/25/2010:
Memo:
Abbink Daily Report    6 21 10

The weather was hot about 95 with no rain.

The forklift and the man lift were used on site today

BTV had 7 men on site today.
Todd B. Tim B. Nicolas R. Rolando N. Francisco Martin H. 
Pedro I.
Install EXT trim. Prep floors for stone .Prep bath room 
for durarock.

The stone floor installer had 3 men on site .
Install stone on the 2nd floor.

Todd Bowers


Todd Bowers 6/7-19/10 entered the following on 11:17:47 Jun/25/2010:
Memo:
Abbink Daily Report    6 7-19 10

The weather has been hot in the high 90s with rain 1 day.

The forklift and the Terex man lift have been used on site 
every day.

BTV has had 9 to 10 men on site every day.
Todd B. Tim B. Danny T. Charlie W. Greg B. Nicolas R. 
Rolando N. Martin I. Pedro H..
Francesca T.

Work in progress or completed
EXT trim.  The right side of the house and master bed room 
windows is now about 98% complete.
The copper work on the drip and the work around the bay 
window over the entry is complete.
The beam wrap and column wrap has been milled and is ready 
to be installed.
The water feature mock up has been removed from the site.
New scaffolding has been installed at the back porch and 
the entry.
All of the stone flooring has been delivered to the site.
All of the stone flooring has been washed and sorted.
The Prep work for the stone flooring has been completed.
The stone flooring on the 2nd floor is being installed and 
should be complete today.
The grinding of high spots on the first floor has been 
started and should be comlete Monday.
The shower on the first floor is being prepped for tile 
and should be ready Monday.


CCS has had 1 to 3 men on site of and on as needed.
Work on lutron panels.
Install temp AC.

D and G tile installers have had 4 to 6 men on site. They 
started on 6/15/10.
They will have the 2nd floor complete today.

Linda’s carpet man came out and measured for the carpet.

The park has been cleaned and more mulch spread out were 
we have warn it down..

Todd Bowers


Todd Bowers 6/7-19/10 entered the following on 11:17:42 Jun/25/2010:
Memo:
Abbink Daily Report    6 7-19 10

The weather has been hot in the high 90s with rain 1 day.

The forklift and the Terex man lift have been used on site 
every day.

BTV has had 9 to 10 men on site every day.
Todd B. Tim B. Danny T. Charlie W. Greg B. Nicolas R. 
Rolando N. Martin I. Pedro H..
Francesca T.

Work in progress or completed
EXT trim.  The right side of the house and master bed room 
windows is now about 98% complete.
The copper work on the drip and the work around the bay 
window over the entry is complete.
The beam wrap and column wrap has been milled and is ready 
to be installed.
The water feature mock up has been removed from the site.
New scaffolding has been installed at the back porch and 
the entry.
All of the stone flooring has been delivered to the site.
All of the stone flooring has been washed and sorted.
The Prep work for the stone flooring has been completed.
The stone flooring on the 2nd floor is being installed and 
should be complete today.
The grinding of high spots on the first floor has been 
started and should be comlete Monday.
The shower on the first floor is being prepped for tile 
and should be ready Monday.


CCS has had 1 to 3 men on site of and on as needed.
Work on lutron panels.
Install temp AC.

D and G tile installers have had 4 to 6 men on site. They 
started on 6/15/10.
They will have the 2nd floor complete today.

Linda’s carpet man came out and measured for the carpet.

The park has been cleaned and more mulch spread out were 
we have warn it down..

Todd Bowers


Todd Bowers 6/6/10 entered the following on 17:07:43 Jun/07/2010:
Memo:
Abbink Daily Report   6 6 10

The weather was nice about 85 with no rain.

The forklift and the Terex man lift were used on site 
today.

BTV had 8 men on site today.
Todd B. Tim B. Danny T. Charlie W. Nicolas R. Rolando N. 
Martin I. Pedro H.
Install EXT trim. Shim ceiling in the family room. Wash 
stone for the floor installation project. Prep floors 
floor stone. 

CCS had 3 man on site today.
Wash stone for floor installation project. Add duct work 
to temp AC so that the unit will run more efficiently. 

HHIS had 1 man on site today. 
Check wires at window locations that have temp AC in them.

I spoke to Todd at Design Gal. The kitchen is scheduled to 
ship to us on 6/24/10 and the install will start the week 
after.

Todd Bowers


Todd Bowers 6/5/10 entered the following on 16:55:38 Jun/07/2010:
Memo:
Abbink Daily Report    6 5 10

The weather was hot about 94 with no rain. 

The forklift and the Terex man lift were used on site 
today.

BTV had 4 men on site today.
Todd B. Charlie W. Martin I. 
Install EXT trim. Cut shims. Clean and organize. Remove 
fountain mock up.

Todd Bowers


Todd Bowers 6/4/10 entered the following on 08:48:37 Jun/05/2010:
Memo:
Abbink Daily Report    6 4 10

The weather was good about 83 with late after noon rain.

The forklift and the Terex man lift were used on site 
today.

BTV had 8 men on site today.
Todd B. Tim B. Danny T. Nicolas R. Rolando N. Charlie W. 
Martin I. Pedro H.
Install EXT trim and siding. Prep floors for stone. Remove 
scaffolding. Unload stone flooring.

Ed E. had a stone floor installer on site today to quote 
the floor and shower installation.

Todd Bowers


Todd Bowers 6/3/10 entered the following on 08:41:08 Jun/05/2010:
Memo:
Abbink Daily Report   6 3 10

The weather was nice about 81 with no rain.

The forklift and the Terex man lift were used on site 
today.

BTV had 8 men on site today.
Todd B. Tim B. Danny T. Nicolas R. Rolando N. Charlie W. 
Martin I. Pedro H.
Install EXT trim and siding. Prep floors for stone. Prep 
site for stone flooring work.

Todd Bowers


Todd Bowers 6/2/10 entered the following on 08:33:59 Jun/05/2010:
Memo:
Abbink Daily Report     6 2 10

The weather was nice about 80 with no rain.

The forklift and Terex man lift were used on site today.

BTV had 10 men on site today.
Todd B. Tim B. Danny T.  Nicolas R. Rolando N. Charlie W. 
Pedro H. Martin I. Duane C. Ed E.
Install EXT siding. Prep Floors upstairs for stone. Site 
meeting.

Todd Bowers


Todd Bowers 6/1/10 entered the following on 08:02:24 Jun/02/2010:
Memo:
Abbink Daily Report   6 1 10

The weather was ok about 78 with morning rain.

The forklift and the Terex man lift were used on site 
today.

BTV had 7 men on site today.
Install durarock. Install EXT trim.

ACC had 3 men on site today.
Finish sheetrock.

Todd Bowers


Todd Bowers 5/31/10 entered the following on 07:57:14 Jun/02/2010:
Memo:
Abbink Daily Report    5 31 10

The weather was nice about 78 with no rain.

The forklift was used on site today.

BTV had 7 men on site today.
Install durarock all day.

ACC had 3 men on site today.
Finish sheetrock.

Todd Bowers


Todd Bowers 5 29 10 entered the following on 07:51:23 Jun/02/2010:
Memo:
Abbink Daily Report    5 29 10

The weather was nice about 79 with no rain.

The forklift and the Terex man lift were used on site 
today.

BTV had 3 men on site today.
Install EXT trim.

Todd Bowers


Todd Bowers 5/28/10 entered the following on 07:42:51 Jun/02/2010:
Memo:
Abbink Daily Report     5 28 10

The weather was nice about 78 with no rain.

The forklift and the Terex man lift were used on site 
today.

BTV had 6 men on site today.
Install EXT trim. Clean the park and remove all the 
trailers and dumpster. Install sheetrock metal. 

ACC had 3 men on site today. 
Finish sheetrock.

Todd Bowers


Todd Bowers 5/27/10 entered the following on 08:35:52 May/28/2010:
Memo:
Abbink Daily Report     5 27 10

The weather was nice about 78 with no rain.

The forklift and the Terex man lift were both used on site 
today.

BTV had 7 men on site today
Todd B. Tim B. Duane C. Charlie W. Danny T. Nicolas R. 
Rolando N.
Install EXT trim. Install sheetrock metal. Install 
durarock.

ACC had 3 men on site today.
Finish sheetrock.

Todd Bowers


Todd Bowers 5/26/10 entered the following on 16:52:01 May/26/2010:
Memo:
Abbink Daily report    5 26 10

The weather was nice about 74 with no rain.

The forklift and the Terex man lift was used on site today.

BTV had 5 men on site today. 
Install EXT trim. Install metal out side of master bed 
room to make panels. Grade the front of the house to keep 
water out of the garage. Clean the garage and set up wood 
shop in it.

ACC had 3 men on site today.
Finish sheetrock.

Carolina Blinds had 2 men on site to measure for blinds.

45 sheets of 1/4/  durarock was delivered today.

Todd Bowers


Todd Bowers 5/25/10 entered the following on 16:33:37 May/26/2010:
Memo:
Abbink Daily Report     5 25 10

The weather was bad with rain all day.
The forklift and the Terex man lift were used on site 
today.

BTV had 1 man on site today.
EXT trim.

ACC had 3 men on site today. 
Finish sheetrock.

Big horn had 4 men on site today.
Grind floor.

Todd Bowers


Todd Bowers 5/24/10 entered the following on 16:28:57 May/26/2010:
Memo:
Abbink Daily Report    5 24 10

The weather was bad about 72 and rain.

The forklift and Terex man lift were used on site today.

BTV had 2 men on site today.
Todd B. Danny T.
Install sheetrock metal Install EXT trim.

ACC had 3 men on site today.
Finish sheetrock.

Big Horn had 4 men on site today.
Grind concrete floor in the living room. This is a spot 
that got away from them while pouring the foundation. They 
came back and grinded the floor at no cost to Bay 10.

Todd Bowers


Todd Bowers 5/21/10 entered the following on 16:21:24 May/26/2010:
Memo:
Abbink Daily Report 5 21 10

The weather was nice about 77 with no rain.

The forklift and Terex man lift was used on site today.

BTV had 6 men on site today.
Todd B. Danny T. Tim B. Nicolas R. Rolando N.
Install floor heat mat in Opels office. EXT trim.

ACC had 3 men on site today.

Todd Bowers


Todd Bowers 5/20/10 entered the following on 16:20:25 May/26/2010:
Memo:
Abbink Daily Report     5 20 10

The weather was n ice about 77 with no rain. 

The forklift and the Terex man lift were used on site 
today.

BTV had 5 men on site today. 
Todd B. Tim B. Danny T. Nicolas R. Rolando N.
EXT trim. Install durarock 2nd floor.

ACC had 3 men on site today

Todd Bowers


Todd Bowers 5/19/10 entered the following on 16:17:57 May/26/2010:
Memo:
Abbink Daily Report     5 18 10

The weather was good about 75 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Tim B. Charlie W. Greg B. Nicolas R. Rolando N.
Install sheetrock metal. Install Durarock 2nd floor. 
Install EXT. trim.

ACC had 3 men on site today.
Sheetrock mud and fininsh walls.

Todd Bowers


Todd Bowers 5/18/10 entered the following on 16:16:44 May/26/2010:
Memo:
Abbink Daily Report     5 18 10

The weather was good about 75 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Tim B. Charlie W. Greg B. Nicolas R. Rolando N.
Install sheetrock metal. Install Durarock 2nd floor. 
Install EXT. trim.

ACC had 3 men on site today.
Sheetrock mud and fininsh walls.

Todd Bowers


Todd Bowers 5/17/10 entered the following on 16:15:05 May/26/2010:
Memo:
Abbink Daily Report  5 17/10

The weather was OK about 78 with rain off and on all day.

The forklift was used on site today.

BTV had 7 men on site today.
Todd B. Tim B. Greg B. Danny T. Charlie W. Nicolas R. 
Rolando N.
Install sheetrock metal. Install durorock 2nd floor. 
Install EXT trim at breeze way.

ACC had 2 men on site today finishing sheetrock.


Todd Bowers


Todd Bowers 5/14/10 entered the following on 09:21:26 May/18/2010:
Memo:
Abbink Daily Report      5 14 10

The weather was nice about 78 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B Tim B. Danny T. Greg B. Nicolas R. Rolando N.
Install sheetrock metal. Clean and tape off sheetrock 
metal. Install speekers.

CCS had 1 man on site today.
Help BTV.  

Todd Bowers


Todd Bowers 5/12/10 entered the following on 09:19:48 May/18/2010:
Memo:
Abbink Daily Report    5 13 10

The weather was nice about 75 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Install sheetrock metal. Remove plants from back of the 
house. 

CCS had 1 man on site today.
Remove plants from the back of the house.

Todd Bowers


Todd Bowers 5/13/10 entered the following on 09:18:15 May/18/2010:
Memo:
Abbink Daily Report    5 13 10

The weather was nice about 75 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Install sheetrock metal. Remove plants from back of the 
house. 

CCS had 1 man on site today.
Remove plants from the back of the house.

Todd Bowers


Todd Bowers 5/11/10 entered the following on 09:17:15 May/18/2010:
Memo:
Abbink Daily Report         5 11 10

The weather was nice about 74 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B Tim B Danny T. Charlie W. Nicolas R. Rolando N.
Install sheetrock metal. Clean house of all sheetrock 
dust. Install foam plugs in AC boots to keep dust out of 
the duct work. Brake up and remove old side walk in the 
front of the house. ( We saved the old concrete to use as 
drainage rock) Install grounds for copper in the front on 
the house so the roofer can complete the roofing. Install 
blocking for exhaust fans. 

OM Roofing had 1 man on site today.
Work on the 2 small flat roofs in the front of the house.

Danny with ACC was on site today to check on the sheetrock 
hangers and have the finishers start on Monday.

Todd Bowers




Todd Bowers 5/10/10 entered the following on 09:16:24 May/18/2010:
Memo:
Abbink Daily Report     5 10 10

The weather was nice about 74 with no rain.

The forklift was used on site today.

BTV had 6 men on site today
Todd B. Charlie W. Tim B Nicolas R. Rolando N.
Install metal for sheetrock. Change out broken skylight 
glass. Spray foam insulation in living room fire place. 
Clean windows and doors.

ACC had 6 men on site today 
Hang sheetrock

Todd Bowers


Todd Bowers 5/3-8/10 entered the following on 13:49:18 May/11/2010:
Memo:
Abbink Daily Report      5 3-8 10

The weather was nice last week with rain Tuesday. This 
rain did not effect us at all we worked inside.

The forklift was used on site all week.

BTV had 6 to 7 men on site all week.
Todd B. Charlie W. Danny T. Tim B. Greg B. Nicolas R. 
Rolando N.
Work preformed or in progress.
•	Install AC    Complete
•	Install plywood on soffits.  Complete
•	Install plywood in front hall. Complete
•	Install plywood in powder room. Complete
•	Install temp doors.  Complete
•	Complete sound insulation.  
•	Install grounds for sheet rock.  Complete
•	Install plywood on the back of studs in the living 
room fire place so we can spray foam against it.  Complete.
•	Adjust all outlets to make sure they work in the 
base board. Complete
•	Shim walls and door openings Complete.
•	Clean all walls of debris and glue.  Complete
•	Shim sky lights for sheetrock.   Complete
•	Hang sheetrock.
•	Install fresh air to living room fire place.  
Complete
•	Install sheetrock metal trim
•	Clean windows and doors of all sheetrock dust.
•	Lay out front entry landscape and check grades.  
Needs more work.


ACC had 6 men on site this week.
Hang sheetrock.

CCS had 1 to 2 men on site this week.
Check wiring. Help BTV with all the above items.

Allan Glassberg was on site Thursday to go over landscape 
and grade.

This past week has been very productive. 

Todd Bowers
  


Todd Bowers 4/29/10 entered the following on 10:30:17 May/03/2010:
Memo:
Abbink Daily Report    4 29 10

The weather was nice about 76 with no raun.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Danny T. Charlie W. Greg B. Nicolas R. Rolando N.
Install plywood. Install soffit plywood, Install sheetrock 
grounds, Build header in bed 2,
Cleans and prep for sheetrock.

CCS had 1 man on site today.
Work with BTV.

East Coast Ins. Had 3 men on site today
Install sound insulation. 


Suburban Propane had 1 man on site today.
Install valve for cook top.

Todd Bowers


Todd Bowers 4/28/10 entered the following on 10:12:49 May/03/2010:
Memo:
Abbink Daily Report     4 28 10

The weather was nice about 75 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Charlie W. Danny T. Greg B. Rolando N. Nicolas R.
Plywood soffits in Hans office, install temp door, protect 
laundry door, rip grounds for sheetrock.

East Coast Ins. Had 2 men on site to install sound 
insulation.

CCS had 2 men on site today.
Install DDC conduits, Check all wiring,

Todd Bowers


Todd Bowers 4/27/10 entered the following on 17:12:07 Apr/27/2010:
Memo:
Abbink Daily Report    4 27 10

The weather was nice about 72 with chance of late 
afternoon rain.

The forklift was used on site today.

BTV had 7 men on site today.
Todd B.DannyT. Tim B. Charlie W. Greg B. Nicolas R. 
Rolando N.
Remove 2 palm trees from the front of the house. Grade in 
the front of the house. Place water feature in place. 
Install plywood. Cut out wall for AV in the master bed 
room. Shim Doors. 

CCS had 2 men on site today.
Check wires. Work in the front of the house with BTV.

MMC had 1 man on site today. Sand entry door. Assist BTV 
with  tree removal

Linda was on site to look at the finish on the front door. 
She liked it.

Terry was on site today. General visit. 

Toby came out and did a window and door count for the 
hardware.

Todd Bowers.  


Todd Bowers 4/26/10 entered the following on 16:43:59 Apr/27/2010:
Memo:
Abbink Daily Report    4 26 10

The weather was nice about 85 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Danny T. Greg B. Charlie W. Nicolas R. Rolando N.
Install plywood, shim doors, Install metal for AC grills, 
shim soffits, dig for water feature, 

CCS had 2 men on site today.
Checking wiring,


The Abbinks came to the site late today with there 
granddaughter and liked all the progress they saw. It has 
been over a week cents they had been on site. They both 
liked the entry door and all the plywood on the walls. 

Todd Bowers


Todd Bowers 4/23/10 entered the following on 16:20:20 Apr/27/2010:
Memo:
Abbink Daily Report   4 23 10

The weather was nice about 80 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Greg B. Danny T. Charlie W. Nicolas R. Rolando N.
Install plywood, Shim doors, Install speaker cut outs, 
Paint HLM on skylight steel.

CCS had two men on site today.
Check wiring to make sure it is all good before we cover 
the walls.

Todd Bowers


Todd Bowers 4 22 10 entered the following on 15:56:27 Apr/23/2010:
Memo:
Abbink Daily Report    4 23 10

The weather was nice about 73 with no rain.

The forklift was used on site today.

BTV had 7 men on site today.
Todd B. Tim B Danny T. Charlie W. Greg B. Nicolas R. 
Rolando N.
Shim and plywood walls, Pull wires 

CCS had 2 men on site today.
Pull wires 

Todd Bowers


Todd Bowers 4/21/10 entered the following on 15:41:30 Apr/23/2010:
Memo:
Abbink Daily Report    4 21 10

The weather was nice about 72 with no rain.

The forklift was used on site today.

BTV had 7 men on site today. 
Todd B. Tim B Charlie W. Danny T. Greg B. Nicolas R. 
Rolando N.
Pull AV wires, Shim and plywood walls, Pull wires for 
track lights, Check door opening for plumb level and 
square.

Suburban Propane was on site to install keyed valves at 
the fire places.

MMC had 2 men on site today to sand entry door.

OM roofing was on site to tape off the roof over breeze 
way.

Todd Bowers


Todd Bowers 4/20/10 entered the following on 15:24:42 Apr/23/2010:
Memo:
Abbink Daily Report    4 20 10 

The weather was nice about 71 with no rain.

The forklift was used on site today

BTV had 6 men on site today.
Todd B. Tim B. Charlie W. Danny T. Nicolas R. Rolando N.
Blower door test, Pull AV wires, set up and check 
scaffolding for safety issues, set laundry room door, cut 
in skylights in breeze way.

CCS had 2 men on site today.
Pull wires, wire panels. 

Suburban Propane pull new gas line to living room fire 
place.

MMC had 2 men on site today to install the entry door.

Tony from the Leeds people was on site to due the blower 
door test. He said that he had never seen a house at the 
rough in have such low numbers.

Todd Bowers


Todd Bowers 4/19/10 entered the following on 14:58:43 Apr/23/2010:
Memo:
Abbink Daily Report    4 19 10

The weather was nice about 73 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Danny T. Nicolas R. Rolando N.  Charlie W. Duane C.
Shim and straighten walls. Caulk the outside of windows 
and doors. Foam skylights.Clean for blower door test.

CCS had 2 men on site today.
Pull wire and wire panels. 

MMC had 2 men on site to install laundry room and entry 
door.

Todd Bowers



Todd Bowers 4/13-14/10 entered the following on 14:38:42 Apr/21/2010:
Memo:
Abbink Daily Report     4  13-14 10

The weather was nice about 72 with no rain.

The forklift was used onsite both days.

BTV had 6 men on site both days.
Todd B. Tim B. Danny T. Charlie W. Nicolas R. Rolando N.
Install plywood on walls and soffits. Caulk and seal the 
house. Clean job.

CCS had 2 men on site both days. 
Wire panels

We were not able to work on site on the 15 and 16 due to 
gulf tournament

Todd Bowers. 


Todd Bowers 4/12/10 entered the following on 10:26:26 Apr/13/2010:
Memo:
Abbink Daily Report      4 12 10

The weather was nice about 73 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Install plywood. Plane studs and headers. Mark studs on 
the floor.

CCS had 4 men on site today.
Wire panels, Test and balance AC.

East Coast INS had 2 men on site today installing 
insulation in the foyer and powder bath ceiling.

Suburban Propane had 2 men on site installing gas piping.

Todd Bowers


Todd Bowers 4/10/10 entered the following on 10:19:58 Apr/13/2010:
Memo:
Abbink daily Report      1 10 10

The weather was nice about 73 with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Install plywood in the family room, dining room and the 
living room.

CCS had 2 men on site today. 
Wire panels.

Todd Bowers


Todd Bowers 4/9/10 entered the following on 09:26:14 Apr/13/2010:
Memo:
Abbink Daily Report         4 9 10

The weather was nice about 70 with no rain.

BTV had 6 men on site today.
Install plywood in the family room. Plane studs and 
header. Caulk and seal the house.

CCS had 4 men on site today.
Wire panels. Test and balance AC. 

Suburban Propane had 2 men on site today to install gas 
piping.

The sound insulation contract was given to East Coast INS 
today.
They are scheduled to insulate 4/22/10.

Todd Bowers


Todd Bowers 4/8/10 entered the following on 07:58:30 Apr/13/2010:
Memo:
Abbink Daily Report      4 8 10

The weather was nice about 70 with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Tim B. Nicolas R. Rolando N.
Install plywood in Opels office. Scrape foam.

CCS had 2 men on site today.
Wire panels.

Todd Bowers


Todd Bowers 4/7/10 entered the following on 07:47:28 Apr/13/2010:
Memo:
Abbink Daily Report  4 7 10

The weather was good with no rain.

The forklift was use on site today.

BTV had 4 men on site today.
Todd B. Tim B. Nicolas R. Rolando N.
Install plywood Opels Office. Scrape foam And caulk studs. 
Spray foam in the garage.

CCS had 4 men on site today.
Wire panels. Test and balance AC.

Site meeting.


Todd Bowers 4/7/10 entered the following on 07:36:48 Apr/08/2010:
Memo:
Abbink Daily Report    4 6 10

The weather was nice about 72 with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Tim B. Nicolas R. Rolando N.
Spay foam insulation. Pull AV wires. Install sheetrock 
blocking.

CCS had 2 men on site today 
Wire wires.
  

Todd Bowers


Toddd Bowers 4/6/10 entered the following on 07:23:53 Apr/08/2010:
Memo:
Abbink Daily Report    4 6 10

The weather was nice about 72 with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Tim B. Nicolas R. Rolando N.
Spay foam insulation. Pull AV wires. Install sheetrock 
blocking.

CCS had 2 men on site today 
Wire wires.
  

Todd Bowers


Todd Bowers 4/5/10 entered the following on 14:42:25 Apr/05/2010:
Memo:
The past 2 weeks have been very busy on site.


BTV has had 5 to 6 men on site.

CCS has ha 3 to 5 men on site.

The weather has been good.
The forklift has been use on site every day.

There has been on going ELC work. Tast an balance of the 
HVAC. 
The waiste an the water pipes have been tested.The can 
lights have been straighten and locked into place.The AV 
rough in has been completed. The entry an luanry room door 
has been reframed.We have fire stopped the house. The win 
screens for the fire places came in Spay close cell foam 
insulation.I have ha 2 companies come out to quote soun 
insulation. We got a framing and rough in inspection.I 
calle in today for a insulation inspection.We have 
installe sheetrock blocking.I odered the metal for the AC 
grills. Run spair conduits so we can still grt threw the 
house after it is closed up.

To Bowers


Todd Bowers 3 23 10 entered the following on 07:27:28 Mar/24/2010:
Memo:
Abbink  Daily Report    3 23 10

The weather was nice about 74 with no rain.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Tim B. Greg B. Danny T. Nicolas R. Rolando N.
Install sheet rock and fiber glass wall board in boiler 
room. Straighten walls. Insulate water pipes. Pull AV 
wires and set AV panels. Install conduit that contacts 
mech rooms.  

CCS had 5 men on site today.
Install fire stop at family room fire place. Insulate 
water pipes. Install conduit that connects the mech rooms 
together.

HHS had 2 men on site today.

Todd Bowers 


Todd Bowers 3/22/10 entered the following on 06:47:08 Mar/24/2010:
Memo:
Abbink Daily Report     3 22 10

The weather was nice about 70 with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Greg B. Danny T. Nicolas R. Rolando N.
Install added light outside exercise room. Install green 
field for steam mist controls. Installed drain pipes for 
steam mist. Insulate water pipes. Pull wire. Straighten 
walls. 

CCS had 4 men on site today.
Pull wire. Install duct wok.

Todd Bowers


Todd Bowes 3/19/10 entered the following on 07:10:12 Mar/22/2010:
Memo:
Abbink Daily Report    3 19 10

The weather was nice about 72 with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Tim B. Greg B. Nicolas R. Danny T.
Pull AV wire. Insulate water pipes. Lay out lights and 
beams in the family room.

CCS had 4 men on site today. Insulate pipes. Pull wire.

We cleaned up the lot next door and removed trash dumpster 
and all trailerstoday for a party on Saturday.

Todd Bowers


Todd Bowers 3/18/10 entered the following on 06:59:12 Mar/22/2010:
Memo:
Abbink Daily Report    3 18 10 

The weather was nice about 67 with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Greg B. Tim B. Nicolas R. Rolando N. Rolando N.
Pull AV wire. Insulate water pips. Pick up faming in the 
attic. Lay out beams in the family room.

CCS had 4 men on site today.
Pull wire. Set ELC boxes in the garage. Install conduit 
for floor heat sensors. Pull AV wire.

Todd Bowers


Todd Bowers 3 17 10 entered the following on 08:57:34 Mar/19/2010:
Memo:
Abbink Daily Report      3 17 10

The weather was cool about 55 with rain all afternoon.

The forklift was used on site today.

BTV had 6 men on site today.
Todd B. Tim B. Rolando N. Nicolas R. Ed E. Duane C.
Pull AV wires. Site meeting.

CCS had 2 men on site today.
Pull wire. 

HHS had 2 men on site today.

Linda C Terry R. and the Abbink’s where on site today fo 
the site meeting.

Todd Bowers


Todd Bowers 3 16 10 entered the following on 08:34:48 Mar/19/2010:
Memo:
Abbink Daily Report    3 16 10

The weather was nice about 60 with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Tim B. Danny T. Rolando N. Nicolas R.
Install conduit for DDC. Pump up water pipe. Pull wires.

CCS had 1 man on site today.
Pull wire.

HHS had 2 men on site today.

Todd Bowers


Todd Bowers 3 /15/20 entered the following on 16:19:08 Mar/15/2010:
Memo:
Abbink Daily Report    3 15 10

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Tim B. Danny T. Rolando N. Nicolas R.
Install J boxes and conduit and jet line. Put water on the 
water pipes.

CCS had 2 men on site today.
Pull wire.

HHS had 3 men on site today.

Harris Sales had 3 men on site today.

Todd Bowers




Todd Bowers 3 13 10 entered the following on 15:58:18 Mar/15/2010:
Memo:
Abbink Daily Report   3 13 10

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 6 men on site today. 
Todd B. Tim B. Greg B. Rolando N. Ed E. Duane C.
Set J boxes, install conduit and pull wire.

CCS had 2men on site today.
Work on wiring panels and pull wire.

Terry R. was on site today.

Todd Bowers


Todd Bowers 3/12/10 entered the following on 15:52:40 Mar/15/2010:
Memo:
Abbink Daily Report     3 12 10

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Greg B. Tim B.
Install conduit for DDC.

HHS had 2 men on site today.

Todd Bowers 


Todd Bowers 3/11/10 entered the following on 11:01:32 Mar/12/2010:
Memo:
Abbink Daily Report     3 11 10 

The weather was warm about 65 with rain all day.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Greg B. Tim B.
Install conduit for DDC. Set lights and lay out beams. Lay 
out panels out side master bath. Install copper water 
pipes for solar panels.

HHS had 3 men on site today.

Todd Bowers


Todd Bowers 3/10/10 entered the following on 07:32:49 Mar/11/2010:
Memo:
Abbink Daily Report    3 10 10

The weather was nice about 70 with no rain.
The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Tim B. Greg B. Nicolas R. Rolando N.
Install water pipes. Lay out for DDC conduit. Set lights 
and beams in Han’s office. Install pipes for solar panels. 
Pull AV wires.

CCS had 1 man on site today.
Pull AV wire.

HHS had 3 men on site today.

Hans and Opel were on site today for about 1 hour.

Todd Bowers


Todd Bowes entered the following on 08:37:25 Mar/10/2010:
Memo:
Abbink Daily Report     3 9 10

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Tim B. Greg B. Nicolas R.
Install water pipes. Change out master shower drain from 
2” to 3”. Set lights . Lay out beams in Opel’s office. 
Pull AV wire.

CCS had 1 man on site today.
Pull wire.

HHS had 3 men on site today.


We put air pressure on the water pipes today. 

Todd Bowers


Todd Bowers 3/8/10 entered the following on 08:22:24 Mar/10/2010:
Memo:
Abbink Daily Report    3 8 10

The weather was good about 60 with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Tim B. Greg B. Rolando N. Nicolas R.
Frame walls in the garage for ELC panels. Install water 
pipes. Pull wire. Set lights. Lay out beams in Opel’s 
office.

CCS had 1 man on site today. 
Pull wire.

HHS had 1 man on site today.

Todd Bowers


Todd Bowers 3/5/10 entered the following on 07:59:42 Mar/08/2010:
Memo:
Abbink Daily Report     3 5 10

The weather was cool about 55 with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Tim B. Greg B. Nicolas R. Rolando N.
Install water pipes in the garage. Set lights. Pull Wire 

HHS had 1 man on site today.

Todd Bowers


Todd Bowers 3/4/10 entered the following on 07:48:13 Mar/05/2010:
Memo:
Abbink Daily Report      3 4 10

The weather was cool about 55 with no rain.

The forklift was used on site today.

BTV 5 had men on site today.
Todd B. Tim B. Greg B. Nicolas R. Rolando N.
Set can lights. Framing in the attic for sheet rock. 
Install conduit for DDC. Reframe wall in the garage for 
DDC control box. Cut framing out of door to boiler room 
for water tanks. Work on water pipes in the garage.

CCS had 1 man on site today.
Wire panels.

HHS had 3 men on site today.

Todd Bowers


Todd Bowers 3/3/10 entered the following on 08:04:02 Mar/04/2010:
Memo:
Abbink Daily Report   3 3 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B Tim B. Nicolas R. Rolando N.
Framing in the attic for sheet rock. Site meeting. 

HHS had 3 men on site today.

Harris Sales had 2 men on site today.

Todd Bowers.


Todd Bowers 3/2/10 entered the following on 08:02:33 Mar/04/2010:
Memo:
Abbink Daily Report   3 2 10

The weather was cold with rain all day.

The forklift was used on site today.

BTV 3 men on site today.
Todd B. Nicolas R. Rolando N.
Install hose bids, Run conduit for DDC.

HHS had 2 men on site today.

Todd Bowers


Todd Bowers 3/1/10 entered the following on 07:56:59 Mar/04/2010:
Memo:
Abbink daily Report    3 1 10

The weather was good about 55 with no rain.

The forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R
Pull wire, lay out stairs with the hand rail guy.

CCS had 2 men on site today.
Pull wire 

The hand rail people had a man on site to measure the 
stairs today.

Todd Bowers


Todd Bowers 2/22-26/10 entered the following on 07:55:53 Mar/04/2010:
Memo:
Abbink Dailt Report    2 22-26 10

The weather was good most of the week with rain one day.

The forklift was used on site all week.

BTV had 5 men on site off and on all week.
We worked on plumbing, Setting lights installing conduit 
for DDC, and pulling wire.

CCS had 2 men on site all week. 
They worked on pulling wire 

Todd Bowers


Todd Bowers 2/15-19/10 entered the following on 07:37:02 Feb/23/2010:
Memo:
Abbink Daily Report    2 15 – 19 10

The weather was good most of the week with rain 1 day.

The fork lift was used all week.

BTV had an average of 3 men on site all week.
Todd B Nicolas R. Rolando N. Danny T. Tim B.
All of these men worked here off and on all week.
We worked on pulling wire and wiring light cans. Reframe 
master shower for new shower valves. Install master shower 
valves. Install copper water pipes to master shower. Cut 
wholes in the attic wall for the ERV exhaust and the cook 
top blower.

CCS had an average of 4 men on site this week.
Wire panels. Pull wire. Install copper pipes for solar 
panels. Install duct work for ERV and blower.

Todd Bowers


Todd Bowers 2/12/10 entered the following on 07:44:15 Feb/16/2010:
Memo:
Abbink Daily Report    2 12 10

The weather was cold with rain all day.

The forklift was used on site today.

BTV had 2 men on site today.
Rolando N. Nicolas R.
Pull low voltage wire 

CCS had 4 men on site today
Install duct work, run copper pipes for solar panels. Pull 
low voltage wires.

Todd Bowers


Todd Bowers 2/11/10 entered the following on 07:33:15 Feb/16/2010:
Memo:
Abbink Daily Report      2 11 10

The weather was cold with no rain.

BTV had 4 men on site today.
Todd B. Danny T. Rolando N. Nicolas R.
Pull low voltage wire

CCS had 4 men on site today.
Install duct work ,Run copper pipes for solar panels. Pull 
low voltage wire.

Todd Bowers


Todd Bowers 2/10/10 entered the following on 07:26:46 Feb/16/2010:
Memo:
Abbink Daily Report     2 10 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Rolando N. Nicolas R.
Wire lights, Pull low voltage wire, Site meeting.

CCS had 4 men on site today.
Install duct work, run copper pipes for solar panels, pull 
low voltage wire, wire panels

Todd Bowers


Todd Bowers 2/9/10 entered the following on 07:58:49 Feb/10/2010:
Memo:
Abbink Daily Report     2 9 10

The weather was cool with rain off and on all day.

The forklift was used on site today.

BTV had 4 men on site today.
Pull wire. Pull shade wire. Wire lights. Lay out master 
shower faucet.

CCS had 4 men on site today.
Pull wire. Pull shade wire. Install copper lines for 
garage AC. Start running copper pipe for solar panels. 

John with Suburban Propane was on site today to quote gas 
tank and gas lines.

Todd Bowers


Todd Bowers 2/8/10 entered the following on 07:46:47 Feb/09/2010:
Memo:
Abbink Daily Report       2 8 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Rolando N. Nicolas R.
Wire can lights. Pull home runs. Paint floor in guest bed 
room.

CCS had  5 men on site today.
Pull wire lay out ELC. install exhaust fan in powder bath. 

Build mock up of solar roof panal.

Todd Bowers


Todd Bowers 2/5/10 entered the following on 08:14:04 Feb/08/2010:
Memo:
Abbink Daily Report     2 5 10

The weather was cold with rain all day.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Danny T. Rolando N.
Pull wire and wire lights.

CCS had 4 men on site today.
Pull wire and inter wire into panels. Install duct work

Todd Bowers


Todd Bowers 2/3/10 entered the following on 14:01:17 Feb/05/2010:
Memo:
Abbink Daily Report     2 3 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Danny T. Rolando N.
Pull wire, Wire lights, site meeting.

CCS had 4 men on site today.
Pull wire, install duct work.

Site meeting 

Todd Bowers


Todd Bowers 2/4/10 entered the following on 13:54:31 Feb/05/2010:
Memo:
Abbink Daily Report   2 4 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Danny T. Rolando N.
Pull wire, wire lights, build platform over duct work in 
the attic.

CCS had 2 men on site today.
Pull wire, install duct work.

Todd Bowers


Todd Bowers 2/2/10 entered the following on 08:06:03 Feb/03/2010:
Memo:
Abbink Daily Report       2 2 10

The weather was cold with rain all day.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Danny T. Rolando N.
Wire lights and pull home runs.

CCS had 4 men on site today.
Install duct work, pull t stat wire, pull home runs and 
wire light cans.

Andrea Emanuele from Chubb was on site today.

I had a phone conversation with Linda about master bed 
room cabinet details.

Todd Bowers


Abbink Daily Report       2 2 10

The weather was cold with rain all day.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Danny T. Rolando N.
Wire lights and pull home runs.

CCS had 4 men on site today.
Install duct work, pull t stat wire, pull home runs and 
wire light cans.

Andrea Emanuele from Chubb was on site today.

I had a phone conversation with Linda about master bed 
room cabinet details.

Todd Bowers



Todd Bowers 2/1/10 entered the following on 07:45:54 Feb/02/2010:
Memo:
Abbink Daily Report      2 1 10

The weather was cold with no rain.

The fork lift was used on site today.

BTV had 3 men on site today.
Todd B. Danny T. Rolando N.
Install ELC boxes and run Home runs for lights.

CCS had 4 men on site today.
Pull home runs for lights and install duct work.

Todd  bowers


Todd Bowers 1/29/10 entered the following on 14:18:00 Feb/01/2010:
Memo:
Abbink Daily Report    1 29 10

The weather was cold with no rain.

The Forklift was used on site today.

BTV had 3 men on site today. 
Todd B. Dan B. Rolando N.
Install durarock. Pull wire. Clean site.

CCS had 4 men on site today.
Install duct work. Pull wire.

Todd Bowers


Todd Bowers 1/28/10 entered the following on 14:15:16 Feb/01/2010:
Memo:
Abbink Daily Report   1 28 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Dan B. Rolando N.
Install durarock on the 2nd floor. Pull wire. Install 
lights.

CCS had 4 men on site today.
Pull wire. Install duct work.

Todd Bowers


Todd Bowers 1/27/10 entered the following on 14:13:54 Feb/01/2010:
Memo:
Abbink Daily Report    1 27 10

The Weather was cold with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Dan B. Danny T. Rolando N.
Install lights on the porches. Pull wire. Cut and head for 
HVAC.

CCS had 4 men on site today. Install duct work. Pull wire.

Todd Bowers


Todd Bowers 1/26/10 entered the following on 14:11:54 Feb/01/2010:
Memo:
Abbink Daily Report    1 26 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Dan B. Rolando N.
Level floor in Hans office and install 1 layer of ¾ 
plywood. Pull wire. Straighten walls

CCS had 3 men on site today.
Install duct work and pull wire.

Todd Bowers


Todd Bowers 1/25/10 entered the following on 14:10:59 Feb/01/2010:
Memo:
Abbink Daily Report    1 25 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Install ac boot in the powder room. Cut whole in attic 
wall for ERV intake. Straighten walls. Pull wire.

CCS had 4 men on site today.
Install duct work. Pull wire.

Todd Bowers


Todd Bowers 1/22/10 entered the following on 14:09:32 Feb/01/2010:
Memo:
Abbink  Daily Report    1 22 10

The weather was cool with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Dan B. Rolando N.
Straiten walls Pull wire.

CCS had 4 men on site today.
Install duct work. Pull wire.

Todd Bowers 


Todd Bowers 1/21/10 entered the following on 14:08:43 Feb/01/2010:
Memo:
Abbink Daily Report   1 21 10

The weather was cool about 56 with rain all day. 

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Dan B. Rolando N.
Install steel in the pocket doors straighten walls. Pull 
wire.

CCS had 4 men on site today
Pull wire.

Todd Bowers


Todd Bowers 1/20/10 entered the following on 10:49:55 Jan/25/2010:
Memo:
Abbink Daily Report    1 20 10

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Dan B. Rolando N.
Drop ceiling in the hall out side of master closets so 
that the TA lights will fit.
Install pocket door tracks. Cut and head for HVAC. Pull 
wire with CCS. Site meeting

CCS had 5 men on site today. 
Install duct work. Pull wire. 

The roofer had 2 men on site today.
Install copper roofing over exercise room.

Todd Bowers


Todd Bowers 1/19/10 entered the following on 10:48:08 Jan/25/2010:
Memo:
Abbink Daily Report      1 19 10

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Dan B. Rolando N.
Install pocket door tracks. Cut and head for lights. 
Change out window in the family room. Install fire stop 
blocking.

CCS had 43 men on site today.
Pull wire. Install duct work.

Elevator lift systems had 3 men on site today.
Rough in wire and install hydraulic hose for the elevator.

The roofer had 2 men on site today.
Work on copper roof over the exercise room where we 
installed the new cricket.

Todd Bowers


Todd Bowers 1/18/10 entered the following on 10:46:55 Jan/25/2010:
Memo:
Abbink Daily Report    1 18 10

The weather was nice about 65 with no rain.

The fork lift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Nicolas R. Rolando N.
Worked on installing pocket door tracks. Pull wire with 
CCS.

CCS had 4 men on site today.
Install duct work. Pull wire.

Todd Bowers


Todd Bowers 1/15/10 entered the following on 10:08:53 Jan/25/2010:
Memo:
Abbink Daily Report      1 15 10

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Danny T. Dan B. Nicolas R. Rolando N.
Cut and head for HVAC. Pull wire with CCS.
 
We had to build a cricket over the exercise room to keep 
water away from the house.
This took 2 men about 4 hours.

CCS had 4 men on site today. 
Install duct work. Pull wire.

Todd Bowers 


Todd Bowers 1/15/10 entered the following on 10:08:47 Jan/25/2010:
Memo:
Abbink Daily Report      1 15 10

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Danny T. Dan B. Nicolas R. Rolando N.
Cut and head for HVAC. Pull wire with CCS.
 
We had to build a cricket over the exercise room to keep 
water away from the house.
This took 2 men about 4 hours.

CCS had 4 men on site today. 
Install duct work. Pull wire.

Todd Bowers 


Todd Bowers entered the following on 10:04:19 Jan/25/2010:
Memo:
Abbink Daily Report     1 14 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B, Danny T, Dan B,
We installed 2 layers of ¾ plywood to the floors of 
bedrooms 2 and 3.

CCS had 3 men on site today.
Install line sets, Install duct work, rough plumbing.

Todd Bowers


Todd Bowers entered the following on 10:03:20 Jan/25/2010:
Memo:
Abbink Daily Report     1 14 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B, Danny T, Dan B,
We installed 2 layers of ¾ plywood to the floors of 
bedrooms 2 and 3.

CCS had 3 men on site today.
Install line sets, Install duct work, rough plumbing.

Todd Bowers


Todd Bowers 1/13/10 entered the following on 16:16:56 Jan/13/2010:
Memo:
Abbink Daily Report    1 13 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Danny T. Dan B,
Mock up finish stair treads and risers. Head off for ac 
boots in the exercise room. Build wall and platform in the 
attic for ELC panels and elevator pump.

CCS had 2 men on site today.
Install duct work and run line sets.

Tom for Pestedge stone came out to measure the house.

Todd Bowers


Todd Bowers 1/12/10 entered the following on 16:07:43 Jan/13/2010:
Memo:
Abbink Daily Report      1 12 10

The weather was cold with no rain ( about 50).

The fork lift was used on site today.

BTV had 3 men on site today. 
Todd B. Danny T. Dan B.
Work on stairs, rough in plumbing.

CCS had 4 men on site today.
Rough in plumbing, install duct work, Install ELC panels.

Todd Bowers


Todd Bowers 1/11/10 entered the following on 16:06:49 Jan/13/2010:
Memo:
Abbink Daily Report   1 11 10

The weather was cold with no rain.

The fork lift was used on site today.

BTV had 3 men on site today.
Todd B, Danny T, Dan B.
Work on the stairs, rough in plumbing.

CCS had 4 men on site today.
Install duct work, install ELC panels, rough in plumbing.

The roofer had 4 men working on the unit next door. This 
project was completed today.

Todd Bowers


Todd Bowers 1/5-8/10 entered the following on 08:01:25 Jan/12/2010:
Memo:
Abbink Daily Report       1 5-8 10

The weather was cold with rain on the 7th .

BTV had 3 to 5 men on site for the past 4 day.
We have worked on building the stairs, installing cabinet 
blocking, rough in plumbing.

CCS has had 4 men on site for the past 4 days.
Rough in plumbing, install panels, install duct work.

The roofer has had 4 men on site working on the roof.

Todd Bowers


Todd Bowers 1/4/10 entered the following on 08:01:44 Jan/05/2010:
Memo:
Abbink Daily Report     1 4 10

The weather was cold with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Danny T. Dan B. Nicolas R. Rolando N.
Build stairs, rough in plumbing, insulate hall ceiling,

CCS had 1 man on site today. 
Rough in plumbing.

Roofer had 5 men on site today.

Todd Bowers


Todd Bowers 12/31/09 entered the following on 17:24:58 Dec/31/2009:
Memo:
Abbink Daily Report     !2 31 09

The weather was cool with morning rain.

The Forklift was used on site today.

BTV had 5 men on site today.
Todd B. Danny T. Dan B. Nicolas R. Rolando N.
Lay out and start the framing on the stairs. Install ELC 
boxes. The caulking of the studs was completed today. 

CCS had 3 men on site today. 
Rough in water pipes. Install duct work.

The roofers were called off because of the rain.

This looks like that will wrap up this year. I think that 
we have had a very productive year. The project is moving 
along very well. 

I am now going to go home and get some rest and come back 
next year ready to go.

Thanks and have a Happy New Year

Todd Bowers




Todd Bowers entered the following on 17:20:22 Dec/30/2009:
Memo:
Bbink Daily Report    12 30 09

The weather was cool with no rain.

The forklift was used on site today.

BTV had 5 men on site today.
Todd B. Danny T. Dan B. Nicolas R. Rolando N.
Caulk studs, Install ELC boxes, install fire blocking.

CCS had 2 men on site today. Rough in plumbing, Install 
panels.

The roofer had 4 men on site today. Install copper and 
shingles.

I ordered the Durarock and pan liner for the floors and 
showers today. I also ordered steel for the pocket doors.

Todd Bowers


Todd Bowers 12/29/09 entered the following on 16:14:31 Dec/29/2009:
Memo:
Abbink Daily Report    12 29 09

The weather was cold with no rain.

The Forklift was used on site today.

BTV had 2 men on site today.
Install ELC boxes.

CCS had 2 men on site today. 
Rough in plumbing and pull wire.

The roofer had 4 men on site today.
Install copper over the garage and nail shingles.

Todd Bowers


Todd Bowers 12/28/09 entered the following on 16:10:12 Dec/29/2009:
Memo:
Abbink Daily Report     12 28 09

The weather was cold with no rain.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Danny T. Dan B. 
Install ELC boxes

CCS had 2 men on site today.
Rough in plumbing, Pull wire.

The roofer had 4 men on site today. 
Install copper over the garage and nail shingles.

Todd Bowers


Todd Bowers 12/22/09 entered the following on 16:30:31 Dec/22/2009:
Memo:
Abbink Daily Report      12 22 09

The weather was cool about 65 with no rain.

The forklift was used on site today. 

BTV had 5 men on site today.
Todd B. Danny T. Dan B. Nicolas R. Rolando N.
Frame drop ceiling in the main hall. Install lights in the 
powder room and in the exercise room. Install blocking at 
the front door. Install foam board where panels are going 
and in main hall ceiling. Frame drop ceiling in Mech 
closet.  

CCS had 4 men on site today.
Install duct work. Install plumbing. Lay out outlets.

No roofers on site today.

Todd Bowers


Todd Bowers 12/21/09 entered the following on 16:13:26 Dec/21/2009:
Memo:
Abbimk Daily Report    12 21 09

The weather was cold about 52 with no rain,

The forklift was used on site today.

BTV had 4 men on site today.
Frame drop ceiling in the main hall. Insulate ceiling in 
the main hall. Caulk studs. Install foam board where 
panels are going to be installed. Finish sheet rock in DVA 
room.

CCS had 2 men on site today. 
Install duct work.

The roofers had 3 men on site today.
Install copper flashing and shingles 

Todd Bowers














Abbimk Daily Report    12 21 09

The weather was cold about 52 with no rain,

The forklift was used on site today.

BTV had 4 men on site today.
Frame drop ceiling in the main hall. Insulate ceiling in 
the main hall. Caulk studs. Install foam board where 
panels are going to be installed. Finish sheet rock in DVA 
room.

CCS had 2 men on site today. 
Install duct work.

The roofers had 3 men on site today.
Install copper flashing and shingles 

Todd Bowers







Abbimk Daily Report    12 21 09

The weather was cold about 52 with no rain,

The forklift was used on site today.

BTV had 4 men on site today.
Frame drop ceiling in the main hall. Insulate ceiling in 
the main hall. Caulk studs. Install foam board where 
panels are going to be installed. Finish sheet rock in DVA 
room.

CCS had 2 men on site today. 
Install duct work.

The roofers had 3 men on site today.
Install copper flashing and shingles 

Todd Bowers














Abbimk Daily Report    12 21 09

The weather was cold about 52 with no rain,

The forklift was used on site today.

BTV had 4 men on site today.
Frame drop ceiling in the main hall. Insulate ceiling in 
the main hall. Caulk studs. Install foam board where 
panels are going to be installed. Finish sheet rock in DVA 
room.

CCS had 2 men on site today. 
Install duct work.

The roofers had 3 men on site today.
Install copper flashing and shingles 

Todd Bowers






















Todd Bowers 12/18/09 entered the following on 15:56:31 Dec/21/2009:
Memo:
Abbink Daily Report     12 18 09

The weather was cold about 52 with rain all day,

The forklift was used on site today.

BTV had 4 men on site today.
Finish sheetrock in the DVA room. Frame walls for panels. 
Frame drop ceiling in main hall. Install insulation board 
in ceiling of main hall. Clean job.

CCS had 2 men on site today.
Install duct work.

AGA had 1 man on site today.
Frame for panels.

The weather did not allow the roofers to work. ! man was 
on site to put up some plastic over some places that where 
leaking.

Todd Bowers


Todd Bowers 12/17/09 entered the following on 15:08:15 Dec/18/2009:
Memo:
Abbink Daily Report   12 17 09

The weather was cool about 58 with no rain.

The forklift was used on site today.

BTV had 4 men on site today.
Todd B. Danny T. Dan B. Nicolas R.
Fire stop AC case. Frame for additional panels. Sheet rock 
mud in the DRV room. Drop ceiling in the hall. Caulk studs 
on EXT walls.

AGA had 1 man on site today.
Frame for panels and HVAC.

The roofer had 4 men on site today.
Install copper panels over porch.

Todd Bowers


Todd Bowers 12/16/09 entered the following on 10:06:42 Dec/17/2009:
Memo:
Abbink Daily Report  12 16 09

The weather was cool about 57 with no rain. 

The forklift was used on site today.

BTV had 3 men on site today.
Todd B. Danny T. Nicolas R.
Drop ceiling in the master bath room to make tile lay out 
work. Caulk studs on EXT walls. Site meeting. 

AGA had 1 man on site today.
Drop ceiling in the master bath room.

Todd Bowers


Todd Bowers 12/15/09 entered the following on 10:04:50 Dec/17/2009:
Memo:
Abbink Daily Report      12 15 09

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 3 men on site today.
Todd B Danny T. Jeff C.
Drop ceiling in master bath to work out with tile. Wrap 
house with felt. Build wall in the attic for ERV.

CCS had 4 men on site today.
Install duct work. Rough in plumbing. Install lights in 
the attic.

AGA had 1 man on site today.
Build wall in the attic for ERV. Wrap house with felt.

Todd Bowers


Todd Bowers 12/14/09 entered the following on 16:54:16 Dec/14/2009:
Memo:
Abbink Daily Report   12 14 09

The weather was nice with no rain.

The forklift was used on site today.

BTV had 2 men on site today.
Todd B. Jeff C. 
Install lights, Build AC platform, lower ceiling in bath 1 
to work out with tile, wrap house with felt, rough in 
plumbing,

CCS had 5 men on site today.
Install duct work, work out lay out of duct for the ERV 
rough in plumbing,

AGA wrap house with felt ,install copper flashing.

Todd Bowers


Todd Bowers 12/11/09 entered the following on 09:09:36 Dec/14/2009:
Memo:
Abbink Daily Report      12 11 09

The weather was cold and wet. Rain off and on all day.

The forklift was used on site today. 

BTV had 3 men on site today.
Todd B. Danny T. Jeff C.
Build round ceiling in bath 1,Install copper over drip 
EXT. Install lights in the family room. 

CCS had 4 men on site today.
Install lights in the attic. Install duct work. Rough in 
plumbing.

AGA had 1 man on site today.
Install copper flashing over drip EXT. 

Big Horn had 3 men on site today. 
Install lights in the family room. Work soffit in the 
family room.

Todd Bowers


Todd Bowers 12/11/09 entered the following on 09:09:35 Dec/14/2009:
Memo:
Abbink Daily Report      12 11 09

The weather was cold and wet. Rain off and on all day.

The forklift was used on site today. 

BTV had 3 men on site today.
Todd B. Danny T. Jeff C.
Build round ceiling in bath 1,Install copper over drip 
EXT. Install lights in the family room. 

CCS had 4 men on site today.
Install lights in the attic. Install duct work. Rough in 
plumbing.

AGA had 1 man on site today.
Install copper flashing over drip EXT. 

Big Horn had 3 men on site today. 
Install lights in the family room. Work soffit in the 
family room.

Todd Bowers


Todd Bowers 12/10/09 entered the following on 16:48:33 Dec/10/2009:
Memo:
Abbink Daily Report   12 10 09 

The weather was cool about 55 with morning rain.

The forklift was used on site today.

BTV had 2 men on site today.
Todd B. Danny T. 
EXT band, soffit work, lay out tile in bath 1, rough in 
plumbing, lay out lights in family room, 

Big Horn had 3 men on site today.
Install lights, work on soffits, hang sheet rock in DVA 
room.

CCS rough in plumbing, install duct work.

Vaught Con. had 1 man on site today.
EXT band.

AGA had 1 man on site today.
EXT band.

Todd Bowers


Todd Bowers 12/9/09 entered the following on 08:40:49 Dec/10/2009:
Memo:
Abbink Daily Report   12 9 09

The weather was warm about 68 with rain. I shut the job 
down at 4:00 because of the rain.

The forklift was used on site today,

BTV had 2 men on site today.
Todd B. Danny T.
Ext band, soffit work, rough in plumbing, site meeting,

AGA had 1 man on site today.
EXT band

Vaught Con. had 1 man on site today.
EXT band

CCS had 3 men on site today.
Duct work, rough in plumbing.

Big Horn had 3 men on site today.
Soffit work.

Todd Bowers


Todd Bowers 12/8/09 entered the following on 17:07:14 Dec/08/2009:
Memo:
Abbink Daily Report   12 8 09

The weather was cool about 62 with rain off and on all day.

The forklift was used on site today

BTV had 2 men on site today.
Todd B. Danny T.
Install EXT band, rough in plumbing, build soffits, work 
on shade pockets.

CCS had 2men on site today. 
Install duct work, rough in plumbing.

Vaught Con. had 1 man on site today.
Install EXT band.

Big Horn had 3 men on site today.
Install soffits, build platform for steam generator, 
install EXT band,

The roofing work has stopped until OM Roofing gets there 
insurance. I do not think that this will take more than a 
few days.

Todd Bowers


Todd Bowers 12/7/09 entered the following on 16:42:40 Dec/07/2009:
Memo:
Abbink Daily Report     12 7 09

The weather was nice about 65 with no rain.

The forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Rough in plumbing, build soffits, EXT. band.

CCS had 3 men on site today.
Install duct work, rough in plumbing.

Vaught Con. had 1 man on site today.
Install EXT. band at entry.

OM Roofing had 3 men on site today.
Install copper roof over porch.
There was a question  with OM Roofing insurance today. 
They will have to get this matter straightened out before 
they can complete the job.

Big Horn had 3 men on site today.
Build soffits, drop ceilings, Install EXT band.

Espy delivered the shingles today.

Sea Pines inspector was on site today and complemented on 
how good the site looked.

I called Building Specialty today. They need to add more 
fuel to the living room fire place. About 16”.

Todd Bowers




Todd Bowers 12/4/09 entered the following on 15:53:31 Dec/04/2009:
Memo:
Abbink Daily Report    12 4 09

The weather was cool about53 with light morning rain.

The forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Rough in plumbing, Build soffits. Clean up park for party.

CCS had 4 men on site today.
Rough in plumbing, install duct work, start up temp heat.

Big Horn had 3 men on site today.
Install soffits, Clean up park for party.

I spoke with Patty and Todd  with Design Galleria about 
delivering the kitchen in March.

The ice and water shield for the porch roof was delivered 
today.

The temp heat is up and running as of today.

We cleaned the park, spread mulch and removed the dumpster 
and all trailers today for the oyster roast this week end.

Todd Bowers


Todd Bowers 12/3/09 entered the following on 15:30:33 Dec/04/2009:
Memo:
Abbink Daily Report  12 3 09

The weather was cool about 60 with rain off and on all day.

The forklift was used on site today

BTV had 1 man on site today.
Todd B.
Rough in plumbing, build soffits.

CCS had 1 man on site today.
Rough in plumbing.

OM roofing had 3 men on site today.
Install copper drip

4 M Metal delivered the copper panels for the porch.

Big Horn had 3 men on site today.
Build soffits. Cut and head for HVAC.

Todd Bowers


Todd Bowers 12/2/09 entered the following on 12:12:09 Dec/04/2009:
Memo:
Abbink Daily Report   12 2 09

The weather was cool about 65 with no rain.

The forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Rough in plumbing, Install soffits cut and head for HVAC.

CCS had 3 men  on site today.
Install duct work, Rough in plumbing.

Big Horn had 3 men on site today.
Build soffit,Cut and head for HVAC,

Todd Bowers


Todd Bowers 12/1/09 entered the following on 07:39:51 Dec/02/2009:
Memo:
Abbink Daily Report      12 1 09

The weather was cool about 58 with no rain.

The forklift was used on site today.

BTV had 1 man on site today.
Todd B. 
Install plumbing, review plumbing fixtures, Install wall 
cap for DVA, install soffits, work on temp heating unit.

CCS had 3 men on site today.
Install duct work, install plumbing water pipe.

Big Horn had 3 men on site today.
Install soffits, install wall cap for DVA, build seat in 
master shower.

Todd Bowers


Todd Bowers 11/30/09 entered the following on 08:55:19 Dec/01/2009:
Memo:
Abbink Daily Report   11 30 09

The weather was nice about 70 with no rain.

The forklift was used on site today.

BTV had 1 man on site today.
Todd B. 
Install lights 2nd floor.

CCS had 2 men on site today.
Install duct work. Deliver temp AC.

Big Horn had 3 men on site today.
Install lights, cut and head for lights, work on soffits. 

Linda was on site today to look at master tub. I will get 
all the plumbing fixtures on site for the this weeks site 
meeting. We will go over all locations at that point.

Todd Bowers


Todd Bowers 11/25/09 entered the following on 15:50:30 Nov/25/2009:
Memo:
Abbink Daily Report     11 25 09

The weather was cool about 55 with rain off and on all day.

The forklift was used on site today.

BTV had 1 man on site today.
Todd B. 
Install lights in the master bedroom.

CCS had 2 men on site today.
Install duct work in the attic and start to hang the 5 ton 
unit in the attic.

Big Horn had 3 men on site today.
Install lights in the master bedroom. Move and add lights 
in Hans office.

Due to the Thanksgiving holiday the site will be closed 
Thursday and Friday.
I hope everyone has a good and safe holiday. 

Todd Bowers


Todd Bowers 11/24/09 entered the following on 15:40:47 Nov/25/2009:
Memo:
Abbink Daily Report   11 24 09

The weather was cool about 57 with no rain.

The forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
Rough in plumbing, install lights,

CCS had 1 man on site today.
Rough in plumbing.

 ACC had 2 men on site today.
Paint siding.

Todd Bowers


Todd Bowers 11/23/09 entered the following on 13:25:04 Nov/24/2009:
Memo:
Abbink Daily Report   11 23 09

The weather was nice about 67 with no rain.

The forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
Rough in plumbing, set lights, work on shade pockets, 
frame in for med cabinets.

CCS  had 1 man on site today.
Rough in plumbing.

Big Horn had 3 men on site today.
Set lights, frame in for med cabinets.

ACC had 3 men on site today.
Paint siding.

Terry was on site this afternoon.

Todd Bowers



Todd Bowers 11/20/09 entered the following on 07:38:51 Nov/23/2009:
Memo:
Abbink Daily Report   11 20 09

Weather was nice about 65 with no rain. 

The Foeklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
Rough in plumbing, add steel over family room fire place, 
set lights.

CCS had 1 man on site today.
Rough in plumbing

Big Horn had 3 men on site today.
Add steel over family room fire place, set lights.

ACC had 3 men on site today.

Paint soffit and trim over roof.

Todd Bowers


Todd Bowers 11/19/09 entered the following on 08:11:31 Nov/20/2009:
Memo:
Abbink Daily Report    11 19 09

The weather was nice about 74 with no rain.

The forklift was used on site today.

BTV had 2 hen on site today.
Todd B. Nicolas R.
Plumbing, plywood and fur wall in elevator shaft, move 
lights in the kitchen.

CCS had 1 man on site today.
Plumbing

Big Horn had  men on site today.
Move lights in the kitchen, plywood and fur wall in 
elevator shaft.

Todd Bowers


Todd Bowers 11/18/09 entered the following on 08:20:42 Nov/19/2009:
Memo:
Abbink Daily Report   11 18 09

The weather was nice about 70 with no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Duane C. Todd B. Nathan K.
Plumbing, cut and head for HVAC, site meeting, set windows.

CCS had 2 men on site today.
Plumbing

Big horn had 3 men on site today.
Cut and head for HVAC, set windows.

ACC had 3 men on site today.
Prep siding for paint.

Linda C. Joe C. Terry R. was at the site meeting today.
See Nathan’s notes.

Todd Bowers


Todd Bowers 11/17/09 entered the following on 16:49:05 Nov/17/2009:
Memo:
Bbink Daily Report    11 17 09

The weather was nice about 70 with no rain.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
Install water pipes. Install siding. Set windows.

CCS had 1 man on site today. 
Install water pipes.

Big Horn had 3 men on site today.
Install siding and set windows.

ACC had 3 men on site today.
Prep siding for paint.

Terry R. was on site this morning. I gave him a key and 
the alarm code. 

Todd b


Todd Bowers 11/16/09 entered the following on 11:01:51 Nov/17/2009:
Memo:
Abbik Dailt Report  11 16 09

Weather was nice no rain.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R. 
Lay out kitchen cabinets. Install water pipes. Siding, set 
windows

CCS had 1 man on site today.
Install water pipes.

Big Horn had 3 men on site today.
Siding and set windows.

AGC Gutter (Chris) was on site to go over the gutters in 
the front of the house.

OM Roofing was on site today to go over copper flashing 
details that need to be cleaned up.

Todd Bowers



Todd Bowers 11/13/09 entered the following on 11:00:45 Nov/17/2009:
Memo:
Abbink Daily Report  11 13 09

Weather was cool and windy with no rain.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
Cover windows and doors. Siding, Screw down window 
hardware. Work on soffit shade detail. Set windows.

CCS had 1 man on site today.
Cover windows.

AGA had 1 man on site today. 
Set windows. Install lights.

Big Horn had 3 men on site today. 
Siding. Screw down window hardware.

Todd Bowers


Todd Bowers 1/12/09 entered the following on 08:35:51 Nov/13/2009:
Memo:
Abbink Daily Report     11 12 09

Weather was cold with rain all day.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
Install soffits. Pack out wall in master bed room to 
center door. Cover windows and doors with plastic for bug 
juice.

CCS had 1 man on site today.
Cover windows.

AGA had I man on site today. 
Set windows.

Big Horn had 3 men on site today.
Install soffits .

Todd Bowers


Todd Bowers 11/11/09 entered the following on 08:28:02 Nov/13/2009:
Memo:
Abbink Daily Report     11 11 09

Weather was cool with no rain.

Forklift was used on site today.

BTV had 3 man on site today.
Todd B Duane C. Nathan K.
Install lights and soffits. Site meeting.

Big Horn had 3 men on site today.
Install lights and soffits.

Site Meeting 
The Abbinks, Linda, Terry, Joe, 
See meeting notes.

Todd Bowers


Todd Bowers 1/10/09 entered the following on 07:26:23 Nov/11/2009:
Memo:
Abbink Daily Report   11 10 09

Weather was over cast with afternoon rain.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
We worked on siding, plumbing, soffits and removing 
stickers from windows.

CCS had 1 man on site today.
Plumbing

Big Horn had 3 men on site today.
Siding and soffits.

Todd Bowers


Todd Bowers entered the following on 15:04:15 Nov/10/2009:
Memo:
Abbink Daily Report   11 9 09

Weather was nice with no rain.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
We worked on siding, installing soffits and plumbing.

CCS had 3 men on site today.
Install plumbing and duct work.

Big horn had 3 men on site today.
Siding and install soffits.  

Jeff McCandless with Elevator Lift System was on site 
today.
He said we can use a hydraulic elevator and put the moter 
and tank over the master bed room. We need to install 2 
layers of ¾ plywood to the back wall. We need to fur the 
wall on the rite in about 2”. 

Todd Bowers


Todd Bowers 11/2/6/09 entered the following on 10:30:35 Nov/09/2009:
Memo:
Abbink Daily Reports   11 2-6 09

Weather was good with no rain all week.

The forklift was used on site all week.

BTV had 2 men on site all week.
Todd B. Nicolas R.
We worked on plumbing, Siding and building soffits, 
installing lights.

CCS had 3 men on site all week.
Install duct work,plumbing.

Big Horn had 3 men on site all week.
Siding, install soffits, install lights.

MMC came out and laid out the cabinets and did a material 
take of on the INT trim.

Building Specialty installed the fire place in the family 
room.

Todd Bowers



Todd Bowers 10 29 09 entered the following on 15:29:18 Oct/29/2009:
Memo:
Abbink Daily Report 10 28 09

Weather was nice about 75 with no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Install lights in the kitten and frame room over master 
bed room for DVA.

CCS had 4 men on site today.
Install duct work on the 1st and 2nd floor. Flash windows. 
Install temp lights.

Big Horn Had 3 men on site today.
Frame room over master bed room for DVA. Install windows.

Todd Bowers


Todd Bowers 10/27/09 entered the following on 16:04:58 Oct/28/2009:
Memo:
Abbink Daily Report   10 27 09

Weather was cool about 65 with afternoon rain.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
Install siding. Install window flashing. Lay out can 
lights and install in the kitchen.

CCS had 4 men on site today.
Install duct work on the 1st and 2nd floor. Flash windows.

Big horn had 3 men on site today.
Install siding and install lights.

Todd Bowers


Todd Bowers 10/26/09 entered the following on 15:56:17 Oct/28/2009:
Memo:
Abbink Daily Report  10 26 09

Weather was cool about 65 with no rain.

Forklift was used on site toady.

BTV had 3 men on site today.
Flash windows. Install plumbing. Install siding.

CCS had 3 man on site today.
Install duct work on the 1st floor. Install plumbing.

Big Horn had 3 men on site today.
Install siding.

Todd Bowers


Todd Bowers 10/23/09 entered the following on 15:49:56 Oct/28/2009:
Memo:
Abbink Daily Report   10 23 09

Weather was nice about 70 with no rain.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
Flash windows and site clean. Install siding.

SSC had 1 man on site today.
Help flash windows.

Big Horn had 3 men on site today.
Install siding.

Todd Bowers


Todd Bowers 10/22/09 entered the following on 15:40:35 Oct/28/2009:
Memo:
Abbink Daily Report   10 22 09

Weather was nice about 70 with no rain.

Forklift was used on site today.

BTV 3 men on site today.
Todd B. Dan B. Nicolas R.
Install windows. Flash windows. Install siding.

CCS had 1 man on site today.
Install plumbing. 

Big Horn had 3 men on site today. 
Install siding

Todd Bowers


Todd Bowers 10/21/09 entered the following on 15:34:30 Oct/28/2009:
Memo:
Abbink Daily Report    10 21 09 

Weather was nice about 75 with no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Nicolas R. Todd B. Dan B.
Install windows on the 2nd floor. Install plumbing. 
Install siding.

CCS had 6 men on site today.
Install duct work on the 1st floor. Install plumbing on 
the 1st and the 2nd floor.

AGA had 1 man on site today.
Install windows on the 2nd floor.

Big Horn had 7 men on site today. 
Install siding. Install 1st coat of stucco.

Linda and Terry was on site today. 

Todd Bowers


Todd Bowers entered the following on 16:05:29 Oct/21/2009:
Memo:
Abbink Daily Report    10 20 09

Weather was nice about 70 with no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Todd B. Dan B. Nicolas R. 
Set windows on the 2nd floor. Build and install temp door. 
Cut and head for HVAC. Install plumbing. Prep job for EXT 
trim and siding.

CCS had 4 men on site today.
Install plumbing. Install duct work on the 1st floor.

OM Roofing had 1 man on site today.
Install copper roof flashing.

AGA had 1 man on site today.
Set windows on the 2nd floor.

Big Horn had 6 men on site today.
Install soffit. Install wire for stucco to all places that 
are over the roof.
Big Horn started the siding toady. This will be on a T & M 
bases Until we get off the roof or we have the personal 
available to take it over. 

Hans was on site today and liked all that he saw.

Todd Bowers


Todd Bowers 10/19/09 entered the following on 16:03:42 Oct/21/2009:
Memo:
Abbink Daily Report    9 19 09

Weather was cool 60 with no rain.

Forklift was used on site today.

BTV had 4 men on site today.
Install temp door in the back of the house. Paint attic 
floor. Install windows.Cut and head for HVAC.

CCS had 2 men on site today.
Install duct work on the 1st floor.

AGA had 1 man on site today.
Install windows 2nd floor.

Big Horn had 6 men on site today.
Install soffit. Install wire for stucco on chimneys.

OM Roofing had 2 men on site today.
Install copper flashing on the roof.

Todd Bowers 


Todd Bowers 10/16/09 entered the following on 16:10:37 Oct/16/2009:
Memo:
Abbink Daily Report         10 16 09  

Weather rain all day.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Rolando N.
Install windows and doors. Clean site.  

CCS had 3 men on site today.
Install duct work on the 1st floor.

Big Horn had 3 men on site today.
Install soffit. Deliver material for stucco work on Monday.

I met with Charlie York and the people that live across 
the street from the park. I agreed to keep the forklift on 
site as much as I can. I agreed that all employees will 
park against the fence when possible. I agreed to grade 
the ruts out of the park when it is needed.


Todd Bowers


Todd bowers 10/15/09 entered the following on 16:02:17 Oct/16/2009:
Memo:
Abbink Daily Report    10 15 09

Weather rain all day.

Forklift was used on site today.

BTV had 3 men on site today
Dan B. Rolando N. Todd B.
Install windows. Paint attic floor.

CCS had 3 men on site today.
Install duct work on 1st floor.

AGA had 1 man on site today.
Install windows.

Big Horn had 3 men on site today.
Install soffit.

Todd Bowers


Todd Bowers 10/14/09 entered the following on 15:55:21 Oct/16/2009:
Memo:
Abbink Daily Report     10 14 09

Weather rain off and on all day.

Forklift was used on site today.

BTV had  men on site today.
Todd B. Dan B. Rolando N.
Install windows. Plumbing.

CCS had 1 man on site today.
Install duct work on the 1st floor.

Big Horn had 3 men on site today. 
Build, paint and install temp doors.

AGA had 1 man on site today.
Install windows.

Site meeting,
Linda C. Joe C. Nathan K. Terry R. Hans A. Todd B.
See Nathan’s notes.

Chubb Had a person on site today to inspect the site and 
make sure we have met there requirements. See liked what 
she saw.

Todd Bowers


Todd Bowers 10/13/09 entered the following on 15:54:25 Oct/16/2009:
Memo:
Abbink Daily Report  10 13 09

Weather was nice with no rain.

Forklift was used on site today.

BTV had 3 men on site.
Set windows. Install plumbing. Install soffit .

CCS had 1 man on site today.
Install duct work.

AGA had 1 man on site today.
Install windows.

Big Horn had 3 men on site today.
Install soffit on the garage.

Building Specialty  had 2 men on site today.
Install living room fire place. They still need to go 
though the roof.

Todd Bowers


Todd Bowers 10/12/09 entered the following on 15:55:27 Oct/13/2009:
Memo:
Abbink Daily Report   10 12 09

Weather nice with no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Work on straitening out band on the garage. Install 
plumbing. Set windows.

CCS  had 1 man on site today.
Install plumbing

Big Horn had 3 men on site today.
Straiten out band on the garage. Install beams on the 
garage.

Todd Bowers


Abbink Daily Report   10 12 09

Weather nice with no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Work on straitening out band on the garage. Install 
plumbing. Set windows.

CCS  had 1 man on site today.
Install plumbing

Big Horn had 3 men on site today.
Straiten out band on the garage. Install beams on the 
garage.

Todd Bowers



Todd Bowers 10/6-10/9 entered the following on 15:30:38 Oct/13/2009:
Memo:
Abbink Daily Report    10 6-10 9 09

The weather has been good over the past few days.

The forklift was used every day.

BTV had 3 man on site. 

CCS had 1 man on site.

Big Horn had 3 men on site.

Plumbing work. Framing the garage. Setting windows. 
Painting the attic floor and walls.

Todd Bowers
Abbink Daily Report    10 6-10 9 09

The weather has been good over the past few days.

The forklift was used every day.

BTV had 3 man on site. 

CCS had 1 man on site.

Big Horn had 3 men on site.

Plumbing work. Framing the garage. Setting windows. 
Painting the attic floor and walls.

Todd Bowers


Todd Bowers 10/5/09 entered the following on 15:55:59 Oct/08/2009:
Memo:
Abbink Daily Report     10 5 09

Weather, rain all day. Work did not stop.

Forklift was used on site today.

BTV had 2 men on site today.
Todd B. Nicolas R.
Frame garage. Paint walls in the attic.

CCS had 1 man on site today.
Install plumbing.

Big Horn had 3 men on site today.
Frame garage.

Todd Bowers



Todd Bowers 10/2/09 entered the following on 15:54:39 Oct/08/2009:
Memo:
Abbink Daily Report        10 2 09

Weather was nice with no rain.

Fork lift was used on site today.

BTV had 2 men on site today.
Todd B. Duane C.
Frame garage. Pour concrete. Go door by door and make door 
schedule.

CCS had 2 men on site today.
Install duct work for HVAC.

Big Horn had 6 men on site today.
Pour concrete. Frame garage. Clean up job site.

We had site meeting with Linda and the Abbinks on the int. 
doors. We completed the door lay out and marked them on 
the door openings and made a list.

Todd Bowers





Todd Bowers 10/1/09 entered the following on 15:51:51 Oct/08/2009:
Memo:
Abbink Daily Report    10 1 09

Weather was nice with no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd Bowers
Frame garage. Form knee walls.

CCS had 2 men on site today.
Install duct work for HVAC

Big Horn had 4 men on site today.
Frame garage. Form knee walls.

Todd Bowers



Todd Bowers 9/30/09 entered the following on 11:19:06 Oct/05/2009:
Memo:
Abbink Daily Report    9 30 09

Weather was nice with no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Frame garage. Form slab.

CCS had 2 men on site today.
Install duct work for HVAC.

Big Horn had 4 men on site today.
Frame garage. Form slab.

Todd Bowers


Todd Bowers 9/28/09 entered the following on 10:24:53 Oct/05/2009:
Memo:
Abbink Daily Report    9 28 09

Weather was nice today with no rain.

BTV had 2 men on site today.
Todd B. Nicolas R 
Install soffit. Install plumbing. Form for boiler room and 
storage room slab. Pick up framing.

CCS had 3 men on site today. 
Install duct work. Install plumbing.

Big Horn had 4 men on site today.
Install soffit. Form work on the boiler room and storage 
room.

Todd Bowers


Todd Bowers 9/25/09 entered the following on 10:20:15 Oct/05/2009:
Memo:
Abbink Daily Report    9 25 09

Weather was nice with no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Nicolas R. Francisco Todd B.
Install soffit. Wrap window openings. Pick up framing.

CCS had 3 men on site today.
Install duct work. Drill wholes for plumbing.

Big Horn had 4 men on site today. 
Install soffit. Pick up framing.

Todd Bowers


Todd Bowers 9/24/09 entered the following on 16:55:06 Sep/24/2009:
Memo:
Abbinks Daily Report    9 24 09

Weather was nice no rain.

The forklift was used on site today

BTV had 3 men on site today.
Todd B. Nicolas R. Francisco
Install soffit. Wrap window openings. Lift garage, put in 
place and anchor down. 

Big Horn had 5 men on site today. 
Install soffit. Head off for draw behind master vanity. 
Move garage.

The sffit on the main house is now about 85% complete.
The garage is moved and set in place.
The wrapping of the window openings is about 75% complete.
The packing out of the windows is about 85% complete.

Todd Bowers


Todd Bowers 9/23/09 entered the following on 16:43:30 Sep/24/2009:
Memo:
Abbink Daily Report    9 23 09

Weather was nice no rain.

Forklift was used on site today.

BTV had 5 men on site today.
Todd B. Nicolas R. Francisco Duane C. Nathan K.
Install soffit. Wrap window openings. Build shower niches. 
Site meeting.

Big Horn had 4 men on site today.
Install soffit. Build shower niches.

Terry R. was at the site meeting.

Joe C. with CCS was at the site meeting.

The HVAC was approved by the Abbinks.
The plumbing was approved by the Abbinks.
Joe will provide more information to the Abbinks about 
solar power and DDC controls.

The meeting was very good. Because of these approvals we 
can keep on the critical path of getting the mechanicals 
complete in the house.

We still need the lighting to be approved.

I received 2 quotes on the EXT siding and trim packed 
today. I am still waiting on 2 more.

Todd Bowers


Todd Bowers 9/22/09 entered the following on 10:55:05 Sep/23/2009:
Memo:
Abbink Daily Repot    9 22 09

Weather was nice today. There was no rain .

Forklift was used on site today.

BTV had 4 men on site today.
Dan B. Nicolas R. Fran
Install ¾ pack out for the windows. Flash window openings. 
Pour concrete knee walls in the garage. Strip forms and 
finish concrete. Install soffit.

Big Horn had 9 men on site today.
Install soffit. Pour concrete knee walls in the garage. 
Strip forms and finish concrete.

CCS had 2 men on site today.
Install duct work 1st floor.

BFS had 2 men on site today .
Mull windows. 

OM Roofing had 2 men on site today.
Install the last 3 skylights.

I did not report that on 9/19/09 Weber Homes was on site 
and hung the sheetrock in the attic and the 2 mech. rooms 
on the 1st floor.

Weber homes had 1 man on site today.
Mud sheetrock in the attic and 2 mech. rooms on the first 
floor.

Todd Bowers


Todd Bowers 9/21/09 entered the following on 10:39:07 Sep/23/2009:
Memo:
Abbink Daily Report        9 21 09

Weather was nice and no rain.

Forklift was used on site today.

BTV had 2 men on site today.
Dan B. Todd B.
Install ¾ pack out for the windows. Flash the window 
openings. Install soffit. Form work on the garage knee 
wall.

CCS had 1 man on site today.
Spray foam insulation.

Big Horn had 6 men on site today.
Install soffit. Form work on the garage knee walls.

OM Roofing had 2 men on site today.
Install 6 skylights over stairs.

AGA had 1 man on site today.
Install ¾ pack out for windows. Flash window openings.

We got an inspection on the garage knee walls.

HHE sprayed bug juice in the garage knee walls.

Todd Bowers


Todd Bowers 9/18/09 entered the following on 10:51:57 Sep/21/2009:
Memo:
Abbink Daily Report      9 18 09

Weather nice day no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Install soffit. Form knee walls in the garage. Lay out 
shower niches with Linda. Lay out fire places with 
Building Specialty man ( Rick ).

Big Horn had 7 men on site today.
Install soffit and form garage.

Linda was on site today. Lay out shower niches and towel 
bars.

Building Specialty lay out fire places for quoting.

I called for an inspection of concrete knee walls.
I called HHE to spray bug juice in knee walls.

Ed E came and laid out the plumbing waist and vents with 
me today.

Soffit is now about 45% complete. The garage will be 
poured on 9/22/09. The foam insulation of the attic and 
roof will be complete on 9/21/09.

Todd Bowers


Todd Bowers 9/17/09 entered the following on 08:46:26 Sep/21/2009:
Memo:
Abbink Daily Report    9 17 09

Weather nice no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Install soffit. Form knee walls in the garage.

CCS had 3 men on site today.
Spray foam insulation. Prep duct work for installation.

Big Horn had 9 men on site today.
Install soffit. Form knee walls in garage. Frame in attic 
stair. 

OM Roofing had 2 men on site today.
Install copper flashing.  OM also had 2 men on site 
yesterday ( 9/16/09 ).

Todd Bowers


Todd Bowers 9/16/09 entered the following on 09:27:05 Sep/17/2009:
Memo:
Abbink Daily Report     9 16 09

Weather nice day no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Todd B. Duane C. Nathan K.
Lift and move garage out of the way so we can form and 
pour knee walls. Lay out knee walls. Install soffit. 
Repair air compressor. Cut and head for HVAC. Site 
meeting. 
.
CCS had 2 men on site today 
Clean up attic after foam job. Site meeting.

Big Horn had 7 men on site today.
Install soffit. Move garage. Cut post off 2” below garage 
slab. Cut and head for HVAC. Build walls in kitchen.

BFS had 2 men on site today.
Mull widows together.

Site meeting

See Nathan’s notes.

Todd Bowers


Todd Bowers 9/15/09 entered the following on 17:50:03 Sep/15/2009:
Memo:
Abbink Daily Report     9 15 09

Weather nice day no rain.

Forklift was used on site today.

BTV had 1 man on site today. 
Todd B. 
Install soffit. Lay out mech. room in the attic. Cut and 
head for HVAC. Over see the mulling of windows.

CCS had 2 men on site today.
Clean up attic from over spray from the foam. Lay out duct 
work so we can cut and head.

Big Horn had 7 men on site today. 
Cut garage free and prep it to be moved. Install soffit. 
Cut and head for HVAC. Prep mech. room in the attic for 
sheet rock.

BFS  had 2 men on site today.
Mull doors and windows.
BFS also delivered the 2 gararge doors and the master bed 
room door.

I spoke to Terry R. on the phone about the placement of 
the smart vents in the garage. He said to put them on the 
left and the right sides of the garage and try to hide 
them behind plantings.

We got an insulation inspection on the attic today. Joe 
needs to get me paper work stating the R value To give to 
the town.

Todd Bowers


Todd Bowers 9/14/09 entered the following on 08:41:08 Sep/15/2009:
Memo:
Abbink Daily Report        9 14 09

Weather nice day no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Unload windows. Lay out windows and check openings. Go 
over kitchen cabinets with Patty and Todd from downs View. 
Lay picture blocking with Linda.

CCS had 2 men on site today.
Spray foam insulation.  Foaming of the attic is now 
complete.

Big Horn had 3 men on site today. 
Unload windows and help place the windows at the correct 
opening.

Hans was on site today. We went over possibly moving the 
screen door to the middle of the porch instead of by the 
house. This was brought up by Linda because of furniture 
placement. Hans also has concerns about the fire places. 
He does not want to loose energy though the fire places.

I call in for an insulation inspection today.

Todd Bowers


Todd Bowers 9/11/09 entered the following on 15:06:28 Sep/11/2009:
Memo:
Abbink daily Report        9 11 09

Weather, nice no rain.

Forklift was used on site today.

BTV had 1 man on site today. 
Todd B. 
Pick up framing. Install drop ceiling in the kitchen. 
Frame for wall hung toilets. Spray foam insulation.

CCS had 3 men on site today.
Hook up temp power. Spray foam insulation.

Big Horn had 6 men on site today.
Pick up framing. Install drop ceiling in the kitchen. 
Frame for wall hung toilets.
Make new stucco sample.

OM Roofing  had 3 men on site today.
Install copper roof flashing. Install copper caps over 
beam ends.

Linda called and said that Downs View will be here Monday 
to measure for the kitchen cabinets. They are also to 
bring me cabinet plans that I can lay out the kitchen with.

Linda and I will go over picture blocking and over 
blocking she may need on Monday. 

The new stucco sample with the scallop shell is complete.

Todd Bowers


Todd Bowers 9/10/09 entered the following on 15:05:33 Sep/11/2009:
Memo:
Abbink Daily Report        9 10 09

Weather, nice no rain.

Forklift was used on site today.

BTV had 1 man on site today. 
Todd B.
Oversee roof flashing. Spray foam insulation. Install 
blocking. Build walls in the master bath room. Install 
temp power in the elevator shaft.

CCS had 5 men on site today.
2 men sprayed foam. 
2 men delivered duct work.
1 man brought out temp power to install in the elevator 
shaft.

OM Roofing had 2 men on site today.
Install copper flashing.
 
Webber Homes had 1 man come out to give me a quote on 
installing sheetrock in the attic.

Big Horn had 3 men on site today. 
These 3 men worked for BTV by the hour on firing down the 
master bed room ceiling, building walls in the master 
bath. Installing temp floor in the elevator shaft.
Kurt delivered the bag of scallop shells for a new stucco 
sample.
 
Todd Bowers


Todd Bowers 9/9/09 entered the following on 15:04:38 Sep/11/2009:
Memo:
Abbink Daily Report      9 9 09

Weather,  nice day no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Todd B., Duane C., Nathan K.,
Spray foam insulation. Oversee roof flashing. Install 
cabinet blocking. Remove soffit from garage. Attend site 
meeting. Pressure wash the neighbors entry. Paint siding 
on mock up.

CCS had 1 man on site today.
Spray foam insulation. 

Big Horn had 3 men on site today.
Install cabinet blocking. Remove soffit from garage.
Big Horn also had 2 men make a stucco sample today.

OM Roofing had 3 men on site today.
Install copper flashings These flashing need to be 
installed before trim can be installed.

MMC had 1 man on site today for the site meeting.  Jamie K.

Terry was on site for the site meeting.

Site Meeting. 

•	Terry approved the siding, soffit and trim colors 
on the mock up. They still need to be approved by Linda 
and the Abbinks before going to the ARB.
•	Terry gave us the placement of master bath vanity 
wall. It will be 25” off existing wall.
•	The master bath ceiling will be sheetrock instead 
of wood.
•	Linda needs to let us know weather she wants to 
use quarter sawn or rift cut oak.
•	Lifting the garage. Nathan will take the plans to 
the town . Terry has spoken with the POA and said that it 
was ok to lift the garage up 1’. Terry does not have 
anything in writing from the POA and is taking on the 
responsibility to go ahead with the work without have it 
in writing.
•	Linda will have to tell us what she wants the int. 
door to look like.
•	There were some discussions about the stairs. The 
stainless steal post will mount on the side of the stairs 
and not though the treads. With this information we should 
be able to get every thing we need from the hand rail 
people to build the stairs.
Todd Bowers




Todd Bowers 9/8/09 entered the following on 17:04:25 Sep/08/2009:
Memo:
Abbink Daily Report   9 8 09

Weather, nice day.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Framing in the attic. Spray foam insulation. Install 
blocking. Set up scaffolding. 

CCS had 2 men on site today. Spray foam insulation. Set up 
scaffolding.

Big Horn had 6 men on site today. 
Install blocking, Set up scaffolding. Framing in the attic.

Danny Smith dropped off the soffit material primed and 
ready to install.

Terry R. came to the site today to get as built 
measurements on the post brackets for the garage. 

Todd Bowers


Todd Bowers 9/4/09 entered the following on 11:28:19 Sep/08/2009:
Memo:
Abbink Daily Report      9 4 09

Weather, nice day 

Forklift was used on site today.

BTV had 1 man on site today.
Todd B. 
Oversee blocking, Install scaffolding, spray foam 
insulation.

Big Horn had 8 men on site today.
Install blocking, Set up scaffolding, 

The roofer came out and measured for custom copper roof 
flashings that need to be installed before the soffit 
starts.

Todd Bowers


Todd Bowers 9/3/09 entered the following on 11:27:22 Sep/08/2009:
Memo:
Abbink Daily Report      9 2 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Todd B./ Duane C. /Nathan K.
Oversee framing and site meeting.

Big Horn had 8 men on site today
Water proof back porch. Install 1x4 for copper flashing. 
Install blocking 

CCS had 1 man on site for meeting.
Joe C.

MMC had 1 man on site for meeting.
Jamie K.

Linda C Terry R. Hans and Opel where in the meeting aswell.

Todd Bowers


Todd Bowers 9/2/09 entered the following on 11:25:27 Sep/08/2009:
Memo:
Abbink Daily Report      9 2 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 3 men on site today.
Todd B./ Duane C. /Nathan K.
Oversee framing and site meeting.

Big Horn had 8 men on site today
Water proof back porch. Install 1x4 for copper flashing. 
Install blocking 

CCS had 1 man on site for meeting.
Joe C.

MMC had 1 man on site for meeting.
Jamie K.

Linda C Terry R. Hans and Opel where in the meeting aswell.

Todd Bowers


Todd Bowers 9/1/09 entered the following on 11:24:42 Sep/08/2009:
Memo:
Abbink Daily Repot     9 1 09

Weather Hot with no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Oversee framing

Big Horn had 8 men on site today.
Frame back porch. Frame wall in the living room.

Terry R. was on site this afternoon. We siding details.

•	We will raise the louvers under windows in Han’s 
office 8” to allow for proper flashing.
•	The band that runs around the house at the 2nd 
floor will be about 16” wide and will be made with 1x12 
and 1x8.
•	Terry wants to be apart of the gutter layout. This 
will take place at the end of the job.
Todd Bowers


Todd Bowers 8/30/09 entered the following on 08:58:23 Sep/01/2009:
Memo:
Abbink Daily Report      8 30 09

Weather, hot with afternoon rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Oversee framing.

Big Horn had 8 men on site today.
Frame screen porch. Straighten walls on the 2nd floor. 
Build wall in the living room at block fire wall. Install 
straps. 

I called in for a strapping inspection today.

Todd Bowers


Todd Bowers 8/27/09 entered the following on 08:19:08 Sep/01/2009:
Memo:
Abbink Daily Report      8 27 09

Weather, hot with afternoon rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Oversee framing.

Big Horn had 8 men on site today.
Frame screen porch. Install blocking 2nd floor. Frame 
living room fire place.

Todd Bowers


Todd Bowers 8/27/09 entered the following on 09:33:52 Aug/28/2009:
Memo:
Abbink Dailt Report    8 27 09

Weather, Hot with morning rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd b.
Oversee framing.

Big Horn had 8 men on site today.
Frame screen porch. Install Simpson straps. Install 
blocking 2nd floor. Build living room fireplace.   

Todd Bowers




Todd Bowers 8/26/09 entered the following on 09:20:37 Aug/28/2009:
Memo:
Abbink Daily Report       8 26 09

Forklift was used on site today,

BTV had 1 man on site today
Todd B.
Oversee framing.

Big Horn had 8 men on site today.
Frame screen porch. Water proof the house. Frame living 
room chimney. Install Simpson straps.

Todd Bowers


Todd Bowers 8/25/09 entered the following on 08:43:36 Aug/28/2009:
Memo:
Abbink Daily Report    8 25 09

Weather, hot no rain.

Forklift was used on site today. Pressure was washer used 
today.

BTV had 1 man on site today.
Todd B.
Oversee framing and pressure wash drive way.

Big Horn had 8 men on site today
Frame screen porch. Water proof house walls. Install 
Simpson strapping. Frame around skylight.

Todd Bowers
 


Todd Bowers 8/24/09 entered the following on 08:35:25 Aug/28/2009:
Memo:
Abbink Daily Report    8 24 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B. 
Oversee framing

Big Horn had 8 men on site today.
Waterproof walls and roof. Frame screen porch. Build 
family room chimney.

Todd Bowers


Todd Bowers 8/21/09 entered the following on 11:15:29 Aug/24/2009:
Memo:
Abbink Daily Report      8 21 09

Weather, hot with afternoon rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B. 
Oversee framing.

Big Horn had 8 men on site today.
Pour concrete in block fire wall. Replace headers. Water 
proof the back side of the house. Install rafters and 
plywood over bay windows.

Todd Bowers


Todd Bowers 8/20/09 entered the following on 08:39:49 Aug/21/2009:
Memo:
Abbink Daily Report          8 20 09

Weather, hot no rain. 

Forklift was used on site today.

BTV had 1 man on site today.
Todd B. 
Oversee framing

Big Horn had 8 men on site today.
Install rafters over bay window in the master bed room. 
Install plywood roof sheeting and water proof roof over 
the exercise room. Water proof the sound side walls. 
Remove and rebuild header in the dinning room. Plywood 
wall in bed 2.

Big Horn had a company come out and grind the high spot 
out of the living room floor.
I think this will take about 2 or 3 days.

Dew to all the rain that we have had over the passed 2 
weeks the LVL headers are moving around a lot. The headers 
are swelling and bowing. There are about 5 headers that we 
are going to have to replace. Big horn is taking care of 
this problem.  Now that we are getting the house dried in 
this should no longer be a problem.

Terry stopped by the job to let me know that the ARB gave 
him permission to raise the garage.

Todd Bowers



Todd Bowers 8/19/09 entered the following on 11:47:36 Aug/20/2009:
Memo:
Abbink Daily Report    8 19 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
 Oversee framing.

Big Horn had 8 men on site today.
Install roof sheeting, Water proof the roof decks. Install 
rafters over the Exercise room. Build round wall at foyer.

I ordered CYP 2x4 for freeze board today. They will go to 
MMC for mill work.


Todd Bowers


Todd Bowers 8/18/09 entered the following on 11:39:55 Aug/20/2009:
Memo:
Abbink Daily Report     8 18 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
 Oversee framing.

Big Horn had 8 men on site today.

Install rafters and roof sheeting.

Todd Bowers


Todd Bowers 8/17/09 entered the following on 15:10:08 Aug/18/2009:
Memo:
Abbink Daily Report     8 17 09 

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Oversee framing.
Duane was on site today for about 2 ½ hours.

Big Horn had 8 men on site today.
Install rafters and Roof plywood.

Terry R. was on site today.
We went over paint colors and other details in the house. 
( see email ) 

Todd Bowers


Todd Bowers 8/14/09 entered the following on 13:19:49 Aug/17/2009:
Memo:
Abbink Daily Report    8 14 09

Weather, hot with morning rain. The rain did not stop work.
Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Oversee framing and do a material take off on soffit.
Duane C. was on site today. 

Big Horn had 8 men on site today.
Install plywood sheeting. Install rafters.

Terry R. was on site today.
This that were change and discussed
•	Make bed 1 door 8-0
•	Make the ceiling out side bed 2 the same as the 
ceiling over the stairs.
•	Center the skylite in guest bath right to left and 
keep it in line with either the top or bottom skylite. We 
will do what will give us the most room in the atic.
•	We discussed adding a window in the master shower.
•	We will stucco block wall over the unit next door.
•	The roof over hang at Opel’s closet will step back 
1’ where it changes plan.

Todd Bowers


Todd Bowers 8/13/09 entered the following on 13:18:22 Aug/17/2009:
Memo:
Abbink Daily Report          8 13 09

Weather, with hot morning rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B. 
Oversee  framing.

Big Horn had 8 men on site today.
Install plywood sheeting. Install roof rafters.

Todd Bowers



Todd Bowers 8/12/09 entered the following on 13:08:01 Aug/17/2009:
Memo:
Abbink Daily Report      8 12 09

Weather, hot with afternoon rain.

Forklift used on site today.

BTV had 1 man on site today.
Todd B.
Over see framing and site meeting.

Big Horn had 7 men on site today.
Install plywood sheeting, Cut and install rafters.

Site meeting 
Todd B., Duane C., Nathan K., Terry R., Linda C., Hans and 
Opel.
See Nathan’s notes.
The meeting lasted about 2 hours and we covered a lot.

Todd Bowers


Todd Bowers 8/11/09 entered the following on 13:07:04 Aug/17/2009:
Memo:
Abbink Daily Report      8 11 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B. 
Over see framing.
Duane C. was on site toady for about 2 hours.

Big Horn had 8 men on site today.
Install rafters over living room. Cut rafters. Change 
walls on the 2nd floor out side Hans’s office. Install 
wall sheeting 2nd floor.

Todd Bowers


Todd Bowers 8/10/09 entered the following on 13:06:08 Aug/17/2009:
Memo:
Abbink Daily Report   8 10 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 2 me on site today.
Todd B. Duane C.
Oversee framing and site meeting with Linda.

Big Horn had 8 men on site today.
They worked on sheeting walls. Install beams that hold 
soffits. Cut and install rafters.

MMC did a good job of getting us the soffits beams ready 
for us to install. Because of the OT that they ran we did 
not hold the project up.

Site meeting with Linda today was a good meeting. We 
discussed many items and work though some details. ( see 
notes from meeting.)

Todd Bowers 


David - For Todd entered the following on 08:41:23 Aug/17/2009:
Memo:
Abbink Daily Report     8 7 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Over see framing

Big Horn had 8 men on site today.
Install ceiling joist on the 2nd floor. Install steal 
column that supports the 2nd floor under bed 2. Install 
temp. hand rails. Clean job site.

I ordered the copper caps for the beams today.
The mill shop will run over time so that we can get the 
beams on Monday.

Todd Bowers 


David - For Todd entered the following on 08:41:09 Aug/17/2009:
Memo:
Abbink Daily Report     8 7 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Over see framing

Big Horn had 8 men on site today.
Install ceiling joist on the 2nd floor. Install steal 
column that supports the 2nd floor under bed 2. Install 
temp. hand rails. Clean job site.

I ordered the copper caps for the beams today.
The mill shop will run over time so that we can get the 
beams on Monday.

Todd Bowers 


David - for Todd entered the following on 08:40:33 Aug/17/2009:
Memo:
Abbink Daily Report        8 6 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Over see framing. Lay out lights on the 2nd floor.

Big Horn had 8 men on site today.
Build walls on the 2nd floor. Add headers over 3 bay 
windows on the 2nd floor. Start to straighten 2nd floor 
walls. Lay out ceiling joist while trying to keep lights 
in mind. 


We will add a steal flitch plate into beam over stairs to 
carry the weight of the 2 roofs that it will be caring. We 
will also use LVLs for rafters on the long run on the back 
of the house over the living room to help keep it from 
sagging. This run is over 23’. 

Todd Bowers


David For Todd entered the following on 08:39:50 Aug/17/2009:
Memo:
Abbink Daily Report     8 5 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Over see framing. Order material for ceiling joist, studs 
at block wall. 

Big Horn had 7 men on site today.
Stand walls on the 2nd floor. Install temp. stairs. 

Do to lack of room for shade pocket in the master bed room 
bay window. We will have to make a steal header over the 3 
windows in the bay.

Todd Bowers


David - for Todd entered the following on 08:39:30 Aug/17/2009:
Memo:
Abbink Daily Report     8 4 09

Hot, no rain

Fork lift was used on site today.

BTV had 1 man on site today.
Todd B. 
Over see framing. Take Header material to shop and mill 
down to 11/2 .  
Duane C was on site for about 2 hours. We went over the 
changes made to stairs and how it effects the doors 
leading into bed 2 &3. 

Big Horn had 7 men on site today.
Lay out walls on the 2nd floor. Build headers. Install 
blocking on the 1st floor…

Terry R was on site first thing this morning. 

Todd Bowers


David - for Todd entered the following on 08:38:47 Aug/17/2009:
Memo:
Abbink Daily Report      7 29 09

Weather hot midday rain. The rain stopped production for 
about 1 hour.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Over see framer and lay out penetrations in TGI for duct 
work.

Big Horn had 7 men on site today.
They worked on installing the rim joist. Cut wholes in the 
plywood that will reinforce the TGI for the duct work. 
Install TGI floor joist. Install seal at laundry room. 

Terry R. Came to the site to go over the way the radius 
wall in the foyer works out with the ceiling at the 
stairs. Terry Wants to pack out the kitchen wall so that 
the wall and the ceiling come together at the right place. 
We will pack the wall out about 2”.

We will add 2 steal post in the exercise room to support 
the steal beam in the ceiling. Because of the floor heat 
pipes we needed to ad more steal support in the exterior 
wall of the exercise room as well.

Todd Bowers


David - For Todd entered the following on 08:37:58 Aug/17/2009:
Memo:
Abbink Daily Report   7 28 09

Weather, hot no rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Pick up plywood and take to shop to be ripped down for TGI 
support. (36 sheets )
Lay out floor system with Brian.
Order sallow joist from MMC for floor system.

Big Horn had 7 men on site today.
Install wall sheathing. Install rim joist. Build beams. 

Because of the shade pockets in the window headers we are 
building 16” deep headers that will be installed over all 
the windows that have shade pockets.

Todd Bowers


Todd Bowers 7/27/09 entered the following on 11:16:24 Jul/28/2009:
Memo:
Abbink Daily Report      7 27 09

Weather, hot heavy afternoon rain.

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Lay out 2nd floor floor system.

Big Horn had 7 men on site today.
Build beams and install plywood on 1st floor walls. 
Straighten and install perlines.

We received the OK ( by phone with Richard Spruce) from 
the town that the 1st floor can be built out of SPF and 
did not need to be PT.

Because we were waiting on the answer from the town Big 
Horn did not start work until 11:30.

The 1st floor wall sheathing is PT plywood at the bottom 
of wall and is dropped 7” glued and screwed to concrete. 
We used stainless nails on the PT. All wall and roof 
sheathing will be glued with PL Premium.  

Todd Bowers


Todd Bowers 7/24/09 entered the following on 08:30:27 Jul/27/2009:
Memo:
Abbink Daily Report      7 24 09

Weather hot non rain

Forklift was used on site today.

BTV had 1 man on site today.
Todd B.
Over see framing.

Big Horn had 7 men on site today.
Frame walls 1st floor. Plum walls. 

Terry R. came to the site to get measurements on the 
stairs.

Hans, Opal and Linda were on site today to look at the 
cabinets. They are going to make the dining room cabinet a 
little smaller.

We ran into some problems with the elevation today and 
what type of material to use on the first floor. ( PT or 
SPF ). The inspector is out of town and will be back on 
Monday. We should be able to get an answer first thing 
Monday morning.

Todd Bowers





Todd Bowers 7/23/09 entered the following on 09:09:12 Jul/24/2009:
Memo:
Abbink Daily Report   7 23 09

Weather hot no rain

Forklift was used on site today.

BTV had 1 man on site today
Todd B.

Duane C and Ed E. had a meeting with Terry R. to go over 
changes in the plate height and working out the stairs to 
make the changes work. Duane and Ed then came out to job 
site to go over the changes with me and the framer.

Big Horn had 7 men on site today. 
They worked on building headers and standing walls.

Notes from the meeting

All the 8 feet walls in the entry and the kitchen will now 
be 9’1”.

We will make one of the beams in the kitchen out of steal 
so we can cut wholes in it for ac and plumbing lines. 

Ed E. will provide us with a plan so that we can make all 
the penetrations in the floor joist for plumbing and AC.

We will also use steal in the exercise room were there is 
a load bearing wall over it.

Terry will provide new drawings on the stairs because of 
plate height changes.

Terry let us know what the EXT. beams are and what they 
should look like.

Today was a good day. There where a lot of good decisions 
made today and a lot of walls got stood.

Todd Bowers









Todd Bowers 7/22/09 entered the following on 10:02:04 Jul/23/2009:
Memo:
Abbink Daily Report     7 22 09

Weather hot no rain

Forklift was used on site today.

BTV had 2 men on site today.
Dan B. Todd B.
Install PT plates on the first floor. Pull dirt from 
around trees. Spread wood mulch. Over see framing.

Big Horn had 7 men on site today.
Precut studs, cut jacks, Rip down headers, Build header,. 
Build walls. 

Ed came out and we went over the plate height and the lay 
out of 2nd floor system

Todd Bowers


Todd Bowers 7/21/09 entered the following on 11:26:28 Jul/22/2009:
Memo:
Abbink Daily Report 7 21 09

Weather hot no rain

Forklift was used on site today.

BTV had 2 men on site today.
Dan B. Todd B.
Installed PT plates on the first floor.

Duane ED and myself met at the shop and worked on the ROs 
for the first floor and header details  for shades. We 
will be adding steal to over the doors in the living room. 

Terry R came to the site  and wanted me to pull some more 
dirt from around 1 of the trees.

Todd Bowers




Todd Bowers 7/20/09 entered the following on 09:05:08 Jul/21/2009:
Memo:
Abbink Daily Report    7 20 09

Weather hot no rain

Forklift was used on site today.

BTV had 3 men on site today. Dan B. called in.
We cut and laid out plates for the first floor.

Hans came by the job after lunch and had some paper work 
on a Ecowater system he wants Duane to review.

Brain with big Horn. Order the framing package today.

Todd Bowers



Todd Bowers 7/17/09 entered the following on 07:52:44 Jul/20/2009:
Memo:
Abbink Daily Report     7 17 09

Weather   hot no rain

Forklift used on site today.

BTV had 4 men on site today.
Dan B. Gerson M. Rolando N. Todd B.

We drilled and epoxy in anchors for wall tie downs. Cut 
and installed PT bottom plates. Paint Drylok water 
proofing paint on block fire wall. Cleaned job site.

Hans Abbink was on site for about 1 ½ hours this afternoon.

Todd Bowers



Todd Bowers 7/16/09 entered the following on 16:04:56 Jul/16/2009:
Memo:
Abbink daily Report   7 16 09

Weather hot no rain

Forklift was used on site today.

BTV had 4 men on site today.
Dan B. Rolando N. Gerson M. Todd B.
Grade work around foundation. Paint block fire wall with 
Drylok water proof paint. It took 20 gallons. Lay out 
cabinets on the first floor slab. Pour Gardox in the 
expansion joints in the first floor slab.

BFS delivered all thread 2x6 for bottom plates.


Todd Bowers


Todd Bowers 7/15/09 entered the following on 08:45:54 Jul/16/2009:
Memo:
Abbink Daily Report    7 15 09

Weather   hot no rain

Forklift was used on site today.

BTV had 4 men on site today.
Todd B. Dan B. Rolando N. Gerson M.  Remove exes dirt from 
around foundation.

Big Horn had 3 men on site today.
Chip off plaster from block fire wall and paint wall.

Linda C.  came to the site. She would like to look at some 
options on the radius wall in the foyer.  

Todd Bowers


Todd Bowers 7/14/09 entered the following on 16:25:01 Jul/14/2009:
Memo:
Abbink Daily Repot    7 14 09

Weather     Over cast and not to hot.

Forklift used on site today.

BTV had 2 men on site today.
Todd B. Dan B.
Install flashing and siding. Lay out walls and center 
lines for windows and doors. Paint slab where floor heat 
pipes are.

Duane C. on site for about 1 hour. Help lay out windows.

Survey of as built slab was done today.

HHI EXT came and spayed bug juice in the expansion joints 
in the slab. 
Todd Bowers


Todd Bowers 7/13/09 entered the following on 08:26:05 Jul/14/2009:
Memo:
Abbink Daily Repot 7 13 09

Weather hot no rain.

Forklift used on site today.

BTV had 2 men on site today.
Dan B. Todd B.
Lay out walls add doors.

CCS had 2 men on site today.
Mark slab where floor heat pipes are.

Todd Bowers



Todd Bowers 7/10/09 entered the following on 08:20:47 Jul/14/2009:
Memo:
Abbink Daily Report 7 10 09

Heavy rain 

No one on site because of rain.


Todd Bowers 7 9 09 entered the following on 08:18:35 Jul/14/2009:
Memo:
Abbink Daily Repot  7 9 09

Heavy Rain

No one on site because of rain.


Todd Bowers 7/8/09 entered the following on 08:11:13 Jul/14/2009:
Memo:
Abbink Daily Report 7 8 09

Weather     Hot with afternoon rain.

Forklift was used on site today.

BTV had 2 men on site today.
Dan B. Todd B.
Lay out walls and control lines.

We left the site about 3:00 because of rain.

Todd Bowers




Todd Bowers 7/7/09 entered the following on 08:05:08 Jul/14/2009:
Memo:
Abbink Daily Report       7/7/09

Weather hot no rain.

Fork lift used on site today.

BTV had 2 men on site today.
Dan B. Todd B.
Pour concrete and strip forms.

Big Horn had 6 men on site today.
Pour concrete and strip forms.

CCS had 1 man on site today. 
Check water pressure in floor heat pipes.


Todd Bowers


Todd Bowers 7/6/09 entered the following on 07:57:23 Jul/14/2009:
Memo:
Abbink Daily Report      7 6 09

Weather     hot       no rain

Forklift used on site today.

BTV had 2 men on site today. 
Todd B. Dan B.
Cut in and install wall and roof flashing at block fire 
wall over unit 413.

Big Horn.  Came out to site but did not work because of 
rain chances being very high.


Todd Bowers 7/2/09 entered the following on 07:55:45 Jul/14/2009:
Memo:
Abbink Daily Report  7 2 09

Weather hot no rain.

Forklift used on site today.

BTV had on 2 men on site toady.
Dan B. Rolando N.
Removed forms for previous pour. Formed zone 5 and 9 for 
concrete. Cut concrete for safe.

Big Horn had 6 men on site today.
Form up zones 5 and 9 for concrete pour.

CCS had 4 men on site today.
Installed floor heat pipe.

Todd Bowers






Todd Bowers 7/1/09 entered the following on 07:54:15 Jul/14/2009:
Memo:
Abbink Daily Report    7 1 09

Weather hot   no rain

Fork lift used on site today.

BTV had 2 men on site today.
Dan B. Rolando N.
Remove forms. Pour concrete zones 3 and 7. Clean up after 
concrete pour. Run conduit. Set shower drain.

Duane was on site today for about 2 hours. Over see job.

Big Horn had 6 men on site today.
Pour concrete zones 3 and 7.

CCS had 1 man on site today.
Watch gages while concrete is being poured. Set shower 
drain.




Todd Bowers 6/30/09 entered the following on 07:52:27 Jul/14/2009:
Memo:
Abbink Daily Report 6 30 09

Weather   hot no rain

Fork lift used on site today.

BTV had 2 men on site today. 
Dan B. Rolando N.
Form zones 3, 7 and patio.

Duane on site lay out floor heat pipe and over see job.

Big Horn 6 men on site today.
Form zones 3, 7 and patio.

CCS 3 men ½ day.
Install floor heat pipe for zones 3 and 7.


Todd Bowers


Todd Bowers 6/29/09 entered the following on 15:21:59 Jun/30/2009:
Memo:
Abbink Daily Report       6 29 09

Weather    hot    late afternoon rain

Fork lift used today.

BTV had 1 man on site today.
Dan B.
Help with concrete pour. Form work on up coming pours. 
Clean up from concrete pour.

Duane was on site for about 1 hour. Over see concrete pour.

Terry R. on site ½ hour.

CCS had 1 man on site today. Watch pressure gages while 
concrete was being poured.

Big Horn had 6 men on site today. 
Pour concrete. Install steel for patio slab. Install forms 
up coming pours.

HHI Exterminators came out and sprayed bug juice for patio 
slab.

Todd Bowers,



Todd Bowers 6/26/09 entered the following on 11:34:56 Jun/29/2009:
Memo:
Abbink Daily Report  6 26 09 

Weather   hot no rain

Fork lift used on site today.

BTV had 2 men on site today
Dan B. Rolando N.
Installed floor outlet boxes and conduit in dinning room 
and Opel ‘s office. Lay out for safe. Move dirt so we can 
form for patio. Cover ditch for temp service.

CCS had 2 men on site today.
Make up slip joints between slabs. Make up manifold. 
Pressurize floor heat pipe for pour on Monday.

Big Horn had 6 men on site today.
Install steel for patio slab and 3 sections of main house 
slab. Brake down forms from previous pour.

We will pour 3 sections of main house slab and the patio 
on Monday. 

We got the slab inspection today.

Site clean.
Todd Bowers


Todd B 6/25/09 entered the following on 07:13:53 Jun/26/2009:
Memo:
Abbink Daily Report     6 25 09

Weather      HOT   95 no rain

Forklift on site.

BTV had 2 men on site today.
Dan B. Rolando N>
Install forms for3 more floor heat zones.

Duane C. on site for about 2 hours. Over see work.

CCS had 4 men on site today. 
Install floor heat insulation and pipes.

Big Horn had 7 men on site today.
Install form work and steel..

Called in for slab inspection.

Temp service was hooked up today.
The temp phone line was also hooked up this week.


Todd Bowers 6/24/09 entered the following on 08:17:36 Jun/25/2009:
Memo:
Abbink Daily Report  6 24 09 

Weather hot no rain

BTV  had 1 man on site today.
Dan B.
Pour concrete, site clean

Duane C. over see concrete  ( 2 hours)



CCS 1 man (5 hours)
Watch pressure gages on floor heat pipes while the 
concrete was being poured.

Big Horn had 6 men on site today. (6hours)
Pour concrete and finish concrete. 

We also got inspections on the form work, steel, heat 
pipes, and the temp service yesterday. ( 6/23/09 )


Todd Bowers 6/23 09 entered the following on 07:57:33 Jun/25/2009:
Memo:
Abbink Daily Report  6.23.09       

Weather:   hot no rain


BTV- 1 man on site today
Dan B:
Prep for concrete, Wash driveway, install conduit for 
phone & cable.
Duane C: On site to over see. (2 Hours)


CCS- 1 man on site (5 hours)
Check pressure gages on floor heat pipes. Secured floor 
heat pipes & insulate back to manifold. This is important 
to have watched so that we can catch any leaks that might 
occur.


Big Horn- 2 men on site (5 hours)
Prep of concrete

This has been entered by Todd Bowers with information 
received by phone from Dan B.

 
 


Todd Bowers 6/19/09 entered the following on 14:47:12 Jun/24/2009:
Memo:
Abbink Daily Report  6 19 06                    
Weather     Very hot

BTV had 2 men on site today. 
Dan B. Todd B.
Lay out zone for floor heat. Install form borad.

Duane C. on site and helped with floor heat.

CCS had 4 men on site. 
Install insulation and pipe for floor heat. Joe also 
brought the floor boxes to the site today. 

Hans Abbink came by and was on site for about 1 hour. ( He 
wants to make sure he can completely close off the fire 
place so no heat will escape. 


Nathan Klein entered the following on 10:55:12 Jun/23/2009:
Weather Conditions:Sunny Low 90's
Date
:
6/22/2009
Employees Working on site: Dan B. Duane C. Ed E.
Subcontractors on site: CCS,3 men
Visitors: Hans Abbink
Equipment Used: Fork Lift
Urgent Items and Equipment Needed
:
Todd Bowers was injured over the weekend, so Dan Burke is supervising the jobsite along with Duane and Ed.
Possible Change Order Items: none addressed today
Work Completed or Work in Progress notes: Hydronic Heat tubing installtion continues Reinforing Bar installation continues Form work was trued up. 5 inspections were scheduled Temporary power installation continues Reinforing bars were delivered Concrete wire mat material was delivered


Todd B 6/18/09 entered the following on 07:31:38 Jun/19/2009:
Memo:
Abbink Daily Report  6 18 09

BTV had 2 men on site. 
Ban B. Todd B.
We only worked about 2 hours then left because of rain.

CCS 1 man. 
The floor heat pipe and insulation was delivered.

Todd Bowers


Todd B 6/18/09 entered the following on 07:30:35 Jun/19/2009:
Memo:
Abbink Daily Report  6 18 09

BTV had 2 men on site. 
Ban B. Todd B.
We only worked about 2 hours then left because of rain.

CCS 1 man. 
The floor heat pipe and insulation was delivered.

Todd Bowers


Todd B. 6/17/09 entered the following on 06:59:23 Jun/18/2009:
Memo:
Abbink Daily Report 6 17 09

BTV had 3 men on site today.
Gerson M. Dan B. Todd B.
Set ground rods for temp service. Lay out walls on lower 
slab for floor heat. Spread mulch. Take tools to shop. 
Clean up tool storage.


CCS had 1 man on site today. Set ground rods for tenp 
power. Spread mulch. Clean tool storage. Left at 1:00 pm 


Big Horn had 6 men on site today.
Block work on fire wall. Take down scaffolding Install 
soffit plywood unit 413.

Block wall is as complete as we can do until the roof is 
framed. Then we can form the upper bond beam and pour the 
cells,

We took 2 tamps, battery charger, big pipe oven, Straps, 
chain saw, generator and 5 sheet of 4x10sheetrock back to 
the shop today.


Todd B 6/16/09 entered the following on 09:26:57 Jun/17/2009:
Memo:
Abbink Daily Report 6 16 09

BTV had 2 men on site today. 
Gerson M. Todd B. 
Set  temp power. Install conduit for temp power. Clean job 
site. Grade around site. Prime plywood soffit for next 
door unit 413.

CCS had 1 man on site today. 
Same as BTV.

Big Horn had 6 men on site today.

We filled the cells in block fire wall and poured the 
lower bond beam today. This took 3.5 yards of concrete.  
Reck forms for bond beam. Framed soffit back side of the 
unit next door. Wash down driveway. Add 1 ¾ to top of form.

I checked the unit next door while we poured the block 
wall and every thing is good. They still have a flee 
problem. I call Island Pest Control and they said it would 
take 14 days to kill all the flees. 

We poured the lower slab and filled in all cut outs in the 
existing slab. 
23 yard of concrete.

MMC provided us with 220 lf  1 ¾ x 1 ½  wood for the forms 
because of on for seen depth of floor heat insulation. 

Things are looking good here. We have had 2 very good days 
and got a lot of big things completed. I am looking 
forward to the weeks to come. 

Todd Bowers


Todd B 6/12/09 entered the following on 09:25:08 Jun/17/2009:
Memo:
Abbink Daily Report 6 15 09

BTV had 2 men on site today
Gerson M. Todd B. Dig ditch for temp. power. Grade work 
around foundation.Install temp. water. Work on block fire 
wall.


CCS had 1 man on site today. Dig ditch for temp. power. 
Grade around foundation. Install tenp. Water.


Big Horn had 6 men on site today.
Form lower bond beam and install steel. Install plastic 
and steel for 1st pour. Remove block, sheetrock, plywood 
and Bituthene wall.  

HHI EXT came out and sprayed bug juice today. This should 
complete all of the bug juice we will need for the slab.

HAS came out for compaction test today. (PASSRD)

Town of HHI came out and gave of the plumbing inspection 
this morning. (PASSED) They will come back after lunch and 
inspect slab for concrete pour. (PASSED)

We will pour concrete tomorrow morning.


Todd B 6/12/09 entered the following on 09:23:43 Jun/17/2009:
Memo:
Abbink Daily Report 6 12 09

BTV had 2 men on site today.
Gerson M. Todd B. 
Gerson cleaned and helped install sleeves to kitchen 
island.
I worked on fire wall.

CCS had 1 man on site today. Help clean, install sleeves 
for water and ELC to kitchen island.

Big Horn had 6 men on site today.
They worked on removing wall at block fire wall. 
Installing sheetrock, plywood and Bbituthene. 

When we took the wall down we found that the rats eaten 
the flex duct in unit 413. I had CCS come out and make the 
repairs. ( I have pics) I called Ted and let him know what 
I found. CCS will come out next week and do an inspection 
of there AC system. This was by phone with Ted.

We got unit 413 completely water tight today. We will form 
the lower bond beam on Monday. We should be ready to pour 
concrete on Tuesday.

We removed all of our things out of the park and cleaned 
it up good for a party on Saturday.  

Called for a plumbing is slab inspection.


Todd B 6/11/09 entered the following on 09:22:29 Jun/17/2009:
Memo:
Abbink Daily Report 6 11 09

BTV had 2 men on site today.
Gerson M. Todd B.  Gerson went to Capital and dug for 
water meter and temp ELC. I worked on fire wall.

Duane C. was on site for about 1 ½ hours. Worked on taking 
down wall at block fire wall.

CCS had 1 man on site today.
Dig for water meter and ELC temp service.

Big Horn had 6 men on site today.
They helped dig for new water meter and elc. conduit. T&M 
4 men 2 hours
They started work on the bock fire wall. Demo roof and 
remove siding from unit 413.  
TM 4 men all day.

Block Fire Wall

On the back side of the block fire wall we found that the 
siding on the unit next door was nailed to sheetrock and 
no insulation to the attic. We removed the siding and 
sheetrock as far down as we could. We sprayed foam in the 
cracks to help keep bugs out, insulated the wall with R19  
and installed 2 layers of 5/8 type X sheetrock and then  ¾ 
PT plywood and we covered it all with Bituthene 400.

The back side of the fire wall is ready for us to form up 
the bond beam.

PSD came out and installed new 1” meter.

I went into unit 413 to check the fire wall and found that 
the house was completely covered with flees. I called Fred 
and let him know and he is calling Island Pest Control and 
I will let them in the house.  Island Pest Control came 
and sprayed the house today.

Hans was on site today for about 1 hour.


Todd B 6/10/09 entered the following on 09:21:01 Jun/17/2009:
Memo:
Abbink Daily Report 6 10 09

BTV had 2 men on site today. 
Gerson M. Todd B.

Duane C. was on site for about 3 hours today. We worked on 
sleeves for water gas and ELC.

Ed E. was on site today for about 4 hours. We worked on 
the same as Duane.

CCS had 2 men on site today.
They completed the plumbing in the slab. Worked on 
installing sleeves for gas, water and ELC.

Big Horn had 6 men on site today 
They work on tamping , installing steel and form work. 
They left at 1:30.

Raleigh Ward with the PSD came out and located the water 
meter today. In order for us to keep the water meter out 
of the way of side walks and water features we will put it 
about center the garage. BTV is responsible for digging 
it. 

We got plans for block fire wall from Terry today.
We will start wall tomorrow.

Todd Bowers


Todd B 6/9/09 entered the following on 09:19:12 Jun/17/2009:
Memo:
Abbink Daily Report 6 9 09

BTV had 3 men on site today.
Rolando N. Gerson M. Todd B.
Grade work for slab. Help with plumbing. Lay out plumbing. 
Rolando worked about 5 hours installing plumbing. Todd 
worked about 7 hours plumbing.

CCS had 2 men on site today. Steve went home at 10:00.
They worked on rough in plumbing in slab. Plumbing in slab 
is 80% complete.

Big Horn had 6 men on site today.
They worked on form boards, establish grade for 1st pour 
and epoxy steel into old slab.  Grade for slab.

We returned the walk behind concrete saw today. 
Sent our concrete saw to Matt to get repaired. It got ran 
over.

Todd Bowers


Todd B 6/9/09 entered the following on 09:19:03 Jun/17/2009:
Memo:
Abbink Daily Report 6 9 09

BTV had 3 men on site today.
Rolando N. Gerson M. Todd B.
Grade work for slab. Help with plumbing. Lay out plumbing. 
Rolando worked about 5 hours installing plumbing. Todd 
worked about 7 hours plumbing.

CCS had 2 men on site today. Steve went home at 10:00.
They worked on rough in plumbing in slab. Plumbing in slab 
is 80% complete.

Big Horn had 6 men on site today.
They worked on form boards, establish grade for 1st pour 
and epoxy steel into old slab.  Grade for slab.

We returned the walk behind concrete saw today. 
Sent our concrete saw to Matt to get repaired. It got ran 
over.

Todd Bowers


Todd B - 6/8/09 entered the following on 09:16:31 Jun/17/2009:
Memo:
Abbink Daily Report 6 8 09

BTV had 3 men on site today.
Rolando N. Gerson M. Dan B. Todd B.

We installed pipes for entry drainage and some sleeves for 
future plumbing and ELC.
Work on grade around foundation. Lay out walls for the 
plumber. Lay out the elevator.

Duane C. was on site for about 3 hours. He worked on 
plumbing lay out and we talked about putting a 18” 
concrete wall at the garage to house.

Ed E. was on site to go over plumbing.

CCS had two men on site.
They worked on plumbing in the slab.

Big Horn had 6 men on site today.
They poured the block walls with concrete. Installed form 
boards around foundation. Pour drop slab for elevator 
shaft.

Terry R. was on site working on the block fire wall 
drawing.
Linda C. was on site to give me Kitchen plans and some 
plumbing details.

We had an inspection on the block foundation walls    
(passed)

HHI EXT. came out and sprayed bug juice under elevator 
slab.

Todd Bowers


Nathan Klein entered the following on 15:34:40 Jun/05/2009:
Weather Conditions:Sunny high 80's, intermitant showers
Date
:
6/5/2009
Employees Working on site: Duane C. Todd B. Gerson Rolando Dan B.
Subcontractors on site: Big Horn 5 men
Visitors: No visitors today
Equipment Used: Forklift
Urgent Items and Equipment Needed
:
None today
Possible Change Order Items: None today
Work Completed or Work in Progress notes: Blockwork is nearly complete cutting of slab for plumbing is now complete Rebar inspections have been scheduled for Monday, so that the party wall cells can be grouted.


Nathan Klein entered the following on 15:34:33 Jun/05/2009:
Weather Conditions:Sunny high 80's, intermitant showers
Date
:
6/5/2009
Employees Working on site: Duane C. Todd B. Gerson Rolando Dan B.
Subcontractors on site: Big Horn 5 men
Visitors: No visitors today
Equipment Used: Forklift
Urgent Items and Equipment Needed
:
None today
Possible Change Order Items: None today
Work Completed or Work in Progress notes: Blockwork is nearly complete cutting of slab for plumbing is now complete Rebar inspections have been scheduled for Monday, so that the party wall cells can be grouted.


Nathan Klein entered the following on 15:11:22 Jun/05/2009:
Weather Conditions:Sunny high 80's
Date
:
6/3/2009
Employees Working on site: Duane C. Todd B. Gerson Rolando Dan B.
Subcontractors on site: Big Horn 6 men
Visitors: No visitors today
Equipment Used: Forklift and Backhoe
Urgent Items and Equipment Needed
:
none today
Possible Change Order Items: None today
Work Completed or Work in Progress notes: Footing forming Rebar Placement Concrete Scheduled for tomorrow, weather depending Soil poisoning scheduled for the morning, weather depending Rebar. partial footing inspection called for the AM. If weather holds out, footings will be poured tomorrow


Nathan Klein entered the following on 15:03:42 Jun/05/2009:
Weather Conditions:Sunny high 80's
Date
:
6/2/2009
Employees Working on site: Duane C. Todd B. Gerson Rolando Dan B.
Subcontractors on site: Big Horn Construction 5 men
Visitors: No visitors today
Equipment Used: back hoe forklift
Urgent Items and Equipment Needed
:
none today
Possible Change Order Items: none today
Work Completed or Work in Progress notes: Footing excavation and forming party walls dowel placement Dowel rod turnouts Slab cuts for plumbing.


Nathan Klein entered the following on 14:54:16 Jun/05/2009:
Weather Conditions:Sunny high 80's
Date
:
6/2/2009
Employees Working on site: Duane C. Todd B. Gerson Rolando Dan B.
Subcontractors on site: Big Horn Construction 5 men
Visitors: No visitors today
Equipment Used: back hoe forklift
Urgent Items and Equipment Needed
:
none today
Possible Change Order Items: none today
Work Completed or Work in Progress notes: Footing excavation and forming party walls dowel placement Dowel rod turnouts Slab cuts for plumbing.


Nathan Klein entered the following on 14:54:08 Jun/05/2009:
Weather Conditions:Sunny high 80's
Date
:
6/2/2009
Employees Working on site: Duane C. Todd B. Gerson Rolando Dan B.
Subcontractors on site: Big Horn Construction 5 men
Visitors: No visitors today
Equipment Used: back hoe forklift
Urgent Items and Equipment Needed
:
none today
Possible Change Order Items: none today
Work Completed or Work in Progress notes: Footing excavation and forming party walls dowel placement Dowel rod turnouts Slab cuts for plumbing.


Nathan Klein entered the following on 16:31:58 Jun/01/2009:
Weather Conditions:Sunny Low 90's
Date
:
6/1/2009
Employees Working on site: Duane C. Rolando Gerson Todd B. Dan B.
Subcontractors on site: Big Horn Construction 4 men
Visitors: No visitors today
Equipment Used: one backhoe and two compactors
Urgent Items and Equipment Needed
:
2nd layout of the foundation nearly completed
Possible Change Order Items: none today
Work Completed or Work in Progress notes: Filling and compacting continues Foundation layout nearly complete Building permit info updated New water meter ordered Preliminary Landscape drawings received. Owner review is being scheduled.


Nathan Klein entered the following on 16:32:12 May/29/2009:
Weather Conditions:Partly Sunny, in the 80's
Date
:
5/29/2009
Employees Working on site: Duane C Todd B Gerson m Dan B
Subcontractors on site: Big Horn Construction, 3 men
Visitors: No visitors today
Equipment Used: Back hoe Dump truck Forklift
Urgent Items and Equipment Needed
:
The stamped foundation plan was submitted to the town. The town is requiring revised permit application and additional fees due to the additional demolition. SPARB is requiring additional compliance deposits due to the additional demolition. Window schedule changes.
Possible Change Order Items: Additional fees and compliance deposit required for the additional demolition. New foundation layout required due to dimension conflict.
Work Completed or Work in Progress notes: Preparations for Sunday's Annual Baynard Park Party Fill and compact for slabs continues. Batter Boards being erected. Foundation plans submitted to town with additional fees. Additional Compliance deposit given to SPARB. Application and fees submitted for new 1" water meter. Party wall re-inforcing continues. Mechanical and plumbing design continues off-site with filed input.


Nathan klein entered the following on 16:23:35 May/29/2009:
Weather Conditions:sunny mid 80's
Date
:
5/28/2009
Employees Working on site: Duane C Todd B Gerson M Dan B.
Subcontractors on site: Big Horn Construction 3 men
Visitors: Terry Rosser to look for dimension clarification
Equipment Used: Backhoe, forklift, dumptruck
Urgent Items and Equipment Needed
:
Dimension conflict resolved by making the excercise room and the closets on the floor above smaller by the needed dimension. This will be the least impact to the overall design.
Possible Change Order Items: Dimension revision and re-laying out the foundation.
Work Completed or Work in Progress notes: Dimension conflict resolved. all the tile removed from the slab. foundation layout fill and compact for the slab mulch moved party wall re-inforcing started


Nathan Klein entered the following on 13:12:17 May/28/2009:
Weather Conditions:Sunny high 80's, intermitant showers
Date
:
5/27/2009
Employees Working on site: Duane C. Todd B. 2 laborers
Subcontractors on site: None today
Visitors: No visitors today
Equipment Used: one forklift and one backhoe
Urgent Items and Equipment Needed
:
During foundation layout it was determined that there is a discrepency between the plans and the actual physical property. The conflict appears to be in the area when the dinning room is proposed.
Possible Change Order Items: Consequences of the dimensioning conflict are unknown at this time.
Work Completed or Work in Progress notes: Dirt is being brought in and rough graded and compacted. Foundation of the house is being laided out and verified with the drawings. Terry Rosser has submitted foundation plans to be reviewed by Duane C. Preparations off site are being made to have the meter size upgraded. the existing meter does not appear to have a standard back flow preventer.


Nathan Klein entered the following on 12:45:03 May/28/2009:
Weather Conditions:Sunny high 80's, intermitant showers
Date
:
5/26/2009
Employees Working on site: Duane Constantino 2 Laborers Todd Bowers
Subcontractors on site: None today
Visitors: No visitors today
Equipment Used: 1 forklift 1 backhoe
Urgent Items and Equipment Needed
:
None today
Possible Change Order Items: none today
Work Completed or Work in Progress notes: more smaller tree stumps removed. Concrete cutting layout Dirt brought in, rough graded and compacted


Nathan Klein entered the following on 23:35:48 May/25/2009:
Weather Conditions:sunny mid 80's
Date
:
5/25/2009
Employees Working on site: None, Due to Memorial Day Holiday.
Subcontractors on site: None, Due to Memorial Day Holiday.
Visitors: No visitors today
Equipment Used: None, Due to Memorial Day Holiday.
Urgent Items and Equipment Needed
:
None, Due to Memorial Day Holiday.
Possible Change Order Items: None, Due to Memorial Day Holiday.
Work Completed or Work in Progress notes: None, Due to Memorial Day Holiday.


Nathan Klein entered the following on 23:33:49 May/25/2009:
Weather Conditions:Partly Sunny, with evening showers mid 80's
Date
:
5/22/2009
Employees Working on site: Duane C., Todd B., Charlie L., Gerson
Subcontractors on site: none today
Visitors: Charlie York
Equipment Used: Two Fork lifts One back hoe
Urgent Items and Equipment Needed
:
Waste Management still needs to repair brickwork and pavement gouges from improper Dumpster placement. Mr. York stopped on site to discuss repairs to the park and preparations for upcoming events at the park. We are allowed to keep top soil stored on the park property as long as it is screened from view. There are two upcoming events. Sunday May 31st and Sunday June 14th.
Possible Change Order Items: None today. Storing topsoil and screening the stock pile will have some costs involved. These costs should be less than having new topsoil trucked in.
Work Completed or Work in Progress notes: All Tree roots are removed. Driveway has been scrubbed. Rough grading and foundation prep will start after the holiday.


Nathan Klein entered the following on 23:22:52 May/25/2009:
Weather Conditions:Partly cloudy, afternoon showers
Date
:
5/21/2009
Employees Working on site: Duane C., Todd B., Ed E., Gerson. Matt A.
Subcontractors on site: Waste mangement clean-up sub contractor
Visitors: Alan Glassberg & Jason Hubbard to discuss the landscape design and water feature.
Equipment Used: Two forklifts One backhoe
Urgent Items and Equipment Needed
:
A decidous tree fell over during the course of construction, losen soil and rain. Alan will replace the tree as part of the tree mitigation plan. The tree roots are extraordinarily large and required large excavations to get them out.
Possible Change Order Items: none today. The landscape design has not been presented to the owners.
Work Completed or Work in Progress notes: Tree Root excavation Driveway clean-up by Waste Management Landscape design meeting with Alan Glassberg


Nathan Klein entered the following on 23:13:26 May/25/2009:
Weather Conditions:Partly cloudy, afternoon showers
Date
:
5/20/2009
Employees Working on site: Duane C. Ed E. Gerson Todd B. Matt A.
Subcontractors on site: Waste Management
Visitors: South Island PSD
Equipment Used: two forklifts one backhoe
Urgent Items and Equipment Needed
:
An unmarked waterline was discovered during the excavation of a tree route. SI, PSD was called on site to reapir the damaged waterline that ran from a tee in the main line to a hose spigot new the sanitary sewer lift station. Waste Management erroneously dropped of a dumpster in an incorrect location causing damage to the Parking lot and driveway surface. Waste Management was called and Bay 10 cleaned up the immediate debris and mess. Waste management has scheduled a clean-up company for the oil stains and a mason company to repair the bricks. Additional top coating may need done the the driveway.
Possible Change Order Items: None today
Work Completed or Work in Progress notes: Site Clean-up Tree root excavation Waste management clean-up Waterline repair


Nathan Klein entered the following on 22:33:25 May/25/2009:
Weather Conditions:Partly cloudy, afternoon showers
Date
:
5/19/2009
Employees Working on site: Duane C. , Ed E. , Matt A. Gerson, Nicholas
Subcontractors on site: None
Visitors: Hans Abbink
Equipment Used: two forklifts one back hoe
Urgent Items and Equipment Needed
:
An additional piece of equipment was needed due to the extraordinarily large root balls.
Possible Change Order Items: none today
Work Completed or Work in Progress notes: Site clean-up continues Digging out of tree roots continues


Nathan Klein entered the following on 08:35:29 May/19/2009:
Weather Conditions:Raining mid to upper 60's
Date
:
5/18/2009
Employees Working on site: Todd B., Rolando N. and Garrison
Subcontractors on site: none
Visitors: No visitors today
Equipment Used: none
Urgent Items and Equipment Needed
:
Rain Stopped all work today with the exception of some organization of the garage area for neighborhood appeal.
Possible Change Order Items: None today
Work Completed or Work in Progress notes: Rain Stopped all work today with the exception of some organization of the garage area for neighborhood appeal.


Nathan Klein entered the following on 05:47:37 May/18/2009:
Weather Conditions:sunny mid 80's
Date
:
5/15/2008
Employees Working on site: Duane, Nicolas, Jose, Matt, Ed
Subcontractors on site: Waste Co.
Visitors: No visitors today
Equipment Used: Backhoe and Forklift
Urgent Items and Equipment Needed
:
Party wall investigations continue. There does not appear to be any substantial reinforcing in the wall.
Possible Change Order Items: Additional reinforcing to the party wall. Details will be reviewed with the architect and structural engineer.
Work Completed or Work in Progress notes: Demolition is near completion. Debris is being picked up. Site is being protected and waterproofed for the weekend.


Nathan Klein entered the following on 05:41:28 May/18/2009:
Weather Conditions:Partly Cloudy, Afternoon rain high 70's
Date
:
5/14/2009
Employees Working on site: Duane, Nicholas,Jose, Matt, Ed
Subcontractors on site: Waste Co.
Visitors: No visitors today
Equipment Used: Backhoe and forklift
Urgent Items and Equipment Needed
:
Great Care is still being taken with the party wall between 413 and 414. It has become apparent that the chimney used one side of the party wall as its wall. An insufficient amount of reinforcing walls discovered in the party wall. This is being investigated further.
Possible Change Order Items: Additional reinforcing in the party wall will be required.
Work Completed or Work in Progress notes: Demolition of the house continued. Party wall investigation of the reinforcing. Waterproofing of the party wall.


Nathan Klein entered the following on 05:31:42 May/18/2009:
Weather Conditions:Sunny morning, Afternoon Showers mid 80
Date
:
5/13/2009
Employees Working on site: Duane Constantino, Nicholas, Jose, Matt Amelung, Ed Ernst
Subcontractors on site: Waste Co.
Visitors: No visitors today
Equipment Used: Backhoe and forklift 3/4 day.
Urgent Items and Equipment Needed
:
Pictures taken of tie in between 413 and 414. Great care is being taken to make sure the party wall is not disturbed.
Possible Change Order Items: None today
Work Completed or Work in Progress notes: Demolition of the house continues.


Nathan Klein entered the following on 05:23:22 May/18/2009:
Weather Conditions:Partly Cloudy mid 70's
Date
:
5/12/2009
Employees Working on site: Duane Constantino, Ed Ernst, Matt Amelung, 2 Laborers
Subcontractors on site: Bartlett Tree Services Atlantic Surveying
Visitors: No visitors today
Equipment Used: Backhoe and forklift
Urgent Items and Equipment Needed
:
After all the site clearing has been completed. The grades on the site have changed. The pre-construction grade was comprised of a lot of pine straw. The grade dropped once all of the pine straw and unsubstantial soil was removed with the landscaping.
Possible Change Order Items: Grade changes after clearing.
Work Completed or Work in Progress notes: Surveying was completed for tree and topo. Demolition of the house started in the afternoon.


Nathan Klein entered the following on 07:23:49 May/12/2009:
Weather Conditions:Sunny 85 with a strong afternoon storm
Date
:
5/11/2009
Employees Working on site: Ed Ernst, Duane Constantino
Subcontractors on site: Bartlett Tree Services
Visitors: No visitors today
Equipment Used: None today
Urgent Items and Equipment Needed
:
An Afternnon storm halted the stump grinding operations. Work will continue on Tuesday.
Possible Change Order Items: none today
Work Completed or Work in Progress notes: Tree trunks were dropped. The two pines in the OCRM setback were limbed and dropped.


Nathan Klein entered the following on 16:44:44 May/08/2009:
Weather Conditions:Sunny high 80's
Date
:
5/8/2009
Employees Working on site: Matt Amelung Edwin Ernst Duane Constantino
Subcontractors on site: Bartlett Tree Services
Visitors: Hans Abbink Palmetto Electric
Equipment Used: none
Urgent Items and Equipment Needed
:
Duane has continued to contact and leave messages for Richard, from the Town of Hilton Head.
Possible Change Order Items: Opal Abbink and Terry Rosser met to discuss the windows in the upstairs. The originally drawn 7 foot tall windows were unable to meet Design Pressure ratings, so they were reduced to 6 foot tall windows with a transom window above. This will change the head height of the windows. The relationship between the interior door height heights is now different.
Work Completed or Work in Progress notes: All trees were limbed up and ready for dropping on Monday. Palmetto Electric came out and removed the electric meter from the house. They also removed the lines that were connected to the meter base on the house. Ed took pictures of the tree operation and supervised the start-up. Terry Rosser and Opal discussed window changes


Nathan Klein entered the following on 16:23:18 May/08/2009:
Weather Conditions:sunny mid 80's
Date
:
5/7/2009
Employees Working on site: Matt Amelung
Subcontractors on site: none
Visitors: No visitors today
Equipment Used: None used today
Urgent Items and Equipment Needed
:
We received verbal results on the asbestos inspection. The house is clear and there is no evidence of asbestos. We have been cleared to demo the house without remediation.
Possible Change Order Items: none today
Work Completed or Work in Progress notes: Asbestos results confirmed. Tree clearing contracts finalized and insurances confirmed. MEP design meeting minutes published


Nathan Klein entered the following on 16:23:08 May/08/2009:
Weather Conditions:sunny mid 80's
Date
:
5/7/2009
Employees Working on site: Matt Amelung
Subcontractors on site: none
Visitors: No visitors today
Equipment Used: None used today
Urgent Items and Equipment Needed
:
We received verbal results on the asbestos inspection. The house is clear and there is no evidence of asbestos. We have been cleared to demo the house without remediation.
Possible Change Order Items: none today
Work Completed or Work in Progress notes: Asbestos results confirmed. Tree clearing contracts finalized and insurances confirmed. MEP design meeting minutes published


Nathan Klein entered the following on 17:40:27 May/06/2009:
Weather Conditions:Morning Rain with Afternoon overcast
Date
:
5/6/2009
Employees Working on site: Duane Constantino Matt Amelung
Subcontractors on site: None
Visitors: No visitors today
Equipment Used: none
Urgent Items and Equipment Needed
:
BTV is trying to coordinate notification of demo with the the Caswells in unit 413. They are out of town, but we are trying to coordinate inspection access to the home during demolition of 414
Possible Change Order Items: Alan Glassberg request a Tree and Topo survey for the project. This was not done previously, so Nathan scheduled the tree and topo for Monday 5/11, after the tree removal. As part of the tree mitigation plan we are required to fertilize all trees that will remain on site. Bartlett has a proposal for this work. Two additional Trees were added to the list of removed trees. This was stated previously.
Work Completed or Work in Progress notes: Additional tree permits were posted. Additional Plywood was dropped off. Bartlett Tree Services was scheduled for Friday. Atlantic Surveying was scheduled for Monday 5/11. Able Inspections was contacted in regards to an inspection report, See associated e-mails from 5/6/2009.


Nathan Klein entered the following on 17:26:39 May/06/2009:
Weather Conditions:over cast low 80's
Date
:
5/5/2009
Employees Working on site: Matt Amelung
Subcontractors on site: none
Visitors: Able Inspection inc. Also on Monday 5/4/2009
Equipment Used: None
Urgent Items and Equipment Needed
:
none documented today
Possible Change Order Items: Tree Mitigation from the town.
Work Completed or Work in Progress notes: Plywood Protection was added to the Garage floor and curb protection/bridging started. Duane has been in contact with Richard Spruce with the town.


Nathan Klein entered the following on 17:26:26 May/06/2009:
Weather Conditions:over cast low 80's
Date
:
5/5/2009
Employees Working on site: Matt Amelung
Subcontractors on site: none
Visitors: Able Inspection inc. Also on Monday 5/4/2009
Equipment Used: None
Urgent Items and Equipment Needed
:
none documented today
Possible Change Order Items: Tree Mitigation from the town.
Work Completed or Work in Progress notes: Plywood Protection was added to the Garage floor and curb protection/bridging started. Duane has been in contact with Richard Spruce with the town.


Nathan Klein entered the following on 17:20:39 May/06/2009:
Weather Conditions:over cast low 80's
Date
:
5/4/2009
Employees Working on site: Charlie Lovely Duane Constantino Ed Ernst
Subcontractors on site: None
Visitors: No visitors today
Equipment Used: none
Urgent Items and Equipment Needed
:
Asbestos inspection and report is needed before house can be torn down. We received formal approval from the town to remove the previously approved trees.
Possible Change Order Items: The town approved the removal of previously marked trees, based on their jurisdiction over condominium properties. Their approval was based on a tree mitigation plan of a replacing six trees.
Work Completed or Work in Progress notes: Asbestos inspection was started today. Charlie, Ed and Duane coordinated the access to the project. Formal approval was received this afternoon from The Town of Hilton Head to remove 6 trees along with a tree mitigation plan. This document was forwarded to Alan Glassberg (AGLA). AGLA has received a signed contract from the Abbinks and will begin work on the project.


Nathan Klein entered the following on 21:35:00 May/03/2009:
Weather Conditions:Sunny, in the 80's
Date
:
5/1/2009
Employees Working on site: Billy Bowers, Matt Amelung, Duane Constantino
Subcontractors on site: None
Visitors: No visitors today
Equipment Used: Backhoe, full day
Urgent Items and Equipment Needed
:
Tree Removals have been approved
Possible Change Order Items: tear down of entire house cap over existing slab with a new slab.
Work Completed or Work in Progress notes: Bushes and Landscape being removed. Temporary waterline set-up Electrical disconnects have been coordinated between the Abbinks, Bay10 and Palmetto Electric.


Nathan Klein entered the following on 11:27:11 May/01/2009:
Weather Conditions:Sunny, low 80's
Date
:
4/30/2009
Employees Working on site: Matt A. Billy B. Todd B.
Subcontractors on site: Blu-jon Waste Co.
Visitors: The Abbinks and guest.
Equipment Used: Back hoe 1/2 hr
Urgent Items and Equipment Needed
:
Town is still reviewing the trees to be removed.
Possible Change Order Items: Changes in scope discussed with homeowner: Provided that we have town approval, we will demo the entire structure. Reasons for this change are: 1. Only a small amount of the existing structure will remain and be laden with mold and substandard materials. 2. The existing structure will require too much to make square, straight and plumb. 3. The existing structure would be in the way and would prevent machine demolition, which is more cost effective. Another change discussed is capping all existing slabs with one new 4" thick slab. Reasons for this change. 1. There are multiple slabs from previous additions or changes to the house. These slabs have different thicknesses and elevations. 2. The is a large crack between to slab sections from a former addition. A new cap will bridge the crack and seal the slab below(This a concern expressed by Hans).
Work Completed or Work in Progress notes: Plywood Protection placed on the driveway. Protection Fencing being finished. Curb Protection being started. Matt cut out the large bush in the front of the house for Fred Caswell of unit 413. BTV and the Abbinks agreed to do this so Fred could know what to expect prior to leaving town for two weeks. There is a potential for Fred to ask us to move some plants to his property to compensate for the temporary loss of greenscape. The Abbinks agreed to help him and make this as less of an impact as possible. Porta-Jon delivered to the site. Constuction Dumpster Delivered to the site.


Nathan Klein entered the following on 10:20:30 May/01/2009:
Weather Conditions:Sunny, low 80's
Date
:
4/29/2009
Employees Working on site: Billy B. Dan B. Todd B.
Subcontractors on site: none
Visitors: No visitors today
Equipment Used: Back Hoe delivered
Urgent Items and Equipment Needed
:
The Town of Hilton Head is still reviewing the Pine Tree removals that have been approved by SeaPines
Possible Change Order Items: none at this time.
Work Completed or Work in Progress notes: BTV worked on removing appliances, vanities, toilets, lights, shelving, and cabinets. One load taken to Habitat. Matt delivered the backhoe and some old plywood to protect the parking lot and curbs.


Nathan Klein entered the following on 21:27:19 Apr/28/2009:
Weather Conditions:Sunny low 80's
Date
:
4/28/2009
Employees Working on site: Duane Constantino Ed Ernst Todd Bowers Billy Bowers Nicholas Dan 8:30 - 5:00
Subcontractors on site: none
Visitors: No visitors today
Equipment Used: Backhoe was delivered to the site today, but not used.
Urgent Items and Equipment Needed
:
Sarah with the town of Hilton Head is requiring that all trees to be removed on the site must be permitted. We have been instructed by the Town, not to cut down any trees without valid permits. This will delay the start of house demolition.
Possible Change Order Items: none at this time.
Work Completed or Work in Progress notes: More habitat materials were taken from the house and delivered to Habitat for Humanity. Silt Fencing and site protection fencing continued.


Nathan Klein entered the following on 23:50:42 Apr/27/2009:
Weather Conditions:Sunny, in the 80's
Date
:
4/27/2009
Employees Working on site: Duane Constantino Ed Ernst Todd Bowers Billy Bowers Nicholas Dan 11:30 - 5:00
Subcontractors on site: Coastal Carolina Specialty
Visitors: Palmetto Electric for utility locations
Equipment Used: none
Urgent Items and Equipment Needed
:
The two pine trees that are within the OCRM setback have been verbally approved for removal. The cherry tree was denied and shall remain.
Possible Change Order Items: The cost to remove two additional pine trees.
Work Completed or Work in Progress notes: Protection fencing is being installed along the bulkhead. Silt fencing has started and will resume. Appliances, doors, and cabinet fronts have been removed and are awaiting Habitat for humanity pick-up.


Nathan Klein entered the following on 23:32:54 Apr/27/2009:
Weather Conditions:Sunny, low 80's
Date
:
4/24/2009
Employees Working on site: Nathan Klein
Subcontractors on site: Coastal Carolina Specialty, 3 men
Visitors: Public Utility Location Service
Equipment Used: None
Urgent Items and Equipment Needed
:
Trees were marked with green ribbon for town approval. The town is scheduled to review within the next few days.
Possible Change Order Items: Possible additional Tree removal
Work Completed or Work in Progress notes: Two Pines and one Cherry Tree were marked woth Green Ribbon for Town review. Coastal Carolina Specialty was removing the heat pumps and air handlers from the house. Utility Location Continued.


Nathan Klein entered the following on 22:48:21 Apr/27/2009:
Weather Conditions:Sunny, low 80's
Date
:
4/23/2009
Employees Working on site: None
Subcontractors on site: None
Visitors: No visitors today
Equipment Used: None
Urgent Items and Equipment Needed
:
Terry Rosser is submitting an application to The Town of Hilton Head to have three trees removed from with-in the OCRM setback. 2 pines and one cherry tree
Possible Change Order Items: None
Work Completed or Work in Progress notes: Off-site preparations continue for the mobilization. HVAC technicians are scheduled for tomorrow. Terry Rosser has submitted an application to have three trees removed. Initially, the application was for two pines. The Abbinks have requested that the cheery tree be added to the application.


Nathan Klein entered the following on 22:38:03 Apr/27/2009:
Weather Conditions:Sunny, High 70's
Date
:
4/22/2009
Employees Working on site: None
Subcontractors on site: None
Visitors: No visitors today
Equipment Used: None
Urgent Items and Equipment Needed
:
none
Possible Change Order Items: None today
Work Completed or Work in Progress notes: The building permit was picked up from The Town of Hilton Head. The building permit was then picked up from SeaPines plantation. The Palmetto Utility Protection Service was scheduled on-line 4/23. The Utility location and stakeout will take 3 working days. Digging work can begin on the 4/27.


Nathan Klein entered the following on 22:18:28 Apr/27/2009:
Weather Conditions:Sunny, High 70's
Date
:
4/21/2009

Employees Working on site: Nathan Klein
Subcontractors on site: None
Visitors: Opal and Hans Abbink, Owners Linda Conklin, Interior Designer J. Terrell Rosser, Architect Patrick Rooney, Landscape Architect Alan Glassberg, Landscape Architect
Equipment Used: None
Urgent Items and Equipment Needed
:
There was a discussion to remove additional trees that are within the OCRM setback.
Possible Change Order Items: costs cannot be determined until tress are approved or denied.
Work Completed or Work in Progress notes:
Meetings were held with two prospective Landscape Architects to meet the Abbink’s and discuss a potential working relationship.
Attendees from the project team were;Opal and Hans Abbink, Terry Rosser, Linda Conklin, and Nathan Klein.
Tuesday April 21st at 414c Baynard Cove Club 1:10pm to 4:05 pm Some Items that were discussed with the entire team and both Landscape Architects that will be consequential:
• All the existing plants and bushes will be removed from the property, with the exception of plantings that are attached to the walls, the bamboo, and anything with in the OCRM 20’ setback. (The face of the bulkhead being the OCRM line).
• The water feature shown on the plans will be a fountain out front. They would like to use and existing fountain from their current home, if possible. The Abbink’s have agreed to make it accessible for viewing and measurements.
• It was discussed and is evident from the stakeout of the house, that equipment access around the house is very limited. The rear and right side cannot be accessed past Opal’s new office. This work will have to be completed with scaffolding and hand moving of materials.
• The large bushes, that have grown as large as trees, need to be removed if they are within the property. The bush closest to the house provides a great deal of shade to the neighbors, so its removal will be consequential to the neighbors. Opal is going to discuss this with Sandy Caswell (her neighbor 413C) and at least give her a heads up and see how she feels about it being removed. The other bush near the parking lot is on the Caswell’s property so the limb will need to be removed that encroaches the property. Opal will be discussing this with the Caswell’s.
• There are two pine trees and a cherry tree that are with-in the OCRM setback that have not been approved for removal, but the Abbink’s would like to have them considered for removal. This would require a review from The Town of Hilton Head. It was discussed that there would be a potential requirement to either plant new specimen trees or provide new trees to the SeaPines tree bank. It was decided to have a tree company look at the trees and provide an arborists opinion as what to do with the trees. The tree removal company and/or arborist would help coordinate the approvals and permitting with the Town and SeaPines. • Opal mentioned that Baynard Cove Club will be doing renovations on their Tennis Courts and Pool Area. A sketch that she saw had a stone sidewalk going from the Tennis area to the Park. Opal will provide a sketch as there may be consideration that can be made to benefit the Abbink’s and the Baynard Cove Club.
• There was a discussion about leaving the wood decking that is in the OCRM setback and adding wood elements throughout the Hardscapes to tie it in with the overall design.
• The large planting pots will be stored at the edge of the property out of harms way during the construction.
• Hans Abbink would like to have a refrigerator in the Garage. Terry Rosser will coordinate a space for it in the garage design. Meeting with Patrick Rooney:
• Introductions were made and the basic scope of work for the project was discussed.
• Patrick explained how he typically functions with providing a design and getting the design approved by The SeaPines Architectural Review Board and presenting it to the Town Of Hilton Head.
• Patrick explained that he is not responsible for the installation, but could help provide names of Landscape companies for the planting and maintenance.
• Patrick will make arrangements to visit their current home to see Opals current landscape and view the fountains.
• The Abbink’s will be provided with a proposal for his services. Meeting with Alan Glassberg:
• Introductions were made and the basic scope of work for the project was discussed.
• Alan presented some preliminary design Ideas that he had worked on prior to the meeting.
• Alan discussed the front entry, water feature locations, and a curved bench.
• There was a discussion of the trees being removed in the OCRM setback area and Alan’s opinion. Alan expressed a concern for the vulnerability of pine trees and lightning strikes jumping to the house. Alan also discussed cherry trees and the debris problems that plague these particular trees throughout the year.
• It was decided to have a tree company look at the trees and provide an arborists opinion as what to do with the trees. The tree removal company and/or arborist would help coordinate the approvals and permitting with the Town and SeaPines.
• Alan felt like he could come up with a workable design that would allow the Abbink’s to keep the wood deck and incorporate it into the overall design. Since the wood deck is in the OCRM setback it can remain undisturbed, bit cannot be replaced. If the Abbink’s remove the deck it would have to return to a native area. The Abbink’s will await a preliminary design to decide.
• There was a discussion of the how to proceed with the approval process. Alan is proposing that a preliminary design be presented to the Town and SeaPines that incorporates all the Abbink’s wishes. Adjustments can be made from their feedback allowing the final design and approval to proceed expeditiously.
• Alan will provide a proposal for his services. He too discussed being a Landscape Architect that would provide a design, help coordinate the approvals, and provide names of Landscaping Companies. Please forward any additions or corrections to these notes that may have be overlooked or need clarification.


Nathan Klein entered the following on 21:53:32 Apr/27/2009:
Weather Conditions:Sunny, low 80's
Date
:
4/20/2009
Employees Working on site: Duane Constantino, Nathan Klein
Subcontractors on site: None
Visitors: Bob Walker
Equipment Used: none
Urgent Items and Equipment Needed
:
Permission needs obtained from the Baynard Park board of directors for access to the park for dumpster, equipment and parking. We are to contact Jim Dougherty.
Possible Change Order Items: none
Work Completed or Work in Progress notes: Job site meeting was held to discuss site access, landscaping demolition, and association guidlines for construction work.